Sample data. These listings are fictional examples used to demonstrate the site. No MLS or board data is displayed.

Shaun Lovell, Real Estate SalespersonRight At Home Realty, Brokerage289-813-3318

Toronto address · Ward 9, Davenport

158 Sterling Rd

Museum of Contemporary Art Toronto

The City of Toronto has 176 building permits since 2017 (10 still open) and 4 Committee of Adjustment files on record for this address.

Building permits

Every permit the City lists for this address since 2017, and any still open from before, newest first.

  • Plumbing

    Plumbing - Proposal for interior alterstions for new demising walls and new shared boardroom in existing office space - 9th Floor

    Applied Feb 27, 2026 · issued Jun 17, 2026 · Permit 26 122287 PLB

    Permit issued
  • Addition or alteration · Interior alterations

    Proposal for interior alterstions for new demising walls and new shared boardroom in existing office space - 9th Floor

    Applied Feb 27, 2026 · issued Jun 17, 2026 · Permit 26 122287 BLD

    Permit issued
  • Heating and ventilation

    HVAC - Proposal for interior alterstions for new demising walls and new shared boardroom in existing office space - 9th Floor

    Applied Feb 27, 2026 · issued Jun 17, 2026 · Permit 26 122287 HVA

    Permit issued
  • Temporary structure · Temporary structures

    Ghazaleh Avarzamani's Mashrabiya is an artwork currently installed on the facade of MOCA's building. It is supported by Toronto's Year of Public Art. We are applying to extend the installation until December 1, 2023.

    Applied Dec 2, 2021 · issued Dec 23, 2021 · Permit 21 185806 TPS (revision 01)

    Revision issued
  • Temporary structure · Temporary structures

    Ghazaleh Avarzamani's Mashrabiya is a play on traditional Islamic window screens; people on the inside can see out but those on the outside cannot see in. It is supported by the City of Toronto Year of Public Art. The work will hang from the facade of the building with anchors above the window. The installer will ensure that the anchor points are as minimal as possible and will be filled in afterwards with a matching concrete. The installation is temporary and the dates are August 2021-January 2022.

    Applied Jul 17, 2021 · issued Aug 11, 2021 · Permit 21 185806 TPS

    Inspections under way
  • Plumbing

    Plumbing - Proposed Interior Alterations to add two new offices to the ground floor.

    Applied Jan 7, 2021 · issued Jan 25, 2021 · completed Aug 24, 2022 · Permit 21 101920 PLB

    Closed
  • Addition or alteration · Interior alterations

    Proposed Interior Alterations to add two new offices to the ground floor.

    Applied Jan 7, 2021 · issued Jan 25, 2021 · completed Dec 8, 2023 · Permit 21 101920 BLD

    Closed
  • Heating and ventilation

    HVAC - Proposed Interior Alterations to add two new offices to the ground floor.

    Applied Jan 7, 2021 · issued Jan 25, 2021 · completed Dec 17, 2022 · Permit 21 101920 HVA

    Closed
  • Addition or alteration · Interior alterations

    REV01: Theater floor and ceiling structure, Reception/Boardroom double height stud wall structure.

    Applied Oct 20, 2020 · issued Nov 4, 2020 · completed Oct 26, 2021 · Permit 20 146732 BLD (revision 01)

    Closed
  • Fire and security upgrade · Electromagnetic locks

    Proposal to install of a maglock on 10th floor of existing office building

    Applied Aug 24, 2020 · issued Sep 17, 2020 · completed Nov 10, 2021 · Permit 20 184458 FSU

    Closed
  • Heating and ventilation

    Hvac - interior alterations to 10th floor "folks vfx ulc"

    Applied May 20, 2020 · issued Jun 18, 2020 · completed Feb 19, 2021 · Permit 20 146732 HVA

    Closed
  • Plumbing

    Plumbing - INTERIOR ALTERATIONS TO 10TH FLOOR "FOLKS VFX ULC"

    Applied May 20, 2020 · issued Jun 18, 2020 · completed Oct 26, 2021 · Permit 20 146732 PLB

    Closed
Show 164 more permits
  • Addition or alteration · Interior alterations

    Interior alterations to 10th floor suite "folks vfx ulc"

    Applied May 20, 2020 · issued Jun 18, 2020 · completed Oct 26, 2021 · Permit 20 146732 BLD

    Closed
  • Fire and security upgrade · Electromagnetic locks

    Proposal to install a new maglock on the suite entry door number 700-1

    Applied May 20, 2020 · issued May 22, 2020 · completed Mar 10, 2022 · Permit 20 146741 FSU

    Closed
  • Addition or alteration · Interior alterations

    Proposal for alterations to an office space for a new demising wall and a new shared board room and lunch room. Under the revision demising wall will be removed and maglock wil be added on suite entry.

    Applied Apr 22, 2020 · issued May 21, 2020 · completed Mar 10, 2022 · Permit 20 106032 BLD (revision 01)

    Closed
  • Plumbing

    Plumbing - Proposal for alterations to an office space for a new demising wall and a new shared board room and lunch room.

    Applied Jan 17, 2020 · issued Feb 25, 2020 · completed Feb 16, 2022 · Permit 20 106032 PLB

    Closed
  • Heating and ventilation

    HVAC - Proposal for alterations to an office space for a new demising wall and a new shared board room and lunch room.

    Applied Jan 17, 2020 · issued Feb 25, 2020 · completed Feb 15, 2022 · Permit 20 106032 HVA

    Closed
  • Addition or alteration · Interior alterations

    Proposal for alterations to an office space for a new demising wall and a new shared board room and lunch room.

    Applied Jan 17, 2020 · issued Feb 25, 2020 · completed Mar 10, 2022 · Permit 20 106032 BLD

    Closed
  • Addition or alteration · Interior alterations

    Proposal for interior alterations to level 6 of existing office building

    Applied Jun 11, 2019 · issued Jun 27, 2019 · completed Mar 15, 2022 · Permit 19 169705 BLD

    Closed
  • Heating and ventilation

    HVAC - Proposal for interior alterations to level 6 of existing office building

    Applied Jun 11, 2019 · issued Jul 22, 2019 · completed Mar 28, 2022 · Permit 19 169705 HVA

    Closed
  • Plumbing

    Plumbing - Proposal for interior alterations to level 6 of existing office building

    Applied Jun 11, 2019 · issued Jul 22, 2019 · completed Jan 27, 2023 · Permit 19 169705 PLB

    Closed
  • Plumbing · Fixtures/Roof Drains: other

    REV01: removal of grease interceptorProposal to install a grease interceptor, backflow prevention device, kitchen sink, floor drains, dishwasher and bar sink in existing restaurant "Forno Cultura"

    Applied Oct 3, 2018 · issued Oct 17, 2018 · completed Mar 13, 2019 · Permit 18 200979 PSA (revision 01)

    Closed
  • Plumbing · Fixtures/Roof Drains: other

    Proposal to install a grease interceptor, backflow prevention device, kitchen sink, floor drains, dishwasher and bar sink in existing restaurant "Forno Cultura"

    Applied Jul 27, 2018 · issued Aug 7, 2018 · completed Mar 13, 2019 · Permit 18 200979 PSA

    Closed
  • Addition or alteration · Interior alterations

    Construct exterior garbage enclosure.

    Applied Jun 14, 2018 · issued Apr 1, 2019 · completed Feb 1, 2022 · Permit 16 176257 BLD (revision 03)

    Closed
  • Addition or alteration · Interior alterations

    Revision to layout.

    Applied May 22, 2018 · issued Jun 19, 2018 · completed Sep 20, 2019 · Permit 17 245170 BLD (revision 01)

    Closed
  • Heating and ventilation

    Revision to layout.

    Applied May 22, 2018 · issued Jun 14, 2018 · completed Aug 10, 2018 · Permit 17 245170 HVA (revision 01)

    Closed
  • Fire and security upgrade · Electromagnetic locks

    Installation of five mag locks on interior door and cross over floors

    Applied May 14, 2018 · issued Jun 26, 2018 · completed Oct 26, 2021 · Permit 18 158228 FSU

    Closed
  • Designated structure · Sign building permit related

    In conjunction with a multi-storey building on the premises, proposal to erect and display one illuminated projecting sign displaying static copy and three wall signs, all displaying static copy, one of which is illuminated. The proposed projecting sign is located on portions of the 3rd, 4th and 5th storey of the east elevation, measuring 11.3 metres vertically by 1.14 metres horizontally at a height of 23 metres. One of the proposed wall signs is located on the first storey of the east elevation, measuring 0.81 metres vertically by 1.39 metres horizontally. Two of the proposed wall signs are…

    Applied May 1, 2018 · issued May 23, 2018 · completed Nov 18, 2020 · Permit 18 151647 DST

    Closed
  • Addition or alteration · Interior alterations

    Revision to add rooftop deck.

    Applied Nov 16, 2017 · issued Feb 20, 2018 · completed Feb 1, 2022 · Permit 16 176257 BLD (revision 02)

    Closed
  • Heating and ventilation

    HVAC - Proposal for interior alterations to 8th and portion of 7th floor of existing office building. Tenant - "Agency 59".

    Applied Oct 10, 2017 · issued Nov 10, 2017 · completed Aug 10, 2018 · Permit 17 245170 HVA

    Closed
  • Plumbing

    Plumbing - Proposal for interior alterations to 8th and portion of 7th floor of existing office building. Tenant - "Agency 59".

    Applied Oct 10, 2017 · issued Nov 10, 2017 · completed Aug 13, 2018 · Permit 17 245170 PLB

    Closed
  • Addition or alteration · Interior alterations

    Proposal for interior alterations to 8th and portion of 7th floor of existing office building. Tenant - "Agency 59".

    Applied Oct 10, 2017 · issued Nov 10, 2017 · completed Sep 20, 2019 · Permit 17 245170 BLD

    Closed
  • Heating and ventilation

    Revision for 2 glazed additions to the West of the heritage building (1 for the base building office elevator lobby and 1for MOCA cafe seating), 2 glass canopies to the West of the heritage building, 1 freight elevator to the North of the heritage building, and service area to the North with reinforced concrete wall surrounding transformer, gas meter and garbage bin storage.

    Applied Jul 19, 2017 · issued Aug 11, 2017 · completed Mar 28, 2022 · Permit 16 176257 HVA (revision 01)

    Closed
  • Addition or alteration · Interior alterations

    Revision for 2 glazed additions to the West of the heritage building (1 for the base building office elevator lobby and 1for MOCA cafe seating), 2 glass canopies to the West of the heritage building, 1 freight elevator to the North of the heritage building, and service area to the North with reinforced concrete wall surrounding transformer, gas meter and garbage bin storage.

    Applied Jul 19, 2017 · issued Aug 10, 2017 · completed Feb 1, 2022 · Permit 16 176257 BLD (revision 01)

    Closed
  • Drains and site services

    Drain - BLOCK D - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Nov 5, 2019 · Permit 17 154108 D03

    Closed
  • Drains and site services

    Drain - BLOCK D - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Nov 7, 2019 · Permit 17 154108 D02

    Closed
  • Drains and site services

    Drain - BLOCK D - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Nov 7, 2019 · Permit 17 154108 D01

    Closed
  • Drains and site services

    Drain - BLOCK D - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Nov 6, 2019 · Permit 17 154108 D08

    Closed
  • Drains and site services

    Drain - BLOCK D - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Nov 6, 2019 · Permit 17 154108 D07

    Closed
  • Drains and site services

    Drain - BLOCK C - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Sep 6, 2019 · Permit 17 154083 D06

    Closed
  • Plumbing

    Plumbing - BLOCK C - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Sep 6, 2019 · Permit 17 154083 P08

    Closed
  • Plumbing

    Plumbing - BLOCK C - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Sep 6, 2019 · Permit 17 154083 P07

    Closed
  • Drains and site services

    Drain - BLOCK C - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Sep 6, 2019 · Permit 17 154083 D05

    Closed
  • Drains and site services

    Drain - BLOCK C - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Sep 6, 2019 · Permit 17 154083 D04

    Closed
  • Drains and site services

    Drain - BLOCK C - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Sep 6, 2019 · Permit 17 154083 D03

    Closed
  • Drains and site services

    Drain - BLOCK C - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Sep 6, 2019 · Permit 17 154083 D02

    Closed
  • Drains and site services

    Drain - BLOCK C - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Sep 6, 2019 · Permit 17 154083 D01

    Closed
  • Plumbing

    Plumbing - BLOCK C - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Sep 6, 2019 · Permit 17 154083 P06

    Closed
  • Plumbing

    Plumbing - BLOCK C - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Sep 6, 2019 · Permit 17 154083 P05

    Closed
  • Heating and ventilation

    HVAC - BLOCK C - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Sep 6, 2019 · Permit 17 154083 H01

    Closed
  • Heating and ventilation

    HVAC - BLOCK C - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Sep 6, 2019 · Permit 17 154083 H02

    Closed
  • Heating and ventilation

    HVAC - BLOCK C - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Sep 6, 2019 · Permit 17 154083 H03

    Closed
  • Heating and ventilation

    HVAC - BLOCK C - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Sep 6, 2019 · Permit 17 154083 H04

    Closed
  • Plumbing

    Plumbing - BLOCK C - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Sep 6, 2019 · Permit 17 154083 P04

    Closed
  • Heating and ventilation

    HVAC - BLOCK C - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Sep 6, 2019 · Permit 17 154083 H06

    Closed
  • Heating and ventilation

    HVAC - BLOCK C - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Sep 6, 2019 · Permit 17 154083 H07

    Closed
  • Heating and ventilation

    HVAC - BLOCK C - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Sep 6, 2019 · Permit 17 154083 H08

    Closed
  • Heating and ventilation

    HVAC - BLOCK D - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Nov 7, 2019 · Permit 17 154108 H01

    Closed
  • Heating and ventilation

    HVAC - BLOCK D - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Nov 7, 2019 · Permit 17 154108 H02

    Closed
  • Heating and ventilation

    HVAC - BLOCK D - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Nov 5, 2019 · Permit 17 154108 H03

    Closed
  • Heating and ventilation

    HVAC - BLOCK D - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Nov 7, 2019 · Permit 17 154108 H04

    Closed
  • Heating and ventilation

    HVAC - BLOCK D - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Nov 7, 2019 · Permit 17 154108 H05

    Closed
  • Heating and ventilation

    HVAC - BLOCK D - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Nov 5, 2019 · Permit 17 154108 H06

    Closed
  • Heating and ventilation

    HVAC - BLOCK D - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Nov 6, 2019 · Permit 17 154108 H07

    Closed
  • Heating and ventilation

    HVAC - BLOCK D - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Nov 6, 2019 · Permit 17 154108 H08

    Closed
  • Heating and ventilation

    HVAC - BLOCK C - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Sep 6, 2019 · Permit 17 154083 H05

    Closed
  • Plumbing

    Plumbing - BLOCK C - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Sep 6, 2019 · Permit 17 154083 P03

    Closed
  • Plumbing

    Plumbing - BLOCK D - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Nov 7, 2019 · Permit 17 154108 P01

    Closed
  • Plumbing

    Plumbing - BLOCK D - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Nov 7, 2019 · Permit 17 154108 P02

    Closed
  • Plumbing

    Plumbing - BLOCK D - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Aug 27, 2025 · Permit 17 154108 P03

    Closed
  • Plumbing

    Plumbing - BLOCK D - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Aug 27, 2025 · Permit 17 154108 P04

    Closed
  • Plumbing

    Plumbing - BLOCK C - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Aug 27, 2025 · Permit 17 154083 P02

    Closed
  • Plumbing

    Plumbing - BLOCK D - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Nov 7, 2019 · Permit 17 154108 P05

    Closed
  • Plumbing

    Plumbing - BLOCK D - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Aug 27, 2025 · Permit 17 154108 P06

    Closed
  • Plumbing

    Plumbing - BLOCK C - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Sep 6, 2019 · Permit 17 154083 P01

    Closed
  • Plumbing

    Plumbing - BLOCK D - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Nov 6, 2019 · Permit 17 154108 P08

    Closed
  • Plumbing

    Plumbing - BLOCK D - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Nov 6, 2019 · Permit 17 154108 P07

    Closed
  • Drains and site services · Site service

    Site Services in connection to new 32 unit (4 Blocks) townhose development. See Block A - 17 152275, Block B - 17 153660, Block C - 17 154083, and Block D - 17 154108 for reference.

    Applied May 4, 2017 · issued Nov 26, 2018 · Permit 17 154203 STS

    Inspections under way
  • Drains and site services

    Drain - BLOCK C - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Sep 6, 2019 · Permit 17 154083 D08

    Closed
  • Drains and site services

    Drain - BLOCK C - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Sep 6, 2019 · Permit 17 154083 D07

    Closed
  • New house · New building - lead

    BLOCK C - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Jun 7, 2018 · completed Jun 17, 2026 · 1 home added · Permit 17 154083 B01

    Closed
  • New house · New building

    BLOCK C - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Jun 7, 2018 · completed Jun 4, 2026 · 1 home added · Permit 17 154083 B02

    Closed
  • New house · New building

    BLOCK C - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Jun 7, 2018 · completed Jun 4, 2026 · 1 home added · Permit 17 154083 B03

    Closed
  • New house · New building

    BLOCK C - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Jun 7, 2018 · completed Jun 12, 2026 · 1 home added · Permit 17 154083 B04

    Closed
  • New house · New building

    BLOCK C - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Jun 7, 2018 · completed Jun 4, 2026 · 1 home added · Permit 17 154083 B05

    Closed
  • New house · New building

    BLOCK C - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Jun 7, 2018 · completed Jun 9, 2026 · 1 home added · Permit 17 154083 B06

    Closed
  • New house · New building

    BLOCK C - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Jun 7, 2018 · completed Jun 5, 2026 · 1 home added · Permit 17 154083 B07

    Closed
  • New house · New building

    BLOCK C - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Jun 7, 2018 · completed Jun 16, 2026 · 1 home added · Permit 17 154083 B08

    Closed
  • New house · New building - lead

    BLOCK D - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Jun 7, 2018 · completed Jul 14, 2026 · 1 home added · Permit 17 154108 B01

    Closed
  • New house · New building

    BLOCK D - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Jun 7, 2018 · completed Jun 22, 2026 · 1 home added · Permit 17 154108 B02

    Closed
  • New house · New building

    BLOCK D - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Jun 7, 2018 · completed Jun 23, 2026 · 1 home added · Permit 17 154108 B03

    Closed
  • New house · New building

    BLOCK D - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Jun 7, 2018 · completed Jul 13, 2026 · 1 home added · Permit 17 154108 B04

    Closed
  • New house · New building

    BLOCK D - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Jun 7, 2018 · completed Jul 3, 2026 · 1 home added · Permit 17 154108 B05

    Closed
  • New house · New building

    BLOCK D - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Jun 7, 2018 · completed Jun 25, 2026 · 1 home added · Permit 17 154108 B06

    Closed
  • New house · New building

    BLOCK D - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Jun 7, 2018 · completed Jun 19, 2026 · 1 home added · Permit 17 154108 B07

    Closed
  • New house · New building

    BLOCK D - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Jun 7, 2018 · completed Jun 19, 2026 · 1 home added · Permit 17 154108 B08

    Closed
  • Drains and site services

    Drain - BLOCK D - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Nov 5, 2019 · Permit 17 154108 D06

    Closed
  • Drains and site services

    Drain - BLOCK D - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Nov 7, 2019 · Permit 17 154108 D05

    Closed
  • Drains and site services

    Drain - BLOCK D - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 4, 2017 · issued Dec 12, 2017 · completed Nov 7, 2019 · Permit 17 154108 D04

    Closed
  • Drains and site services

    Drain - BLOCK B - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 3, 2017 · issued Dec 12, 2017 · completed Jul 9, 2019 · Permit 17 153660 D03

    Closed
  • New house · New building - lead

    BLOCK B - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 3, 2017 · issued Jun 6, 2018 · completed May 29, 2026 · 1 home added · Permit 17 153660 B01

    Closed
  • New house · New building

    BLOCK B - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 3, 2017 · issued Jun 7, 2018 · completed May 29, 2026 · 1 home added · Permit 17 153660 B02

    Closed
  • New house · New building

    BLOCK B - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 3, 2017 · issued Jun 7, 2018 · completed May 29, 2026 · 1 home added · Permit 17 153660 B03

    Closed
  • New house · New building

    BLOCK B - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 3, 2017 · issued Jun 7, 2018 · completed May 29, 2026 · 1 home added · Permit 17 153660 B04

    Closed
  • New house · New building

    BLOCK B - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 3, 2017 · issued Jun 7, 2018 · completed May 29, 2026 · 1 home added · Permit 17 153660 B05

    Closed
  • New house · New building

    BLOCK B - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 3, 2017 · issued Jun 7, 2018 · completed May 29, 2026 · 1 home added · Permit 17 153660 B06

    Closed
  • New house · New building

    BLOCK B - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 3, 2017 · issued Jun 7, 2018 · completed May 29, 2026 · 1 home added · Permit 17 153660 B07

    Closed
  • New house · New building

    BLOCK B - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 3, 2017 · issued Jun 7, 2018 · completed May 29, 2026 · 1 home added · Permit 17 153660 B08

    Closed
  • Heating and ventilation

    HVAC - BLOCK B - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 3, 2017 · issued Dec 12, 2017 · completed Jul 9, 2019 · Permit 17 153660 H01

    Closed
  • Heating and ventilation

    HVAC - BLOCK B - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 3, 2017 · issued Dec 12, 2017 · completed Jul 9, 2019 · Permit 17 153660 H02

    Closed
  • Heating and ventilation

    HVAC - BLOCK B - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 3, 2017 · issued Dec 12, 2017 · completed Jul 9, 2019 · Permit 17 153660 H03

    Closed
  • Heating and ventilation

    HVAC - BLOCK B - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 3, 2017 · issued Dec 12, 2017 · completed Jul 9, 2019 · Permit 17 153660 H04

    Closed
  • Heating and ventilation

    HVAC - BLOCK B - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 3, 2017 · issued Dec 12, 2017 · completed Jul 9, 2019 · Permit 17 153660 H05

    Closed
  • Heating and ventilation

    HVAC - BLOCK B - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 3, 2017 · issued Dec 12, 2017 · completed Jul 9, 2019 · Permit 17 153660 H06

    Closed
  • Heating and ventilation

    HVAC - BLOCK B - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 3, 2017 · issued Dec 12, 2017 · completed Jul 9, 2019 · Permit 17 153660 H07

    Closed
  • Heating and ventilation

    HVAC - BLOCK B - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 3, 2017 · issued Dec 12, 2017 · completed Jun 21, 2019 · Permit 17 153660 H08

    Closed
  • Plumbing

    Plumbing - BLOCK B - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 3, 2017 · issued Dec 12, 2017 · completed Jul 9, 2019 · Permit 17 153660 P01

    Closed
  • Plumbing

    Plumbing - BLOCK B - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 3, 2017 · issued Dec 12, 2017 · completed Jul 9, 2019 · Permit 17 153660 P02

    Closed
  • Plumbing

    Plumbing - BLOCK B - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 3, 2017 · issued Dec 12, 2017 · completed Jul 9, 2019 · Permit 17 153660 P03

    Closed
  • Plumbing

    Plumbing - BLOCK B - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 3, 2017 · issued Dec 12, 2017 · completed Jul 9, 2019 · Permit 17 153660 P04

    Closed
  • Plumbing

    Plumbing - BLOCK B - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 3, 2017 · issued Dec 12, 2017 · completed Jun 21, 2019 · Permit 17 153660 P08

    Closed
  • Plumbing

    Plumbing - BLOCK B - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 3, 2017 · issued Dec 12, 2017 · completed Jul 9, 2019 · Permit 17 153660 P05

    Closed
  • Plumbing

    Plumbing - BLOCK B - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 3, 2017 · issued Dec 12, 2017 · completed Jul 9, 2019 · Permit 17 153660 P06

    Closed
  • Plumbing

    Plumbing - BLOCK B - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 3, 2017 · issued Dec 12, 2017 · completed Jul 9, 2019 · Permit 17 153660 P07

    Closed
  • Drains and site services

    Drain - BLOCK B - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 3, 2017 · issued Dec 12, 2017 · completed Jul 9, 2019 · Permit 17 153660 D01

    Closed
  • Drains and site services

    Drain - BLOCK B - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 3, 2017 · issued Dec 12, 2017 · completed Jul 9, 2019 · Permit 17 153660 D02

    Closed
  • Drains and site services

    Drain - BLOCK B - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 3, 2017 · issued Dec 12, 2017 · completed Jul 9, 2019 · Permit 17 153660 D04

    Closed
  • Drains and site services

    Drain - BLOCK B - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 3, 2017 · issued Dec 12, 2017 · completed Jul 9, 2019 · Permit 17 153660 D05

    Closed
  • Drains and site services

    Drain - BLOCK B - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 3, 2017 · issued Dec 12, 2017 · completed Jul 9, 2019 · Permit 17 153660 D06

    Closed
  • Drains and site services

    Drain - BLOCK B - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 3, 2017 · issued Dec 12, 2017 · completed Jul 10, 2019 · Permit 17 153660 D07

    Closed
  • Drains and site services

    Drain - BLOCK B - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. SEE LEAD FILE 17 152275 B01 & H01 FOR ALL DRAWINGS AND DOCUMENTS and stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 3, 2017 · issued Dec 12, 2017 · completed Jun 21, 2019 · Permit 17 153660 D08

    Closed
  • Heating and ventilation

    HVAC - LEAD FILE - BLOCK A - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. See stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 2, 2017 · issued Dec 14, 2017 · completed Jun 12, 2019 · Permit 17 152275 H05

    Closed
  • Heating and ventilation

    HVAC - LEAD FILE - BLOCK A - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. See stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 2, 2017 · issued Dec 14, 2017 · completed Jun 12, 2019 · Permit 17 152275 H07

    Closed
  • Heating and ventilation

    HVAC - LEAD FILE - BLOCK A - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. See stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 2, 2017 · issued Dec 14, 2017 · completed Jun 12, 2019 · Permit 17 152275 H06

    Closed
  • Heating and ventilation

    HVAC - LEAD FILE - BLOCK A - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. See stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 2, 2017 · issued Dec 14, 2017 · completed Jun 12, 2019 · Permit 17 152275 H02

    Closed
  • Heating and ventilation

    HVAC - LEAD FILE - BLOCK A - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. See stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 2, 2017 · issued Dec 14, 2017 · completed Jun 12, 2019 · Permit 17 152275 H04

    Closed
  • Drains and site services

    Drain - LEAD FILE - BLOCK A - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. See stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 2, 2017 · issued Dec 12, 2017 · completed Jun 12, 2019 · Permit 17 152275 D01

    Closed
  • Drains and site services

    Drain - LEAD FILE - BLOCK A - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. See stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 2, 2017 · issued Dec 12, 2017 · completed Jun 12, 2019 · Permit 17 152275 D02

    Closed
  • Drains and site services

    Drain - LEAD FILE - BLOCK A - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. See stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 2, 2017 · issued Dec 12, 2017 · completed Jun 12, 2019 · Permit 17 152275 D03

    Closed
  • Drains and site services

    Drain - LEAD FILE - BLOCK A - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. See stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 2, 2017 · issued Dec 12, 2017 · completed Jun 12, 2019 · Permit 17 152275 D04

    Closed
  • Drains and site services

    Drain - LEAD FILE - BLOCK A - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. See stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 2, 2017 · issued Dec 12, 2017 · completed Jun 12, 2019 · Permit 17 152275 D05

    Closed
  • Drains and site services

    Drain - LEAD FILE - BLOCK A - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. See stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 2, 2017 · issued Dec 12, 2017 · completed Jun 12, 2019 · Permit 17 152275 D06

    Closed
  • Drains and site services

    Drain - LEAD FILE - BLOCK A - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. See stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 2, 2017 · issued Dec 12, 2017 · completed Jun 12, 2019 · Permit 17 152275 D07

    Closed
  • Drains and site services

    Drain - LEAD FILE - BLOCK A - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. See stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 2, 2017 · issued Dec 14, 2017 · completed Jun 12, 2019 · Permit 17 152275 D08

    Closed
  • Plumbing

    Plumbing - LEAD FILE - BLOCK A - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. See stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 2, 2017 · issued Dec 14, 2017 · completed Jun 12, 2019 · Permit 17 152275 P03

    Closed
  • Plumbing

    Plumbing - LEAD FILE - BLOCK A - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. See stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 2, 2017 · issued Dec 14, 2017 · completed Jun 12, 2019 · Permit 17 152275 P04

    Closed
  • Plumbing

    Plumbing - LEAD FILE - BLOCK A - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. See stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 2, 2017 · issued Dec 14, 2017 · completed Jun 12, 2019 · Permit 17 152275 P02

    Closed
  • Plumbing

    Plumbing - LEAD FILE - BLOCK A - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. See stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 2, 2017 · issued Dec 14, 2017 · completed Jun 12, 2019 · Permit 17 152275 P01

    Closed
  • Plumbing

    Plumbing - LEAD FILE - BLOCK A - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. See stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 2, 2017 · issued Dec 14, 2017 · completed Jun 12, 2019 · Permit 17 152275 P05

    Closed
  • Plumbing

    Plumbing - LEAD FILE - BLOCK A - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. See stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 2, 2017 · issued Dec 14, 2017 · completed Jun 12, 2019 · Permit 17 152275 P06

    Closed
  • Plumbing

    Plumbing - LEAD FILE - BLOCK A - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. See stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 2, 2017 · issued Dec 14, 2017 · completed Jun 12, 2019 · Permit 17 152275 P07

    Closed
  • Plumbing

    Plumbing - LEAD FILE - BLOCK A - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. See stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 2, 2017 · issued Dec 14, 2017 · completed Jun 12, 2019 · Permit 17 152275 P08

    Closed
  • Heating and ventilation

    HVAC - LEAD FILE - BLOCK A - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. See stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 2, 2017 · issued Dec 14, 2017 · completed Jun 12, 2019 · Permit 17 152275 H03

    Closed
  • Heating and ventilation

    HVAC - LEAD FILE - BLOCK A - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. See stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 2, 2017 · issued Dec 14, 2017 · completed Jun 12, 2019 · Permit 17 152275 H01

    Closed
  • Heating and ventilation

    HVAC - LEAD FILE - BLOCK A - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. See stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 2, 2017 · issued Dec 14, 2017 · completed Jun 12, 2019 · Permit 17 152275 H08

    Closed
  • New house · New building

    LEAD FILE - BLOCK A - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. See stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 1, 2017 · issued Jun 7, 2018 · completed Aug 21, 2026 · 1 home added · Permit 17 152275 B08

    Closed
  • New house · New building

    LEAD FILE - BLOCK A - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. See stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 1, 2017 · issued Jun 7, 2018 · completed Aug 28, 2026 · 1 home added · Permit 17 152275 B07

    Closed
  • New house · New building

    LEAD FILE - BLOCK A - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. See stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 1, 2017 · issued Jun 7, 2018 · completed Jul 21, 2026 · 1 home added · Permit 17 152275 B06

    Closed
  • New house · New building

    LEAD FILE - BLOCK A - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. See stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 1, 2017 · issued Jun 7, 2018 · completed Jul 22, 2026 · 1 home added · Permit 17 152275 B05

    Closed
  • New house · New building

    LEAD FILE - BLOCK A - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. See stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 1, 2017 · issued Jun 7, 2018 · completed Jul 31, 2026 · 1 home added · Permit 17 152275 B02

    Closed
  • New house · New building - lead

    LEAD FILE - BLOCK A - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. See stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 1, 2017 · issued Jun 7, 2018 · completed Sep 8, 2026 · 1 home added · Permit 17 152275 B01

    Closed
  • New house · New building

    LEAD FILE - BLOCK A - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. See stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 1, 2017 · issued Jun 7, 2018 · completed Aug 12, 2026 · 1 home added · Permit 17 152275 B04

    Closed
  • New house · New building

    LEAD FILE - BLOCK A - Proposal to construct a total of 32 three storey townhouses (4 blocks with 8 townhouses within each block) with integral garage and finished basement. BLOCKS A, B, C, & D. 20 PERTH AVE. See stand alone shoring and excavation for soil remediation 17 121665 BLD for reference.

    Applied May 1, 2017 · issued Jun 7, 2018 · completed Aug 11, 2026 · 1 home added · Permit 17 152275 B03

    Closed
  • Alternative solution

    Alternative Solution in conjunction to 17 117845 BLD for standpipe purposes.

    Applied Apr 3, 2017 · completed Apr 21, 2017 · Permit 17 138418 ALT

    Approved
  • Fire and security upgrade

    FS - Sprinkler Shop Drawing - Interior alterations to basement and floors 1-5 inclusive in existing gallery/exhibition space/office sapce. Museum of Contemprary Art (MOCA). Note: See active Base Building Permits.

    Applied Mar 31, 2017 · Permit 17 117845 FSU

    Application on hold
  • Addition or alteration · Shoring

    Stand alone shoring and excavation for soil remediation. BLOCK 1. 20 PERTH AVE.

    Applied Feb 27, 2017 · issued Mar 9, 2017 · Permit 17 121665 BLD

    Inspections under way
  • Plumbing

    Plumbing - Interior alterations to basement and floors 1-5 inclusive in existing gallery/exhibition space/office sapce. Museum of Contemprary Art (MOCA). Note: See active Base Building Permits.

    Applied Feb 16, 2017 · issued May 9, 2017 · completed Mar 25, 2022 · Permit 17 117845 PLB

    Closed
  • Heating and ventilation

    HVAC - Interior alterations to basement and floors 1-5 inclusive in existing gallery/exhibition space/office sapce. Museum of Contemprary Art (MOCA). Note: See active Base Building Permits.

    Applied Feb 16, 2017 · issued May 9, 2017 · completed Dec 1, 2021 · Permit 17 117845 HVA

    Closed
  • Addition or alteration · Interior alterations

    Interior alterations to basement and floors 1-5 inclusive in existing gallery/exhibition space/office sapce. Museum of Contemprary Art (MOCA). Note: See active Base Building Permits.

    Applied Feb 16, 2017 · issued May 9, 2017 · completed Mar 30, 2022 · Permit 17 117845 BLD

    Closed
  • Fire and security upgrade

    FS - Sprinkler Shop Drawing - Interior alterations to all floors of existing manufacturing building to convert to mixed use (exhibition, gallery, and office space).

    Applied Sep 15, 2016 · issued Mar 9, 2018 · completed Mar 9, 2018 · Permit 16 176257 FSU

    Closed
  • Plumbing

    Plumbing - Interior alterations to all floors of existing manufacturing building to convert to mixed use (exhibition, gallery, and office space).

    Applied Jun 17, 2016 · issued Oct 5, 2016 · completed Mar 25, 2022 · Permit 16 176257 PLB

    Closed
  • Heating and ventilation

    HVAC - Interior alterations to all floors of existing manufacturing building to convert to mixed use (exhibition, gallery, and office space).

    Applied Jun 17, 2016 · issued Oct 5, 2016 · completed Mar 28, 2022 · Permit 16 176257 HVA

    Closed
  • Addition or alteration · Interior alterations

    Interior alterations to all floors of existing manufacturing building to convert to mixed use (exhibition, gallery, and office space).

    Applied Jun 17, 2016 · issued Oct 5, 2016 · completed Feb 1, 2022 · Permit 16 176257 BLD

    Closed
  • Fire and security upgrade

    FS - Sprinkler Shop Drawing - Proposal for interior alterations for new elevator on ground floor

    Applied Apr 1, 2016 · completed Mar 9, 2018 · Permit 16 118167 FSU

    Closed
  • Addition or alteration · Interior alterations

    Reinforcing to elevator for 10 stories betwn lines C&D adj line 1. Also new FAS (bsmt to 10th) and new sprinklers for the existing warehouse building

    Applied Feb 18, 2016 · issued Apr 7, 2016 · completed Mar 30, 2022 · Permit 16 118167 BLD

    Closed
  • Drains and site services · Site service

    Proposal to cap manhole in existing industrial building.

    Applied Oct 20, 2014 · issued Oct 21, 2014 · Permit 14 239952 STS

    Inspections under way

Committee of Adjustment

This address's applications to the City's Committee of Adjustment since 2017, and any still open. A minor variance asks for a small exception to the zoning by-law, such as a little more height or a smaller setback; a consent divides a lot or grants an easement.

  • Consent · Create new Easement/ROW

    To obtain consent to create an easement/right-of-way for the purpose of pedestrian ingress and egress.

    Decision: Approved (hearing Mar 28, 2018)

    Filed Sep 28, 2017 · File B0098/17TEY

    Closed
  • Minor variance · Other

    See C of A Dec A0607/16TEY Geospatial Mapping Inquiry see SM and emails.

    Decision: Withdrawn

    Filed Jul 18, 2017 · File A0784/17TEY

    Closed
  • Minor variance · NR addition

    To alter the redevelopment plan approved under Site Specific By-law 943-2015(OMB) by constructing a west one-storey glass addition for an office lobby, a west one-storey glass addition for a takeout restaurant, and a three-storey freight elevator addition on the north side of Block 3C.

    Decision: Approved (hearing May 30, 2017)

    Filed Jan 31, 2017 · File A0111/17TEY

    Closed
  • Consent · Sever lot

    To obtain consent to sever the property to create two lots. Note: The retained lot forms the lands within a draft plan of subdivision application (12 226212 STE 18 SB).

    Decision: Approved (hearing Jun 9, 2016)

    Filed Mar 2, 2016 · 1 new lot · File B0014/16TEY

    Closed

What’s planned nearby

Development sites within 500 m

  • 150-158 Sterling Road

    13 storeys · Mixed use

    50 m away · Site plan · Under review · filed Apr 22, 2022

    Under review
  • 158 Sterling Road

    31 storeys · 388 homes · Mixed use

    70 m away · Site plan · Under review · filed May 30, 2024

    Under review
  • 158-200 Sterling Road

    11 storeys · Non-residential

    120 m away · Site plan · Under review · filed Aug 15, 2022

    Under review
  • 72 Perth Avenue

    18 storeys · 262 homes · Residential

    310 m away · Site plan · Approved · filed Oct 15, 2021

    Approved
  • 1405 Bloor Street West

    19 storeys · 325 homes · Mixed use

    320 m away · Condominium · Under review · filed Nov 8, 2021

    Under review
  • 1319 Bloor Street West

    33 storeys · 634 homes · Mixed use

    330 m away · Site plan · Under review · filed Aug 30, 2021

    Under review

Neighbours’ Committee of Adjustment files within 250 m

  • 181 Sterling Rd · Minor variance

    To alter the development standards (as approved under Site Specific Zoning By-law 943-2015 (OMB), for a new 17-storey mixed-use building with 266 dwelling units, 2 retail units and 84 parking spaces within 2 levels of below grade garages (Block 4B) which is currently under construction, by reducing vehicular parking space sizes (length and width).

    70 m away · filed Jan 24, 2025 · Approved

  • 230 Sterling Rd · Minor variance

    To alter the existing two-storey townhouse dwelling by constructing a rear two-storey addition. The existing rear basement walkout stairs, rear ground floor concrete pad, and a portion of the rear ground floor deck will be demolished.

    180 m away · filed Aug 1, 2024 · Approved

  • 181 Sterling Rd · Minor variance

    To alter the development standards, as approved under Site Specific Zoning By-law 943-2015 (OMB), which include adding an additional storey, changes to the overall height, setbacks, and parking standards, for the approved 16-storey mixed-use building (currently under construction).

    70 m away · filed Aug 14, 2023 · Approved

  • 150 Sterling Rd · Minor variance

    To facilitate the redevelopment of this site for a new 14-storey mixed-use building with 181 residential dwelling units, ground level retail space, a child care facility, and underground parking.

    90 m away · filed Jan 31, 2023 · Approved

  • 128 Sterling Rd · Minor variance

    To permit additional interior floor area for an eating establishment in the basement and ground floor of the existing three-storey Industrial/Commercial building. No exterior construction is proposed.

    130 m away · filed Nov 24, 2022 · Approved

  • 150 Sterling Rd · Consent

    To obtain consent to create of new easements/rights-of-way for vehicular and pedestrian access, and utilities, as applicable.

    90 m away · filed Sep 9, 2022 · Approved

  • 228 Sterling Rd · Minor variance

    To alter the existing two-storey townhouse dwelling by rebuilding the existing front basement walkout. In total, there will be one primary unit and two secondary suites within this dwelling.

    170 m away · filed Mar 22, 2022 · Approved

  • 29 Perth Ave · Minor variance

    To alter the existing two-storey semi-detached dwelling by constructing a first storey side addition (integral garage). This proposal was previously approved through Minor Variance application A0148/22TEY, but was missing the two Minor Variances in this application.

    190 m away · filed Jan 28, 2022 · Approved

Everything planned in Davenport

From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.