The City of Toronto has 5 building permits since 2017 (2 still open) on record for this address.
Building permits
Every permit the City lists for this address since 2017, and any still open from before, newest first.
- Inspections under way
Plumbing
Plumbing - PROPOSED: DEMOLITION AND CONSTRUCTION OF NON-LOAD BEARING DRYWALL PARTITIONS. MODIFICATIONS TO LIGHTING/HVAC/SPRINKLER LAYOUT TO SUIT. ADDITION OF SINK USING EXISTING PLUMBING ROUGH-IN.
Applied Aug 31, 2023 · issued Sep 7, 2023 · Permit 23 196282 PLB
- Closed
Addition or alteration · Interior alterations
Proposed: demolition and construction of non-load bearing drywall partitions. Modifications to lighting/hvac/sprinkler layout to suit. Addition of sink using existing plumbing rough-in.
Applied Aug 31, 2023 · issued Sep 6, 2023 · completed Feb 8, 2024 · Permit 23 196282 BLD
- Closed
Heating and ventilation
Hvac - proposed: demolition and construction of non-load bearing drywall partitions. Modifications to lighting/hvac/sprinkler layout to suit. Addition of sink using existing plumbing rough-in.
Applied Aug 31, 2023 · issued Sep 7, 2023 · completed Apr 10, 2026 · Permit 23 196282 HVA
- Closed
Addition or alteration · Garage Repair/Reconstruction
Proposal to repair/replace the parking garage entrance ramp topping complete with new waterproofing.
Applied Nov 6, 2018 · issued Dec 14, 2018 · completed Feb 9, 2022 · Permit 18 253078 BLD
- Permit issued
Plumbing · Backflow prevention devices (Water only)
Install 4" dcva backflow preventer
Applied May 12, 2015 · issued Jun 1, 2015 · Permit 15 155346 PSA
Committee of Adjustment
No applications to the City's Committee of Adjustment for this address since 2017. That's where an owner asks for a minor variance (a small exception to the zoning by-law) or a consent to divide a lot.
What’s planned nearby
Development sites within 500 m
- Under review
40 storeys · Residential
140 m away · Site plan · Under review · filed Dec 31, 2021
- Approved
59 storeys · 1,695 homes · Mixed use
230 m away · Rezoning · Approved · filed Jan 9, 2025
- Submitted
- Under review
- Under review
53 storeys · 561 homes · Residential
320 m away · Site plan · Under review · filed Jun 23, 2023
- Under review
49 storeys · 1,360 homes · Mixed use
400 m away · Rezoning · Under review · filed Dec 19, 2024
Neighbours’ Committee of Adjustment files within 250 m
100 Consilium Pl · Minor variance
To permit recreational uses as a primary use. NOTE: This minor variance application applies to the property municipally known as 350 Consilium Place.
200 m away · filed May 25, 2023 · Approved
675 Progress Ave · Consent
Proposal to sever a 30 m2 parcel of land along the Progress Avenue frontage to be conveyed to the adjacent land shown as PART 2 on the attached plan. The parcels shown as PART 2 and PART 3 were created by severance in June, 2018 under File B0021/18SC.
110 m away · filed Dec 2, 2019 · Approved
675 Progress Ave · Consent
This application is for consent to sever the land into two parcels, shown as PART 2 and PART 3 on the attached draft Reference Plan. A separate application for subdivision approval will create blocks for a future mixed use development, a block for a public park, and public road allowances (File 20 13 175005 ESC 38 SB).
110 m away · filed Apr 13, 2018 · Approved
From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.