The City of Toronto has 7 building permits since 2017 (1 still open) and 1 Committee of Adjustment file on record for this address.
Building permits
Every permit the City lists for this address since 2017, and any still open from before, newest first.
- Cancelled
Temporary structure · Other temporary tents
Installation of Two 30'x75' and Two 30'x50' Temporary Tents for a two days community event in open parking lot area. Install on July 27th 2022 Removal on Aug 1st 2022
Applied Jul 19, 2022 · completed Dec 7, 2023 · Permit 22 178805 TPS
- Closed
Addition or alteration · Interior alterations
Proposal to enlarge existing dwelling unit in existing Church (The Good Shepherd Chaldean Church)
Applied May 13, 2022 · issued Aug 10, 2022 · completed Jun 26, 2024 · Permit 22 146341 BLD
- Closed
Heating and ventilation
HVAC - Proposal to enlarge existing dwelling unit in existing Church (The Good Shepherd Chaldean Church)
Applied May 13, 2022 · issued Aug 10, 2022 · completed Apr 24, 2023 · Permit 22 146341 HVA
- Closed
Plumbing
Plumbing - Proposal to enlarge existing dwelling unit in existing Church (The Good Shepherd Chaldean Church)
Applied May 13, 2022 · issued Aug 10, 2022 · completed Mar 18, 2023 · Permit 22 146341 PLB
- Inspections under way
Addition or alteration · Other
Construct new bell tower for place ot worship *Good Sheppard Chaldean Church*
Applied Nov 12, 2008 · issued Nov 20, 2008 · Permit 08 220627 BLD
- Closed (dormant)
Plumbing
Applied Jul 21, 1998 · issued Dec 25, 1998 · completed Jun 8, 2026 · Permit 98 252037 PLB
- Closed (dormant)
New building
NEW CHURCH
Applied Jul 21, 1998 · issued Dec 22, 1998 · completed Jun 8, 2026 · Permit 98 251273 BLD
Committee of Adjustment
This address's applications to the City's Committee of Adjustment since 2017, and any still open. A minor variance asks for a small exception to the zoning by-law, such as a little more height or a smaller setback; a consent divides a lot or grants an easement.
- Closed
Minor variance · New NR building
To construct a two-storey rectory.
Decision: Approved (hearing Feb 13, 2020)
Filed Nov 22, 2018 · File A0861/18EYK
What’s planned nearby
Development sites within 500 m
No rezoning, site plan, subdivision or condominium file open within 500 m, and no pre-construction project on the site.
Neighbours’ Committee of Adjustment files within 250 m
51 Signet Dr · Minor variance
To permit a parking deficiency to accommodate a proposed one-storey addition along the Fenmar Drive frontage.
160 m away · filed Jan 11, 2022 · Approved
51 High Meadow Pl · Minor variance
To construct a two-storey east side addition. A previous Committee of Adjusment application (A325/02NY) approved variances related to gross floor area and setbacks.
190 m away · filed Feb 8, 2019 · Approved
From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.