Toronto address · Ward 14, Toronto-Danforth
107 Hampton Ave
The City of Toronto has 8 building permits since 2017 and 1 Committee of Adjustment file on record for this address.
Building permits
Every permit the City lists for this address since 2017, and any still open from before, newest first.
- Closed
Small residential project · Multiple projects
Revision #2 - Addition of new dormer to the third floor, deletion of window, deletion of skylight, new layout to 3rd floor ensuite bath (same number of fixtures), new hvac showing one furnace, no proposed changes to the number of plumbing fixtures
Applied Mar 30, 2023 · issued Feb 13, 2024 · completed May 12, 2025 · Permit 22 107396 BLD (revision 02)
- Closed
Heating and ventilation
Revision #2 - Addition of new dormer to the third floor, deletion of window, deletion of skylight, new layout to 3rd floor ensuite bath (same number of fixtures), new hvac showing one furnace, no proposed changes to the number of plumbing fixtures
Applied Mar 30, 2023 · issued Apr 12, 2023 · completed Apr 17, 2025 · Permit 22 107396 HVA (revision 01)
- Closed
Heating and ventilation
HVAC - Proposal for interior alterations to all floors, new partially enclosed front porch, new rear addition to the ground, second and third floors, new basement walkout at the rear and new rear landing and steps.
Applied Jul 28, 2022 · issued Aug 5, 2022 · completed Apr 17, 2025 · Permit 22 107396 HVA
- Closed
Small residential project · Multiple projects
Rev 01: DELETION OF GROUND FLOOR SIDE ADDITION & ASSOCIATED FOUNDATIONS; DELETION OF 2ND FLOOR INTERIOR ALTERATIONS; DELETION OF 3RD FLOOR DORMER AT NORTH ELEVATION; NEW SKYLIGHT AT THIRD FLOOR; NEW SLIDING DOOR AT NORTH KITCHEN WALL; ALTERATIONS TO WINDOW SCHEDULE.
Applied Jul 28, 2022 · issued Aug 16, 2022 · completed May 12, 2025 · Permit 22 107396 BLD (revision 01)
- Closed
Drains and site services
Drain - Proposal for interior alterations to all floors, new partially enclosed front porch, new rear addition to the ground, second and third floors, new basement walkout at the rear and new rear landing and steps.
Applied Jan 25, 2022 · issued Mar 25, 2022 · completed Apr 17, 2025 · Permit 22 107396 DRN
- Closed
Plumbing
Plumbing - Proposal for interior alterations to all floors, new partially enclosed front porch, new rear addition to the ground, second and third floors, new basement walkout at the rear and new rear landing and steps.
Applied Jan 25, 2022 · issued Mar 25, 2022 · completed May 12, 2025 · Permit 22 107396 PLB
- Closed
Small residential project · Multiple projects
Proposal for interior alterations to all floors, new partially enclosed front porch, new rear addition to the ground, second and third floors, new basement walkout at the rear and new rear landing and steps.
Applied Jan 25, 2022 · issued Mar 25, 2022 · completed May 12, 2025 · Permit 22 107396 BLD
- Closed
Small residential project · Underpinning
Admin permit to 105 hampton ave.
Applied Sep 17, 2009 · issued Sep 21, 2009 · completed Mar 6, 2017 · Permit 09 170032 BLD
Committee of Adjustment
This address's applications to the City's Committee of Adjustment since 2017, and any still open. A minor variance asks for a small exception to the zoning by-law, such as a little more height or a smaller setback; a consent divides a lot or grants an easement.
- Closed
Minor variance · R addition
To alter the existing 2 ½-storey semi-detached dwelling with: a front one-storey addition; a rear one-storey addition; a rear second-storey addition; a rear third-storey addition and a rear third-storey terrace.
Decision: Approved (hearing Sep 1, 2021)
Filed Apr 3, 2021 · File A0440/21TEY
What’s planned nearby
Development sites within 500 m
No rezoning, site plan, subdivision or condominium file open within 500 m, and no pre-construction project on the site.
Neighbours’ Committee of Adjustment files within 250 m
22 Garnock Ave · Minor variance
To alter the existing two-and-one-half-storey semi-detached dwelling by constructing a rear one-storey addition (including basement) with a rear deck and stairs.
160 m away · filed Sep 15, 2026 · Postponed
67 Wolfrey Ave · Minor variance
To alter the existing two-and-one-half-storey detached dwelling by constructing a rear one-storey addition (including a basement) and a rear ground level deck with stairs. Also, to enlarge portions of the east and west sides of the third storey.
160 m away · filed Aug 20, 2026 · Hearing scheduled
152 Wolfrey Ave · Minor variance
To alter the existing two-and-one-half-storey detached dwelling by constructing a partial rear three-storey addition with rear second and third storey balconies. There will be a total of one residential dwelling unit on this lot.
110 m away · filed Jun 17, 2026 · Approved
180 Wolfrey Ave · Minor variance
To construct a new three-storey detached dwelling with a front covered porch with stairs, a rear deck with stairs, a rear basement walkout, and a rear third floor terrace.
190 m away · filed May 25, 2026 · Approved
40 Grandview Ave · Minor variance
To construct a new two-and-one-half-storey detached dwelling with a front covered porch, a rear second storey roof deck, and a front third storey roof deck.
220 m away · filed Mar 20, 2026 · Approved
2 Grandview Ave · Minor variance
To alter the existing two-and-one-half-storey semi-detached dwelling by constructing a rear third floor addition with a balcony.
170 m away · filed Mar 4, 2026 · Approved
7 Grandview Ave · Minor variance
To alter the existing two-storey semi-detached dwelling by enclosing the rear second storey deck into habitable space.
220 m away · filed Dec 11, 2025 · Approved
176 Wolfrey Ave · Minor variance
To alter the existing two-storey townhouse dwelling by constructing a front one-storey addition (including the basement) with a front porch and stairs, a side (west) one-storey addition with an entrance way and stairs, and a rear covered deck with stairs. Also, to construct a rear one-storey detached ancillary building (one-car garage), abutting the laneway.
180 m away · filed Dec 3, 2025 · Approved
From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.