The City of Toronto has 6 building permits since 2017 and 1 Committee of Adjustment file on record for this address.
Building permits
Every permit the City lists for this address since 2017, and any still open from before, newest first.
- Closed
Heating and ventilation
REV01- revision as per attached drawingsHVAC - Proposed demolition of existing single family dwelling and construction of a single family detached dwelling with a covered front porch and an integral garage.
Applied Jun 22, 2018 · issued Aug 20, 2018 · completed Jan 29, 2021 · Permit 18 131440 HVA (revision 01)
- Closed
Drains and site services
Drain - Proposed demolition of existing single family dwelling and construction of a single family detached dwelling with a covered front porch and an integral garage.
Applied Jun 5, 2018 · issued Jun 5, 2018 · completed May 9, 2019 · Permit 18 131440 DRN
- Closed
Heating and ventilation
HVAC - Proposed demolition of existing single family dwelling and construction of a single family detached dwelling with a covered front porch and an integral garage.
Applied Mar 19, 2018 · issued Apr 12, 2018 · completed Jan 29, 2021 · Permit 18 131440 HVA
- Closed
Plumbing
Plumbing - Proposed demolition of existing single family dwelling and construction of a single family detached dwelling with a covered front porch and an integral garage.
Applied Mar 19, 2018 · issued Apr 12, 2018 · completed Feb 1, 2021 · Permit 18 131440 PLB
- Closed
New house · New building
Proposed demolition of existing single family dwelling and construction of a single family detached dwelling with a covered front porch and an integral garage.
Applied Mar 19, 2018 · issued Apr 12, 2018 · completed Feb 9, 2021 · 1 home added · Permit 18 131440 BLD
- Closed
Demolition
Proposed demolition of existing single family dwelling and construction of a single family detached dwelling with a covered front porch and an integral garage.
Applied Mar 19, 2018 · issued Apr 12, 2018 · completed Dec 10, 2020 · 1 home removed · Permit 18 131072 DEM
Committee of Adjustment
This address's applications to the City's Committee of Adjustment since 2017, and any still open. A minor variance asks for a small exception to the zoning by-law, such as a little more height or a smaller setback; a consent divides a lot or grants an easement.
- Closed
Minor variance · New R building
To construct a detached dwelling with a covered front porch and an integral garage.
Decision: Approved (hearing Feb 8, 2018)
Filed Nov 27, 2017 · File A0992/17EYK
What’s planned nearby
Development sites within 500 m
No rezoning, site plan, subdivision or condominium file open within 500 m, and no pre-construction project on the site.
Neighbours’ Committee of Adjustment files within 250 m
3 Gentian Dr · Minor variance
To construct a new detached dwelling. The existing detached garage and shed in the rear yard will be maintained.
130 m away · filed Jun 12, 2026 · Approved
3 Gentian Dr · Minor variance
To construct a second storey addition above the existing dwelling.
130 m away · filed Aug 28, 2025 · Approved
60 Risdon Crt · Minor variance
To construct a one-storey garage addition, a second storey addition above the existing dwelling and a new front porch.
130 m away · filed Apr 22, 2022 · Approved
43 Danish Cres · Minor variance
To construct a second storey addition above the existing garage and to create a secondary suite.
170 m away · filed Jun 4, 2020 · Approved
5 Sagamore Cres · Minor variance
To construct a one-storey front addition, a one-storey south side addition that will include an attached garage, a second storey addition above the existing dwelling, a new front porch, and a rear yard deck.
240 m away · filed Feb 6, 2018 · Approved
39 Gentian Dr · Minor variance
To construct a second suite in the basement.
140 m away · filed Jan 27, 2017 · Approved
37 Risdon Crt · Minor variance
To construct a carport along the east side of the existing dwelling.
60 m away · filed Jan 23, 2017 · Approved
From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.