Sample data. These listings are fictional examples used to demonstrate the site. No MLS or board data is displayed.

Shaun Lovell, Real Estate SalespersonRight At Home Realty, Brokerage289-813-3318

Toronto address · Ward 14, Toronto-Danforth

101 Commissioners St

The City of Toronto has 93 building permits since 2017 (45 still open) and 5 Committee of Adjustment files on record for this address.

Building permits

Every permit the City lists for this address since 2017, and any still open from before, newest first.

  • Temporary structure · Other

    Revision 14 - Proposal to extend removal date REVISION 11 - temporary workshop/flex area to be included as part of the Pinewood StudioProposal emporary One-Storey Communications and Broadcasting Establishment building (temporary workshop/flex area) to be included as part of the Pinewood Toronto Studios complex.Revision #8: To allow for a 6 month extension for temporary structure to be dismantled Dec 1, 2022

    Applied Jun 4, 2026 · issued Jul 7, 2026 · Permit 18 250917 TPS (revision 14)

    Revision issued
  • Temporary structure · Other

    Revision 14: Proposal to extend removal date. New Removal date: December 1, 2026REVISION 11 - temporary workshop/flex area to be included as part of the Pinewood StudioProposal to construct an addition to the temporary communication and broadcasting structure approved under permit 18-250917 TPS 00. To be erected June 1, 2024 and dismantled December 1, 2024.

    Applied Jun 4, 2026 · issued Jul 6, 2026 · Permit 19 122401 TPS (revision 14)

    Revision issued
  • Temporary structure · Other

    Revision 13: Proposal to extend removal date. New Removal date: REVISION 11 - temporary workshop/flex area to be included as part of the Pinewood StudioProposal to construct an addition to the temporary communication and broadcasting structure approved under permit 18-250917 TPS 00. To be erected June 1, 2024 and dismantled December 1, 2024.

    Applied Jan 7, 2026 · issued Jan 28, 2026 · Permit 19 122401 TPS (revision 13)

    Revision issued
  • Temporary structure · Other

    Revision 12: Proposal to extend removal date. New Removal date: December 31, 2025REVISION 11 - temporary workshop/flex area to be included as part of the Pinewood StudioProposal to construct an addition to the temporary communication and broadcasting structure approved under permit 18-250917 TPS 00. To be erected June 1, 2024 and dismantled December 1, 2024.

    Applied Jul 21, 2025 · issued Aug 19, 2025 · Permit 19 122401 TPS (revision 12)

    Revision issued
  • Temporary structure · Other

    Revision 13 - Proposal to extend removal date REVISION 11 - temporary workshop/flex area to be included as part of the Pinewood StudioProposal emporary One-Storey Communications and Broadcasting Establishment building (temporary workshop/flex area) to be included as part of the Pinewood Toronto Studios complex.Revision #8: To allow for a 6 month extension for temporary structure to be dismantled Dec 1, 2022

    Applied Jul 21, 2025 · issued Feb 17, 2026 · Permit 18 250917 TPS (revision 13)

    Revision issued
  • Temporary structure · Other

    Revision 12: Proposal to extend removal date.REVISION 11 - temporary workshop/flex area to be included as part of the Pinewood StudioProposal to construct an addition to the temporary communication and broadcasting structure approved under permit 18-250917 TPS 00. To be erected June 1, 2024 and dismantled December 1, 2024.

    Applied Jan 6, 2025 · issued Feb 12, 2025 · Permit 19 122401 TPS (revision 11)

    Revision issued
  • Temporary structure · Other

    Revision 12 - Proposal to extend removal date REVISION 11 - temporary workshop/flex area to be included as part of the Pinewood StudioProposal emporary One-Storey Communications and Broadcasting Establishment building (temporary workshop/flex area) to be included as part of the Pinewood Toronto Studios complex.Revision #8: To allow for a 6 month extension for temporary structure to be dismantled Dec 1, 2022

    Applied Jan 3, 2025 · issued Feb 14, 2025 · Permit 18 250917 TPS (revision 12)

    Revision issued
  • Temporary structure · Other

    REVISION 11 - temporary workshop/flex area to be included as part of the Pinewood StudioProposal to construct an addition to the temporary communication and broadcasting structure approved under permit 18-250917 TPS 00. To be erected June 1, 2024 and dismantled December 1, 2024.

    Applied Sep 4, 2024 · issued Jan 6, 2025 · Permit 19 122401 TPS (revision 10)

    Revision issued
  • Temporary structure · Other

    REVISION 11 - temporary workshop/flex area to be included as part of the Pinewood StudioProposal emporary One-Storey Communications and Broadcasting Establishment building (temporary workshop/flex area) to be included as part of the Pinewood Toronto Studios complex.Revision #8: To allow for a 6 month extension for temporary structure to be dismantled Dec 1, 2022

    Applied Sep 4, 2024 · issued Sep 26, 2024 · Permit 18 250917 TPS (revision 11)

    Revision issued
  • Temporary structure · Other

    REV; 10 Temporary One-Storey Communications and Broadcasting Establishment building (temporaryworkshop/flex area) to be included as part of the Pinewood Toronto Studios complex.Revision # 09: To extend the time from December 2022 to June 2023. Proposal emporary One-Storey Communications and Broadcasting Establishment building (temporary workshop/flex area) to be included as part of the Pinewood Toronto Studios complex.Revision #8: To allow for a 6 month extension for temporary structure to be dismantled Dec 1, 2022

    Applied Oct 24, 2023 · issued Nov 22, 2023 · Permit 18 250917 TPS (revision 10)

    Revision issued
  • Temporary structure · Other

    REV; 09 ; Temporary One-Storey Communications and Broadcasting Establishment building (temporaryworkshop/flex area) to be included as part of the Pinewood Toronto Studios complex.Revision 08: To extend the removal date until June 2023Revision #7: To allow for a 6 month extension for temporary structure to be dismantled Dec1, 2022

    Applied Oct 24, 2023 · issued Nov 22, 2023 · Permit 19 122401 TPS (revision 09)

    Revision issued
  • Temporary structure · Other

    Revision 08: To extend the removal date until June 2023Revision #7: To allow for a 6 month extension for temporary structure to be dismantled Dec1, 2022

    Applied Mar 28, 2023 · issued May 25, 2023 · Permit 19 122401 TPS (revision 08)

    Revision issued
Show 81 more permits
  • Temporary structure · Other

    Revision # 09: To extend the time from December 2022 to June 2023. Proposal emporary One-Storey Communications and Broadcasting Establishment building (temporary workshop/flex area) to be included as part of the Pinewood Toronto Studios complex.Revision #8: To allow for a 6 month extension for temporary structure to be dismantled Dec 1, 2022

    Applied Mar 28, 2023 · issued May 23, 2023 · Permit 18 250917 TPS (revision 09)

    Revision issued
  • Plumbing

    Revision 01 - Addition of a domestic cold water makeup provision for the site irrigation system.Plumbing - Proposed to construct 3 Storey Building comprised of 3 sound stages for Media Production, two support workshops, and office.

    Applied Jan 10, 2023 · issued Feb 21, 2023 · completed May 18, 2023 · Permit 20 197292 PLB (revision 01)

    Closed
  • Temporary structure · Other

    Revision #7: To allow for a 6 month extension for temporary structure to be dismantled Dec1, 2022

    Applied May 16, 2022 · issued Jun 14, 2022 · Permit 19 122401 TPS (revision 07)

    Revision issued
  • Temporary structure · Other

    Revision #8: To allow for a 6 month extension for temporary structure to be dismantled Dec 1, 2022

    Applied May 16, 2022 · issued Jun 16, 2022 · Permit 18 250917 TPS (revision 08)

    Revision issued
  • Designated structure · Sign building permit related

    To erect and display eleven first party non-illuminated wall signs, displaying static copy.*****VARIOUS IDENTIFICATION SIGNS*****

    Applied Mar 23, 2022 · issued Jun 17, 2022 · completed Nov 6, 2025 · Permit 22 126082 DST

    Closed
  • Temporary structure · Other

    Revision #6: To allow for a 6 month extension for temporary structure to be dismantled June1, 2022

    Applied Nov 30, 2021 · issued Feb 1, 2022 · Permit 19 122401 TPS (revision 06)

    Revision issued
  • Temporary structure · Other

    Revision #7: To allow for a 6 month extension for temporary structure to be dismantled June 1, 2022

    Applied Nov 30, 2021 · issued Feb 2, 2022 · Permit 18 250917 TPS (revision 07)

    Revision issued
  • New building

    Revision 02 - Revisions to the ground floor slab and vapour intrusion systemRevision - change to masonry construction from using precast concrete wall panels as demising walls between the stage areas, stages and office, and the stages and workshop area - Phase 4

    Applied Aug 19, 2021 · issued Oct 29, 2021 · Permit 20 197292 BLD (revision 02)

    Revision issued
  • New building

    REVISION 2 - revisions to the ground floor slab and vapour intrusion system (see attached cover letter)Phase 5A and 5B: Proposal to build a new one storey medium hazard industrial building (group F2) for communications and broadcasting establishment. A single story building, comprised of 2 sound stages for media production and amenity spaces(washrooms and various rooms that support the sound stages). Building construction will consist ofpoured concrete foundations, steel superstructure, precast concrete walls for sound stages, insulatedmetal panels walls for amenity area. All areas of the bui…

    Applied Aug 13, 2021 · issued Oct 14, 2021 · Permit 20 148505 BLD (revision 02)

    Revision issued
  • New building

    Revision - change to masonry construction from using precast concrete wall panels as demising walls between the stage areas, stages and office, and the stages and workshop area - Phase 4

    Applied May 29, 2021 · issued Jul 2, 2021 · Permit 20 197292 BLD (revision 01)

    Revision issued
  • Temporary structure · Other

    Revision #6: To allow for a 6 month extension for temporary structure to be dismantled December 1, 2021

    Applied May 26, 2021 · issued Jun 2, 2021 · Permit 18 250917 TPS (revision 06)

    Revision issued
  • Temporary structure · Other

    Revision #5: To allow for a 6 month extension for temporary structure to be dismantled December 1, 2021Revision #4: To allow for a 6 month extension for temporary structure to be dismantled June 1, 2021Revision #3: to allow for a 6 month extension for temporary structure to be dismantled December 1, 2020

    Applied May 26, 2021 · issued Jun 2, 2021 · Permit 19 122401 TPS (revision 05)

    Revision issued
  • New building

    Revision 01: change of precast walls into masonry walls in select locations.

    Applied May 8, 2021 · issued May 27, 2021 · Permit 20 148505 BLD (revision 01)

    Revision issued
  • Fire and security upgrade

    FS - Sprinkler Shop Drawing - Proposed to construct 3 Storey Building comprised of 3 sound stages for Media Production, two support workshops, and office. (phase 4 part of SPA)

    Applied Dec 18, 2020 · completed Oct 8, 2021 · Permit 20 197292 FSU

    Closed
  • Temporary structure · Other

    Revision #4: To allow for a 6 month extension for temporary structure to be dismantled June 1, 2021Revision #3: to allow for a 6 month extension for temporary structure to be dismantled December 1, 2020

    Applied Nov 19, 2020 · issued Nov 30, 2020 · Permit 19 122401 TPS (revision 04)

    Revision issued
  • Temporary structure · Other

    Revision #5: To allow for a 6 month extension for temporary structure to be dismantled June 1, 2021 Revision #4: to allow for a 6 month extension for temporary structure to be dismantled December 1, 2020

    Applied Nov 19, 2020 · issued Nov 30, 2020 · Permit 18 250917 TPS (revision 05)

    Revision issued
  • Drains and site services

    Drain - Proposed to construct 3 Storey Building comprised of 3 sound stages for Media Production, two support workshops, and office.

    Applied Sep 24, 2020 · issued Jan 8, 2021 · completed May 18, 2023 · Permit 20 197292 DRN

    Closed
  • Plumbing

    Plumbing - Proposed to construct 3 Storey Building comprised of 3 sound stages for Media Production, two support workshops, and office.

    Applied Sep 24, 2020 · issued Jan 8, 2021 · completed May 18, 2023 · Permit 20 197292 PLB

    Closed
  • Heating and ventilation

    HVAC - Proposed to construct 3 Storey Building comprised of 3 sound stages for Media Production, two support workshops, and office.

    Applied Sep 24, 2020 · issued Jan 8, 2021 · Permit 20 197292 HVA

    Inspections under way
  • New building

    Phase 2B - Proposed construction of a new 1-storey industrial building [2,266sm] for communications and broadcasting establishment.. *Pinewood Toronto Studios*

    Applied Sep 23, 2020 · completed Oct 30, 2020 · Permit 20 197579 BLD

    Cancelled
  • Drains and site services · Inside and outside drains

    Drain - Phase 2B - Proposed construction of a new 1-storey industrial building [2,266sm] for communications and broadcasting establishment.. *Pinewood Toronto Studios*

    Applied Sep 23, 2020 · completed Oct 30, 2020 · Permit 20 197579 STS

    Cancelled
  • Drains and site services

    Drain - Phase 2B - Proposed construction of a new 1-storey industrial building [2,266sm] for communications and broadcasting establishment.. *Pinewood Toronto Studios*

    Applied Sep 23, 2020 · completed Oct 30, 2020 · Permit 20 197579 DRN

    Cancelled
  • Plumbing

    Plumbing - Phase 2B - Proposed construction of a new 1-storey industrial building [2,266sm] for communications and broadcasting establishment.. *Pinewood Toronto Studios*

    Applied Sep 23, 2020 · completed Oct 30, 2020 · Permit 20 197579 PLB

    Cancelled
  • Heating and ventilation

    HVAC - Phase 2B - Proposed construction of a new 1-storey industrial building [2,266sm] for communications and broadcasting establishment.. *Pinewood Toronto Studios*

    Applied Sep 23, 2020 · completed Oct 30, 2020 · Permit 20 197579 HVA

    Cancelled
  • New building

    Proposed to construct 3 Storey Building comprised of 3 sound stages for Media Production, two support workshops, and office. (phase 4 part of SPA)

    Applied Sep 22, 2020 · issued Jan 8, 2021 · Permit 20 197292 BLD

    Inspections under way
  • Fire and security upgrade

    FS - Sprinkler Shop Drawing - Proposal to build a new one storey medium hazard industrial building (group F2) for communications and broadcasting establishment. A single story building, comprised of 2 sound stages for media production and amenity spaces(washrooms and various rooms that support the sound stages). Building construction will consist ofpoured concrete foundations, steel superstructure, precast concrete walls for sound stages, insulatedmetal panels walls for amenity area. All areas of the building will be fully sprinklered and with a multizone hvac system. The entire building pad…

    Applied Jul 15, 2020 · completed Nov 24, 2021 · Permit 20 148505 FSU

    Closed
  • New building

    Phase 5A and 5B: Proposal to build a new one storey medium hazard industrial building (group F2) for communications and broadcasting establishment. A single story building, comprised of 2 sound stages for media production and amenity spaces(washrooms and various rooms that support the sound stages). Building construction will consist ofpoured concrete foundations, steel superstructure, precast concrete walls for sound stages, insulatedmetal panels walls for amenity area. All areas of the building will be fully sprinklered and with a multizone hvac system. The entire building pad will have an…

    Applied May 25, 2020 · issued Aug 11, 2020 · Permit 20 148505 BLD

    Inspections under way
  • Heating and ventilation

    HVAC - Proposal to build a new one storey medium hazard industrial building (group F2) for communications and broadcasting establishment. A single story building, comprised of 2 sound stages for media production and amenity spaces(washrooms and various rooms that support the sound stages). Building construction will consist ofpoured concrete foundations, steel superstructure, precast concrete walls for sound stages, insulatedmetal panels walls for amenity area. All areas of the building will be fully sprinklered and with a multizone hvac system. The entire building pad will have an under-slab…

    Applied May 25, 2020 · issued Sep 15, 2020 · Permit 20 148505 HVA

    Inspections under way
  • Drains and site services

    Drain - Proposal to build a new one storey medium hazard industrial building (group F2) for communications and broadcasting establishment. A single story building, comprised of 2 sound stages for media production and amenity spaces(washrooms and various rooms that support the sound stages). Building construction will consist ofpoured concrete foundations, steel superstructure, precast concrete walls for sound stages, insulatedmetal panels walls for amenity area. All areas of the building will be fully sprinklered and with a multizone hvac system. The entire building pad will have an under-sla…

    Applied May 25, 2020 · issued Aug 11, 2020 · Permit 20 148505 DRN

    Permit issued
  • Drains and site services · Inside and outside drains

    Drain - Proposal to build a new one storey medium hazard industrial building (group F2) for communications and broadcasting establishment. A single story building, comprised of 2 sound stages for media production and amenity spaces(washrooms and various rooms that support the sound stages). Building construction will consist ofpoured concrete foundations, steel superstructure, precast concrete walls for sound stages, insulatedmetal panels walls for amenity area. All areas of the building will be fully sprinklered and with a multizone hvac system. The entire building pad will have an under-sla…

    Applied May 25, 2020 · issued Jul 6, 2020 · Permit 20 148505 STS

    Inspections under way
  • Plumbing

    Plumbing - Proposal to build a new one storey medium hazard industrial building (group F2) for communications and broadcasting establishment. A single story building, comprised of 2 sound stages for media production and amenity spaces(washrooms and various rooms that support the sound stages). Building construction will consist ofpoured concrete foundations, steel superstructure, precast concrete walls for sound stages, insulatedmetal panels walls for amenity area. All areas of the building will be fully sprinklered and with a multizone hvac system. The entire building pad will have an under-…

    Applied May 25, 2020 · issued Aug 11, 2020 · Permit 20 148505 PLB

    Inspections under way
  • Temporary structure · Other

    Revision #4: to allow for a 6 month extension for temporary structure to be dismantled December 1, 2020

    Applied May 7, 2020 · issued May 28, 2020 · Permit 18 250917 TPS (revision 04)

    Revision issued
  • Temporary structure · Other

    Revision #3: to allow for a 6 month extension for temporary structure to be dismantled December 1, 2020

    Applied May 7, 2020 · issued May 28, 2020 · Permit 19 122401 TPS (revision 03)

    Revision issued
  • Temporary structure · Other

    Revision #3: to allow for a 6 month extension for temporary structure to be dismantled June 1, 2020.

    Applied Nov 20, 2019 · issued Dec 5, 2019 · Permit 18 250917 TPS (revision 03)

    Revision issued
  • Temporary structure · Other

    Revision #2: to allow for a 6 month extension for temporary structure to be dismantled June 1, 2020.

    Applied Nov 20, 2019 · issued Dec 5, 2019 · Permit 19 122401 TPS (revision 02)

    Revision issued
  • Temporary structure · Other

    Revision #2: to allow for a 6 month extension for temporary structure to be dismantled Decemeber 1, 2019.

    Applied May 28, 2019 · issued Jun 21, 2019 · Permit 18 250917 TPS (revision 02)

    Revision issued
  • Temporary structure · Other

    Revision #1: to allow for a 6 month extension for temporary structure to be dismantled Decemeber 1, 2019

    Applied May 28, 2019 · issued Jul 2, 2019 · Permit 19 122401 TPS (revision 01)

    Revision issued
  • Fire and security upgrade · Sprinklers

    Stand alone sprinkler permit associated with 19-122401 TPS - Proposal to construct an addition to the temporary communication and broadcasting structure approved under permit 18-250917 TPS 00.

    Applied May 24, 2019 · issued Jun 27, 2019 · completed Aug 22, 2019 · Permit 19 158815 FSU

    Closed
  • Drains and site services · Site service

    Site Service Permit for a Temporary Structure to be used for communication and broadcasting.

    Applied Mar 29, 2019 · issued Mar 29, 2019 · completed Apr 18, 2019 · Permit 19 132500 STS

    Closed
  • Heating and ventilation

    HVAC - Proposal to construct a temporary communication and broadcasting establishment to be erected , March 29, 2019 and dismantled Sept 29, 2019.

    Applied Mar 6, 2019 · issued May 10, 2019 · completed Aug 14, 2019 · Permit 19 122401 HVA

    Closed
  • Temporary structure · Other

    Proposal to construct an addition to the temporary communication and broadcasting structure approved under permit 18-250917 TPS 00. To be erected March 29, 2019 and dismantled June 1, 2019.

    Applied Mar 6, 2019 · issued May 9, 2019 · Permit 19 122401 TPS

    Inspections under way
  • Plumbing

    Plumbing - Proposal to construct a temporary communication and broadcasting structure to be erected March 29, 2019 and dismantled Sept 29, 2019.

    Applied Mar 6, 2019 · issued May 10, 2019 · completed Aug 21, 2020 · Permit 19 122401 PLB

    Closed
  • Temporary structure · Other

    REV01: Revision to permit 18-250917. Proposal to install ordiary group 2 fire protection. Proposal to construct a temporary communication and broadcasting establishment to be erected December 1st 2018, and dismantled June 1st, 2019.

    Applied Feb 27, 2019 · issued Apr 26, 2019 · Permit 18 250917 TPS (revision 01)

    Revision issued
  • Heating and ventilation

    HVAC - Proposed interior alterations to add a mezzanine within an existing film studio space on the ground floor.

    Applied Feb 8, 2019 · issued Feb 11, 2019 · Permit 19 106149 HVA

    Permit issued
  • Addition or alteration · Interior alterations

    Proposed interior alterations to add a mezzanine within an existing film studio space on the ground floor.

    Applied Jan 18, 2019 · issued Feb 11, 2019 · Permit 19 106149 BLD

    Inspections under way
  • Plumbing

    Plumbing - Proposal to construct a temporary communication and broadcasting establishment to be erected December 1st 2018, and dismantled June 1st, 2018.

    Applied Nov 1, 2018 · issued Jan 9, 2019 · completed Apr 18, 2019 · Permit 18 250917 PLB

    Closed
  • Temporary structure · Other

    Proposal to construct a temporary communication and broadcasting establishment to be erected December 1st 2018, and dismantled June 1st, 2019.

    Applied Nov 1, 2018 · issued Jan 9, 2019 · Permit 18 250917 TPS

    Inspections under way
  • Heating and ventilation

    HVAC - Proposal to construct a temporary communication and broadcasting establishment to be erected December 1st 2018, and dismantled June 1st, 2018.

    Applied Nov 1, 2018 · issued Jan 9, 2019 · completed Apr 17, 2019 · Permit 18 250917 HVA

    Closed
  • Plumbing

    Plumbing - BUILDING C - Proposal to construct a 1 storey broadcasting & communications establishment. 101 Commissioners St and 1 & 17 Basin St.

    Applied May 15, 2018 · issued Aug 27, 2018 · completed Nov 15, 2018 · Permit 18 159319 PLB

    Closed
  • Drains and site services

    Drain - BUILDING C - Proposal to construct a 1 storey broadcasting & communications establishment. 101 Commissioners St and 1 & 17 Basin St.

    Applied May 15, 2018 · issued Aug 27, 2018 · completed Oct 30, 2018 · Permit 18 159319 DRN

    Closed
  • Drains and site services · Inside and outside drains

    Drain - BUILDING C - Proposal to construct a 1 storey broadcasting & communications establishment. 101 Commissioners St and 1 & 17 Basin St.

    Applied May 15, 2018 · issued Aug 31, 2018 · completed Oct 30, 2018 · Permit 18 159319 STS

    Closed
  • New building

    BUILDING C - Proposal to construct a 1 storey broadcasting & communications establishment. 101 Commissioners St and 1 & 17 Basin St.

    Applied May 15, 2018 · issued Aug 27, 2018 · completed Oct 19, 2018 · Permit 18 159319 BLD

    Closed
  • Heating and ventilation

    HVAC - BUILDING C - Proposal to construct a 1 storey broadcasting & communications establishment. 101 Commissioners St and 1 & 17 Basin St.

    Applied May 15, 2018 · issued Aug 27, 2018 · completed Oct 12, 2018 · Permit 18 159319 HVA

    Closed
  • Drains and site services · Inside and outside drains

    Drain - BUILDING B - Proposal to construct a 1 storey broadcasting & communications establishment. 101 Commissioners St and 1 & 17 Basin St.

    Applied May 8, 2018 · issued Aug 31, 2018 · completed Oct 30, 2018 · Permit 18 155080 STS

    Closed
  • Heating and ventilation

    HVAC - BUILDING B - Proposal to construct a 1 storey broadcasting & communications establishment. 101 Commissioners St and 1 & 17 Basin St.

    Applied May 8, 2018 · issued Aug 27, 2018 · completed Oct 12, 2018 · Permit 18 155080 HVA

    Closed
  • New building

    BUILDING B - Proposal to construct a 1 storey broadcasting & communications establishment. 101 Commissioners St and 1 & 17 Basin St.

    Applied May 8, 2018 · issued Aug 27, 2018 · completed Oct 19, 2018 · Permit 18 155080 BLD

    Closed
  • Plumbing

    Plumbing - BUILDING B - Proposal to construct a 1 storey broadcasting & communications establishment. 101 Commissioners St and 1 & 17 Basin St.

    Applied May 8, 2018 · issued Aug 27, 2018 · completed Nov 6, 2018 · Permit 18 155080 PLB

    Closed
  • Drains and site services

    Drain - BUILDING B - Proposal to construct a 1 storey broadcasting & communications establishment. 101 Commissioners St and 1 & 17 Basin St.

    Applied May 8, 2018 · issued Aug 27, 2018 · completed Oct 30, 2018 · Permit 18 155080 DRN

    Closed
  • Fire and security upgrade

    FS - Sprinkler Shop Drawing - Proposal to construct a 1 storey broadcasting & communications establishment located on the northwest corner. 101 Commissioners St and 1 & 17 Basin St.

    Applied Jan 17, 2018 · completed Aug 10, 2018 · Permit 17 274954 FSU

    Closed
  • Heating and ventilation

    HVAC - Proposal to construct a 1 storey broadcasting & communications establishment located on the northwest corner. 101 Commissioners St and 1 & 17 Basin St.

    Applied Dec 13, 2017 · issued Mar 8, 2018 · completed Oct 12, 2018 · Permit 17 274954 HVA

    Closed
  • Drains and site services

    Drain - Proposal to construct a 1 storey broadcasting & communications establishment located on the northwest corner. 101 Commissioners St and 1 & 17 Basin St.

    Applied Dec 13, 2017 · issued Mar 8, 2018 · completed Oct 30, 2018 · Permit 17 274954 DRN

    Closed
  • Plumbing

    Plumbing - Proposal to construct a 1 storey broadcasting & communications establishment located on the northwest corner. 101 Commissioners St and 1 & 17 Basin St.

    Applied Dec 13, 2017 · issued Mar 8, 2018 · completed Nov 6, 2018 · Permit 17 274954 PLB

    Closed
  • Drains and site services · Inside and outside drains

    Drain - Proposal to construct a 1 storey broadcasting & communications establishment located on the northwest corner. 101 Commissioners St and 1 & 17 Basin St.

    Applied Dec 13, 2017 · issued Aug 31, 2018 · completed Nov 6, 2018 · Permit 17 274954 STS

    Closed
  • New building

    Proposal to construct a 1 storey broadcasting & communications establishment. 101 Commissioners St and 1 & 17 Basin St.

    Applied Dec 12, 2017 · issued Mar 8, 2018 · completed Oct 19, 2018 · Permit 17 274954 BLD

    Closed
  • Heating and ventilation

    HVAC - Includes kitchen exhaust -Interior alteration to ground floor to create accessory kitchen/food prep area in existing film studio. Block 8 - Building A. Pinewood. Convenience address - 21 Basin St.

    Applied Nov 14, 2014 · issued Dec 3, 2014 · completed Dec 10, 2018 · Permit 14 252191 HVA

    Closed
  • Drains and site services · Site service

    REVISION TO EXISTING SITE SERVICING PERMIT - REVISION TO ROOF DRAINAGE OFF OF BLOCK 3 ROOF.Site Servicing permit for buildings 2, 3, 7, 8a, 8b - see building permit numbers 06-175640, 06-186519, 06193897, 07104695

    Applied Dec 9, 2009 · issued Jan 27, 2010 · Permit 07 249408 STS (revision 01)

    Revision issued
  • Fire and security upgrade · Sprinklers

    Sprinklers in connection to BLD 07 104695. BLOCK 3 STAGE 4

    Applied Mar 7, 2008 · issued Jul 23, 2008 · completed Feb 21, 2019 · Permit 08 117605 FSU

    Closed
  • Drains and site services

    Drain - Construction of new industrial building - Sound Stage - Building 2. DWG's resubmitted on Jan 5/2007

    Applied Sep 21, 2007 · issued Sep 24, 2007 · completed May 22, 2019 · Permit 06 193897 DRN

    Closed
  • Drains and site services

    Drain - Construction of new industrial building - BLOCK 3 STAGE 4

    Applied Sep 21, 2007 · issued Sep 24, 2007 · completed May 23, 2019 · Permit 07 104695 DRN

    Closed
  • Heating and ventilation

    HVAC - Construction of new industrial building - Sound Stage - Block 7

    Applied Sep 20, 2007 · issued Oct 12, 2007 · completed May 23, 2019 · Permit 06 186519 HVA

    Closed
  • Drains and site services

    Drain - Proposed 2 ( Two) No's Industrial buildings known as #8A - 2 Storey, 1448 m/sq, and # 8B - 1 storey, 929 m/sq. Geotechnical Soil Report included.These are the first two of five proposed for this site. Site Plan Approval 05-211296 STE and 06-101153 pending.

    Applied Sep 20, 2007 · issued Sep 24, 2007 · completed May 22, 2019 · Permit 06 175640 DRN

    Closed
  • Drains and site services

    Drain - Construction of new industrial building - Sound Stage - Block 7

    Applied Sep 20, 2007 · issued Sep 24, 2007 · completed May 23, 2019 · Permit 06 186519 DRN

    Closed
  • Heating and ventilation

    HVAC - Proposed 2 ( Two) No's Industrial buildings known as #8A - 2 Storey, 1448 m/sq, and # 8B - 1 storey, 929 m/sq. Geotechnical Soil Report included.These are the first two of five proposed for this site. Site Plan Approval 05-211296 STE and 06-101153 pending.

    Applied Sep 20, 2007 · issued Oct 12, 2007 · completed Dec 21, 2018 · Permit 06 175640 HVA

    Closed
  • Plumbing

    Plumbing - Proposed 2 ( Two) No's Industrial buildings known as #8A - 2 Storey, 1448 m/sq, and # 8B - 1 storey, 929 m/sq. Geotechnical Soil Report included.These are the first two of five proposed for this site. Site Plan Approval 05-211296 STE and 06-101153 pending.

    Applied Sep 19, 2007 · issued Jan 15, 2008 · completed May 22, 2019 · Permit 06 175640 PLB

    Closed
  • Plumbing

    Plumbing - Construction of new industrial building - Sound Stage - Block 7

    Applied Sep 19, 2007 · issued Jan 23, 2008 · completed May 23, 2019 · Permit 06 186519 PLB

    Closed
  • Drains and site services · Site service

    Site Servicing permit for buildings 2, 3, 7, 8a, 8b - see building permit numbers 06-175640, 06-186519, 06193897, 07104695

    Applied Aug 1, 2007 · issued Sep 19, 2007 · Permit 07 249408 STS

    Inspections under way
  • New building

    Construction of new industrial building - BLOCK 3 STAGE 4

    Applied Jan 24, 2007 · issued Feb 26, 2008 · completed Mar 14, 2019 · Permit 07 104695 BLD

    Closed
  • Plumbing

    Plumbing - Construction of new industrial building - BLOCK 3 STAGE 4

    Applied Jan 24, 2007 · issued Feb 26, 2008 · completed May 23, 2019 · Permit 07 104695 PLB

    Closed
  • Heating and ventilation

    HVAC - Construction of new industrial building - Sound Stage - Building 2. DWG's resubmitted on Jan 5/2007

    Applied Jan 24, 2007 · issued Jan 15, 2008 · completed Dec 21, 2018 · Permit 06 193897 HVA

    Closed
  • Heating and ventilation

    HVAC - Construction of new industrial building - BLOCK 3 STAGE 4

    Applied Jan 24, 2007 · issued Feb 26, 2008 · completed May 23, 2019 · Permit 07 104695 HVA

    Closed
  • Plumbing

    Plumbing - Construction of new industrial building - Sound Stage - Building 2. DWG's resubmitted on Sep. 24, 2007

    Applied Jan 24, 2007 · issued Jan 15, 2008 · completed May 22, 2019 · Permit 06 193897 PLB

    Closed

Committee of Adjustment

This address's applications to the City's Committee of Adjustment since 2017, and any still open. A minor variance asks for a small exception to the zoning by-law, such as a little more height or a smaller setback; a consent divides a lot or grants an easement.

  • Consent · Leases over 21 years

    To obtain consent to establish a mortgage over a portion of the property known as 101 COMMISSIONERS ST(1 and 17 BASIN ST).

    Decision: Approved (hearing Jun 16, 2021)

    Filed Apr 15, 2021 · File B0047/21TEY

    Closed
  • Consent · Leases over 21 years

    To obtain consent to a long-term lease in excess of 21 years.

    Decision: Approved (hearing Jul 9, 2020)

    Filed Mar 10, 2020 · File B0023/20TEY

    Closed
  • Consent · Leases over 21 years

    To obtain consent to a long-term lease in excess of 21 years.

    Decision: Approved (hearing Jul 9, 2020)

    Filed Mar 10, 2020 · File B0022/20TEY

    Closed
  • Consent · Leases over 21 years

    To obtain consent to a long-term lease in excess of 21 years.

    Decision: Approved (hearing Jun 13, 2018)

    Filed Mar 28, 2018 · File B0035/18TEY

    Closed
  • Consent · Sever lot

    To obtain consent to sever the property into two lots and to grant a long-term lease in excess of 21 years.

    Decision: Approved (hearing Feb 1, 2017)

    Filed Aug 3, 2016 · 1 new lot · File B0051/16TEY

    Closed

What’s planned nearby

Development sites within 500 m

Neighbours’ Committee of Adjustment files within 250 m

None on file since 2017.

Everything planned in Toronto-Danforth

From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.