The City of Toronto has 21 building permits since 2017 (16 still open) on record for this address.

Building permits

Every permit the City lists for this address since 2017, and any still open from before, newest first.

  • Fire and security upgrade · Sprinklers

    Interior alterations to existing data centre at ground floor and upper level of existing (2) storey building

    Applied Aug 25, 2015 · completed May 9, 2025 · Permit 15 212561 FSU

    Cancelled
  • Designated structure · Other

    Proposal to construct an additional cooling tower within existing plant.

    Applied Jul 3, 2015 · issued Jan 15, 2016 · Permit 15 184536 DST

    Permit issued
  • Heating and ventilation

    Revision 01 - layout changesHVAC - Interior alterations to existing data centre at ground floor and upper level of existing (2) storey building

    Applied Sep 4, 2014 · completed May 9, 2025 · Permit 14 189084 HVA (revision 01)

    Cancelled
  • Plumbing

    Plumbing - Interior alterations to existing data centre at ground floor and upper level of existing (2) storey building

    Applied Sep 4, 2014 · issued Sep 11, 2014 · Permit 14 189084 PLB

    Inspections under way
  • Addition or alteration · Interior alterations

    Revision 01 - Several changes on both floors.Interior alterations to existing data centre at ground floor and upper level of existing (2) storey building

    Applied Aug 29, 2014 · issued Sep 19, 2014 · Permit 14 189084 BLD (revision 01)

    Revision issued
  • Fire and security upgrade

    FS - Sprinkler Shop Drawing - Interior alterations to existing data centre at ground floor and upper level of existing (2) storey building

    Applied Jul 28, 2014 · completed May 9, 2025 · Permit 14 189084 FSU

    Cancelled
  • Heating and ventilation

    HVAC - Interior alterations to existing data centre at ground floor and upper level of existing (2) storey building

    Applied Jul 11, 2014 · issued Aug 25, 2014 · Permit 14 189084 HVA

    Inspections under way
  • Addition or alteration · Interior alterations

    Interior alterations to existing data centre at ground floor and upper level of existing (2) storey building

    Applied Jul 11, 2014 · issued Aug 5, 2014 · Permit 14 189084 BLD

    Inspections under way
  • Heating and ventilation

    HVAC - interior alterations to data centre Pod D

    Applied Oct 16, 2012 · issued Feb 25, 2013 · Permit 12 263604 HVA

    Inspections under way
  • Plumbing

    Plumbing - interior alterations to data centre Pod D

    Applied Oct 16, 2012 · issued Feb 25, 2013 · Permit 12 263604 PLB

    Permit issued
  • Addition or alteration · Interior alterations

    interior alterations for data centre

    Applied Nov 5, 2010 · issued Feb 17, 2011 · completed Nov 27, 2022 · Permit 10 292167 BLD

    Closed
  • Plumbing

    Plumbing - interior alterations for data centre

    Applied Nov 5, 2010 · issued Feb 17, 2011 · Permit 10 292167 PLB

    Permit issued
Show 9 more permits
  • Heating and ventilation

    HVAC - interior alterations for data centre

    Applied Nov 5, 2010 · issued Feb 17, 2011 · Permit 10 292167 HVA

    Permit issued
  • Plumbing

    revision 1 adding more floor drains

    Applied Oct 20, 2010 · issued Nov 29, 2010 · Permit 10 239311 PLB (revision 01)

    Revision issued
  • Plumbing

    Plumbing - interior alterations for Data Centre and exterior concrete slab

    Applied Aug 13, 2010 · issued Oct 20, 2010 · Permit 10 239311 PLB

    Inspections under way
  • Heating and ventilation

    HVAC - interior alterations for Data Centre and exterior concrete slab

    Applied Aug 13, 2010 · issued Oct 20, 2010 · Permit 10 239311 HVA

    Inspections under way
  • Fire and security upgrade

    FS - Sprinkler Shop Drawing - To erect two (2) new enclosures for equipment adjacent to existing building.

    Applied Oct 23, 2009 · Permit 09 181047

    Application on hold
  • Plumbing

    Plumbing - To erect two (2) new enclosures for equipment adjacent to existing building.

    Applied Oct 21, 2009 · issued Dec 18, 2009 · Permit 09 181047 PLB

    Inspections under way
  • Drains and site services · Inside and outside drains

    Drain - Replacement of existing roofing system including downspouts - non structural

    Applied Sep 3, 2009 · issued Sep 23, 2009 · Permit 09 140888 STS

    Inspections under way
  • Plumbing

    Plumbing - To construct and addition (storage building to enclose generators) and interior alterations.

    Applied Aug 19, 2009 · issued Oct 2, 2009 · Permit 09 159466 PLB

    Inspections under way
  • Heating and ventilation

    HVAC - To construct and addition (storage building to enclose generators) and interior alterations.

    Applied Aug 19, 2009 · issued Dec 23, 2009 · completed Sep 18, 2026 · Permit 09 159466 HVA

    Closed (dormant)

Committee of Adjustment

No applications to the City's Committee of Adjustment for this address since 2017. That's where an owner asks for a minor variance (a small exception to the zoning by-law) or a consent to divide a lot.

What’s planned nearby

Development sites within 500 m

No rezoning, site plan, subdivision or condominium file open within 500 m, and no pre-construction project on the site.

Neighbours’ Committee of Adjustment files within 250 m

  • 345 Finchdene Sq · Minor variance

    To construct an auxiliary structure in the north side yard.

    220 m away · filed Aug 17, 2024 · Approved

  • 41 Pullman Crt · Minor variance

    Minor variance application to reduce the side yard setback.

    200 m away · filed May 12, 2023 · Approved

  • 345 Finchdene Sq · Minor variance

    To construct a one storey rear addition to the existing industrial building.

    220 m away · filed Apr 10, 2018 · Approved

Everything planned in Scarborough North

From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.