The City of Toronto has 1 building permit since 2017 (1 still open) on record for this address.
Building permits
Every permit the City lists for this address since 2017, and any still open from before, newest first.
- Permit issued
Small residential project · Deck
Proposal for rear yard deck.
Applied Nov 8, 2024 · issued Nov 14, 2024 · Permit 24 237089 BLD
Committee of Adjustment
No applications to the City's Committee of Adjustment for this address since 2017. That's where an owner asks for a minor variance (a small exception to the zoning by-law) or a consent to divide a lot.
What’s planned nearby
Development sites within 500 m
No rezoning, site plan, subdivision or condominium file open within 500 m, and no pre-construction project on the site.
Neighbours’ Committee of Adjustment files within 250 m
13 Old Forest Hill Rd · Minor variance
To construct a new three-storey detached dwelling with a front covered porch, a front integral garage (containing a car lift connecting to the basement level/below the front driveway), a rear enclosed walkout basement, a rear ground floor terrace with stairs, and a rear third storey balcony. Also, to construct a new circular driveway, abutting Old Forest Hill Road.
130 m away · filed Jul 28, 2026 · Hearing scheduled
168 Forest Hill Rd · Minor variance
To construct a new three-storey detached dwelling (triplex) with a side (north) integral garage and a new driveway abutting Hillholm Road, a front covered porch with a roof overhang/canopy and stairs, a rear covered ground floor deck with stairs and a pergola, and rear second and third floor balconies. There will be three residential dwelling units on this lot (one unit occupying the basement level, one unit occupying the ground and the second levels, and one unit occupying the third level).
140 m away · filed Nov 28, 2025 · Approved
46 Hillholm Rd · Minor variance
To permit a rear basement extension (the existing above ground floor patio will be maintained) of the existing three-storey detached dwelling, which is currently under construction (Building Permit File Number 22 224997 BLD).
210 m away · filed Apr 25, 2025 · Approved
129 Dunvegan Rd · Minor variance
To alter the existing three-and-one-half-storey detached dwelling (basement level is considered the first storey) by constructing an integral garage with a car lift, partial front and rear second storey additions (ground level), a partial rear two-storey addition (second and third levels), a side (south) third storey addition, a partial side (north) fourth storey addition, a rear porch and canopy extension with a rear third storey balcony extension above, and a widened front driveway.
210 m away · filed Mar 5, 2025 · Approved
174 Dunvegan Rd · Minor variance
To alter the existing two-and-one-half-storey detached dwelling by constructing interior alterations to reconfigure the main stair, a new elevator and constructing a rear (west) second and third floor dormer addition. Also, to construct a side (south) one-storey addition to expand and reconstruct the integral garage entrance (fronting Hillholm Road).
170 m away · filed Jun 24, 2024 · Approved
162 Forest Hill Rd · Minor variance
To construct a new three-storey detached dwelling with a front covered porch, a front integral garage, a rear ground floor deck with a fireplace and BBQ area, and a rear third storey balcony.
100 m away · filed May 28, 2024 · Approved
171 Dunvegan Rd · Minor variance
To construct a new three-storey detached dwelling with a front yard circular driveway, abutting a front integral garage, a front covered porch, front second floor juliet balconies, and a rear ground floor terrace.
170 m away · filed May 22, 2024 · Approved
46 Hillholm Rd · Minor variance
To alter the three-storey detached dwelling (currently under construction from the original permit) by increasing the builidng length (under ground).
210 m away · filed Sep 11, 2023 · Application withdrawn
From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.