Toronto address · Ward 13, Toronto Centre
227 Gerrard St E
The City of Toronto has 14 building permits since 2017 (9 still open) and 1 Committee of Adjustment file on record for this address.
Building permits
Every permit the City lists for this address since 2017, and any still open from before, newest first.
- Revision issued
Heating and ventilation
REV 01 - Revision to mechanical suite layout.HVAC - Application to construct a seven storey mixed use building with 124 dwelling units, ground floor retail and 2 levels of underground parking garage
Applied Jul 11, 2025 · issued Sep 4, 2025 · Permit 24 160495 HVA (revision 01)
- Revision issued
Plumbing
REV 01 - Revision to mechanical suite layout.Plumbing - Application to construct a seven storey mixed use building with 124 dwelling units, ground floor retail and 2 levels of underground parking garage
Applied Jul 11, 2025 · issued Sep 4, 2025 · Permit 24 160495 PLB (revision 01)
- Approved
Alternative solution
Alternative solution proposal for standpipe (in connection with building permits 24 160495 )
Applied Dec 10, 2024 · completed Jan 3, 2025 · Permit 24 248858 ALT
- Closed
Partial permit · Partial permit - foundation
Part Permit - Foundation part permit in connection with application to construct a seven storey mixed use building with 124 dwelling units, ground floor retail and 2 levels of underground parking garage
Applied Jun 12, 2024 · issued Nov 29, 2024 · completed Dec 3, 2024 · Permit 24 160495 FND
- Closed
Partial permit · Partial permit - structural framing
Part Permit - Foundation part permit in connection with application to construct a seven storey mixed use building with 124 dwelling units, ground floor retail and 2 levels of underground parking garage
Applied Jun 12, 2024 · issued Nov 29, 2024 · completed Oct 27, 2025 · Permit 24 160495 STR
- Inspections under way
Plumbing
Plumbing - Application to construct a seven storey mixed use building with 124 dwelling units, ground floor retail and 2 levels of underground parking garage
Applied Jun 6, 2024 · issued Dec 3, 2024 · Permit 24 160495 PLB
- Inspections under way
New building
Application to construct a seven storey mixed use building with 124 dwelling units, ground floor retail and 2 levels of underground parking garage
Applied Jun 6, 2024 · issued Oct 27, 2025 · 116 homes added · Permit 24 160495 BLD
- Inspections under way
Drains and site services
Drain - Application to construct a seven storey mixed use building with 124 dwelling units, ground floor retail and 2 levels of underground parking garage
Applied Jun 6, 2024 · issued Nov 29, 2024 · Permit 24 160495 DRN
- Inspections under way
Heating and ventilation
HVAC - Application to construct a seven storey mixed use building with 124 dwelling units, ground floor retail and 2 levels of underground parking garage
Applied Jun 6, 2024 · issued Feb 3, 2025 · Permit 24 160495 HVA
- Permit issued
Drains and site services · Inside and outside drains
Drain - Application to construct a seven storey mixed use building with 124 dwelling units, ground floor retail and 2 levels of underground parking garage
Applied Jun 6, 2024 · issued Nov 29, 2024 · Permit 24 160495 STS
- Closed
Demolition
Proposal to demolish existing Beer Store; 1-storey mixed-use building proposed.
Applied May 10, 2023 · issued Jul 6, 2023 · completed Aug 30, 2025 · Permit 23 144010 DEM
- Permit issued
Addition or alteration · Shoring
Shoring and excavation for the purpose of soil remediation ONLY.
Applied Apr 26, 2023 · issued May 8, 2024 · Permit 23 138282 BLD
Show 2 more permits
- Closed
Plumbing · Backflow prevention devices (Water only)
Proposal to install one back flow prevention device to a retail store (The Beer Store)
Applied Feb 5, 2010 · issued Feb 10, 2010 · completed Oct 23, 2019 · Permit 10 114789 PSA
- Closed
Addition or alteration · Multiple projects
Exterior alterations (new facade and stucco work) to Beer Store.
Applied Jan 10, 2005 · issued Feb 14, 2005 · completed Dec 16, 2025 · Permit 05 101248 BLD
Committee of Adjustment
This address's applications to the City's Committee of Adjustment since 2017, and any still open. A minor variance asks for a small exception to the zoning by-law, such as a little more height or a smaller setback; a consent divides a lot or grants an easement.
- Closed
Minor variance · Other
To alter the development standards (as approved under Site Specific Zoning By-laws 887-2021(OLT) and 888-2021(OLT)), for a 7-storey mixed-use building, by increasing the number of dwelling units.
Decision: Approved (hearing Mar 20, 2024)
Filed Nov 10, 2023 · File A0074/24TEY
What’s planned nearby
Development sites within 500 m
- Under review
107 homes · Residential
20 m away · Condominium · Under review · filed Oct 27, 2021
- Under review
10 storeys · 60 homes · Mixed use
60 m away · Site plan · Under review · filed Jul 4, 2025
- Under review
10 storeys · Residential
200 m away · Condominium · Under review · filed Oct 26, 2021
- Now selling
- Under review
11 storeys · Mixed use
340 m away · Site plan · Under review · filed May 26, 2026
- Under appeal
39 storeys · 378 homes · Residential
360 m away · Site plan · Under appeal · filed Jul 6, 2023
Neighbours’ Committee of Adjustment files within 250 m
185 Gerrard St E · Minor variance
To construct a new four-storey apartment building with a west side courtyard area at the centre of the building, a front (north) green roof, and a maintenance equipment storage area on the roof level. There will be a total of 17 bicycle parking spaces on the lot and no vehicular parking spaces will be provided. Also, to construct a rear one-storey detached ancillary building (waste storage enclosure) on the southwest corner on the lot. There will be a total of 15 residential dwelling units (12 studio units and 3 one bedroom units) on the lot.
210 m away · filed Aug 28, 2026 · Hearing scheduled
380 Berkeley St · Minor variance
To alter the existing two-and-one-half-storey semi-detached dwelling by constructing a side (south) two storey addition. Also, to construct rear ground floor and second storey bay windows, a rear second storey balcony, and a rear third storey rooftop pergola and terrace extension (above the second storey roof).
220 m away · filed Apr 16, 2026 · Approved
183 Carlton St · Minor variance
To alter the existing two-and-one-half semi-detached building (houseplex), which is currently under construction (Building Permit 25 258356 BLD), by constructing a side (east) basement walkout with a flat roof canopy. Also, to maintain the existing rear second storey roof deck with stairs, and third storey roof deck. There will be two existing units and two new units for a total of four residential dwelling units on this lot (one unit occupying the basement level, two units occupying the first level, and one unit occupying the second and third levels).
220 m away · filed Apr 10, 2026 · Approved
311 Sherbourne St · Minor variance
To alter the existing three-storey mixed-use building by converting the storage room on the second and third levels into seven additional hostel suites (three on the second level, and four on the third level). The existing pharmacy and cafeteria on the ground level, 19 hostel suites on the second level, and 20 hostel suites on the third level will be maintained and unaltered.
110 m away · filed Apr 8, 2026 · Approved
388 Berkeley St · Minor variance
To alter the existing two-storey semi-detached dwelling by constructing a rear two-storey addition with a ground floor stair landing, and a side (south) basement walkout. The existing basement walkout and rear deck with be demolished, and a portion of the rear second storey roof will be reconstructed. Also, to construct one additional parking space (for a total of two parking spaces), abutting the laneway.
240 m away · filed Jan 12, 2026 · Approved
320 Ontario St · Minor variance
To alter the existing two-storey detached dwelling by constructing a rear two-storey addition with a ground floor covered deck. The existing rear one-storey addition and rear deck will be demolished.
200 m away · filed Apr 10, 2025 · Approved
311 Sherbourne St · Minor variance
To alter the existing three-storey commercial building (containing office uses) by converting the west half of the first storey, and the second and third storeys into a hotel use with a common use area located on the ground floor. The existing east half of the building and the existing pharmacy (located on the ground floor) will be maintained. There will be a total of 39 hotel rooms within this mixed-use building.
110 m away · filed Feb 5, 2025 · Approved
169 Carlton St · Minor variance
To construct a one-storey ancillary structure (carport), in the rear yard, abutting the laneway (Doctor O Lane), for two parking spaces.
240 m away · filed Oct 10, 2024 · Approved
From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.