The City of Toronto has 19 building permits since 2017 (11 still open) on record for this address.
Building permits
Every permit the City lists for this address since 2017, and any still open from before, newest first.
- Revision issued
Addition or alteration · Interior alterations
REV 01: Revision to re-build the concrete floor slab (foundation).Proposal for interior alteratons for a new Press and Conveyor Tunnel in an existing industrial building - Deco Automotive
Applied Jul 16, 2025 · issued Aug 19, 2025 · Permit 24 130478 BLD (revision 01)
- Inspections under way
Addition or alteration · Interior alterations
Proposal for interior alteratons for a new Press and Conveyor Tunnel in an existing industrial building - Deco Automotive
Applied Mar 28, 2024 · issued Oct 1, 2024 · Permit 24 130478 BLD
- Permit issued
Plumbing
Plumbing - piping only, no fixturesProposal for interior alteratons for a new Press and Conveyor Tunnel in an existing industrial building - Deco Automotive
Applied Mar 28, 2024 · issued Oct 1, 2024 · Permit 24 130478 PLB
- Permit issued
Heating and ventilation
HVAC - Proposal for interior alteratons for a new Press and Conveyor Tunnel in an existing industrial building - Deco Automotive
Applied Mar 28, 2024 · issued Oct 1, 2024 · Permit 24 130478 HVA
- Cancelled
Temporary structure · Certified tents
Installation of a 30' x 60' certified (#14-219348) Clearspan tent at Deco Automotive's warehouse for the purpose of providing employees with a safe lunch room with COVID-19 protocols in mind. Tent to be installed on April 30, 201 - removal date to be determined based on Public Health Guidelines
Applied May 3, 2021 · completed Mar 15, 2024 · Permit 21 149505 TPS
- Inspections under way
Fire and security upgrade · Sprinklers
Proposal to replace corroded sprinkler main, remove and replace main only branch lines and existing sprinklers to remain. Sprinkler valve to be relocated for accessibility.
Applied Apr 25, 2018 · issued May 24, 2018 · Permit 18 148317 FSU
- Cancelled
Plumbing · Other
Proposal for rework of water meter including backflow preventor and distribution.
Applied Apr 13, 2016 · completed Mar 3, 2021 · Permit 16 139761 PSA
- Inspections under way
Drains and site services · Site service
Proposed upgrade of the domestic watermain from a 2" to a 6" for existing industrial building.
Applied Oct 14, 2015 · issued Nov 25, 2015 · Permit 15 237072 STS
- Cancelled
Drains and site services · Inside and outside drains
Drain - Proposal to construct an apron concrete pad to existing Deco Automotive
Applied Oct 4, 2013 · completed Aug 29, 2024 · Permit 13 244863 STS
- Inspections under way
Addition or alteration · Garage Repair/Reconstruction
Proposal to construct an apron concrete pad to existing Deco Automotive
Applied Oct 2, 2013 · issued Oct 11, 2013 · Permit 13 244863 BLD
- Revision issued
Addition or alteration · Interior alterations
Interior alteration, roof and exterior walls upgrade at north section of existing industrial building. Change of use from rail bay to E-coat line rehabilation. Revision 01: Changes to openings in north wall of building, stairs and interior wall at grid A1-14.
Applied Feb 6, 2013 · issued Apr 9, 2013 · Permit 12 189601 BLD (revision 01)
- Revision issued
Plumbing
Revision 01 - change to location of piping Plumbing - Interior alteration, roof and exterior walls upgrade at north section of existing industrial building. Change of use from rail bay to E-coat line rehabilation.
Applied Dec 17, 2012 · issued Jan 31, 2013 · Permit 12 189601 PLB (revision 01)
Show 7 more permits
- Inspections under way
Plumbing
Plumbing - Interior alteration, roof and exterior walls upgrade at north section of existing industrial building. Change of use from rail bay to E-coat line rehabilation.
Applied Sep 24, 2012 · issued Nov 23, 2012 · Permit 12 189601 PLB
- Inspections under way
Addition or alteration · Interior alterations
Interior alteration, roof and exterior walls upgrade at north section of existing industrial building. Change of use from rail bay to E-coat line rehabilation.
Applied Jun 8, 2012 · issued Jul 31, 2012 · Permit 12 189601 BLD
- Closed
Addition or alteration · Addition(s)
To install ramp enclosure for fork lift ramp
Applied Oct 27, 2003 · issued Dec 5, 2003 · completed Aug 20, 2026 · Permit 03 188813 BLD
- Closed
Addition or alteration · Addition(s)
Addition to truck off loading space shed. HVAC &, Plb. included.
Applied Dec 17, 2001 · issued Jul 25, 2002 · completed Aug 20, 2026 · Permit 01 203435 BLD
- Closed (dormant)
Addition or alteration · Other
Foundation for industrial building
Applied Jan 6, 1997 · issued Jan 28, 1997 · completed Jun 8, 2026 · Permit 97 083501 BLD
- Closed (dormant)
Addition or alteration · Interior alterations
''scap tunnel'' to industrial building
Applied Dec 17, 1996 · issued Dec 20, 1996 · completed Jun 8, 2026 · Permit 96 083648 BLD
- Closed (dormant)
Addition or alteration · Other
Foundation (revision to c78611)
Applied May 9, 1996 · issued Jun 4, 1996 · completed Jun 8, 2026 · Permit 96 083536 BLD
Committee of Adjustment
No applications to the City's Committee of Adjustment for this address since 2017. That's where an owner asks for a minor variance (a small exception to the zoning by-law) or a consent to divide a lot.
What’s planned nearby
Development sites within 500 m
- Approved
1 storeys · 22 homes · Residential
340 m away · Condominium · Approved · filed Aug 29, 2024
Neighbours’ Committee of Adjustment files within 250 m
None on file since 2017.
From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.