Toronto address · Ward 14, Toronto-Danforth
2 Dingwall Ave
The City of Toronto has 4 building permits since 2017 (3 still open) and 1 Committee of Adjustment file on record for this address.
Building permits
Every permit the City lists for this address since 2017, and any still open from before, newest first.
- Revision issued
Small residential project · Multiple projects
Revision 01 - relocate rooms in basement, third floor - open to below has been added to the west of existing stair, structural changes to steel beam in the second floor framingProposal to construct a new two storey rear addition with roof top deck,construct a new second floor front addition, a new second floor front roof top deck, interior alterations. **** See C of A Decision ****
Applied Aug 31, 2021 · issued Oct 7, 2021 · Permit 21 144923 BLD (revision 01)
- Inspections under way
Heating and ventilation
HVAC - construct a new two storey rear addition with roof top deck,construct a new second floor front addition, a new second floor front roof top deck and a new second floor front roof top green roof
Applied Apr 23, 2021 · issued Apr 27, 2021 · Permit 21 144923 HVA
- Inspections under way
Small residential project · Multiple projects
Proposal to construct a new two storey rear addition with roof top deck,construct a new second floor front addition, a new second floor front roof top deck, interior alterations. **** See C of A Decision ****
Applied Apr 23, 2021 · issued Apr 27, 2021 · Permit 21 144923 BLD
- Closed
Plumbing
Plumbing - construct a new two storey rear addition with roof top deck,construct a new second floor front addition, a new second floor front roof top deck and a new second floor front roof top green roof
Applied Apr 23, 2021 · issued Apr 27, 2021 · completed Sep 27, 2023 · Permit 21 144923 PLB
Committee of Adjustment
This address's applications to the City's Committee of Adjustment since 2017, and any still open. A minor variance asks for a small exception to the zoning by-law, such as a little more height or a smaller setback; a consent divides a lot or grants an easement.
- Closed
Minor variance · R addition
To alter a 2 ½ semi-detached dwelling by constructing a two-storey rear addition with roof top deck, a second floor front addition with a front roof top deck, and a second floor front roof top green roof.
Decision: Approved (hearing Dec 11, 2019)
Filed Aug 2, 2019 · File A0861/19TEY
What’s planned nearby
Development sites within 500 m
No rezoning, site plan, subdivision or condominium file open within 500 m, and no pre-construction project on the site.
Neighbours’ Committee of Adjustment files within 250 m
198 Withrow Ave · Minor variance
To alter the existing three-storey semi-detached dwelling by constructing front and rear basement additions, and a rear three-storey addition with a third floor balcony. Also, to construct a new front basement walkout, a front porch with stairs, and a rear deck with stairs. In addition, to convert the rear two-storey ancillary building (abutting the laneway) into a one-car garage and interior staircase on the first level and office/habitable space on the second level.
230 m away · filed Nov 3, 2025 · Approved
7 Strathcona Ave · Minor variance
To alter the existing two-storey semi-detached dwelling by constructing a complete third storey addition with a rear juliet balcony and front (north) dormer, a front three storey addition and a partial front one-storey addition (north-west side). Also, a front basement extension, front and rear second floor canopies, a front covered porch with stairs, and a rear ground floor covered deck with stairs. The existing rear one-storey ancillary building (detached garage, abutting the laneway) will be maintained and unaltered.
220 m away · filed Oct 21, 2025 · Approved
260 Bain Ave · Minor variance
To alter the existing two-and-one-half-storey semi-detached dwelling by constructing a rear third storey addition and a third storey side (west) roof deck. The rear ground floor one-storey addition has been demolished and a new rear ground floor deck with stairs and as well as a rear basement walkout has already been constructed under approved Building Permit No. 24 172386 BLD 02 SR.
100 m away · filed May 23, 2025 · Approved
627 Carlaw Ave · Minor variance
To alter the existing two-storey detached dwelling by constructing a rear two-storey addition, a rear ground floor deck, and a front yard parking pad.
190 m away · filed Apr 9, 2025 · Approved
587 Carlaw Ave · Minor variance
To alter the existing two-and-one-half-storey detached dwelling by constructing a rear basement addition, rear ground floor deck with stairs, and a rear third storey balcony. Also, to construct a one-storey ancillary building (detached two-car garage) in the rear yard.
60 m away · filed Jan 29, 2025 · Approved
255 Bain Ave · Minor variance
To construct a new three-storey detached dwelling with a front porch, a third storey terrace (above the second floor at the southwest portion of the dwelling), and a rear ground floor deck. Also, to construct a new one-storey ancillary building (detached garage) in the rear yard, abutting the laneway.
120 m away · filed Dec 27, 2024 · Approved
601 Carlaw Ave · Minor variance
To construct a one-storey ancillary building (detached garage), in the rear yard, abutting the laneway.
120 m away · filed Jan 24, 2024 · Approved
10 Frizzell Ave · Minor variance
To alter the existing two-storey semi-detached dwelling by constructing a complete third storey addition with a front deck and a planter, a rear three-storey addition with a ground floor covered deck and stairs, as well as new front stairs and planters. Also, to construct a new one-storey ancillary building (detached garage), in the rear yard, abutting the laneway.
90 m away · filed Oct 27, 2023 · Approved
From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.