Toronto address · Ward 4, Parkdale-High Park
239 Quebec Ave
The City of Toronto has 5 building permits since 2017 (5 still open) on record for this address.
Building permits
Every permit the City lists for this address since 2017, and any still open from before, newest first.
- Inspections under way
Small residential project · Multiple projects
Rebuild an existing second floor rear addition with deck above, interior alterations, new rear landing, raise third floor dormer height for existing stairs headroom.
Applied Apr 5, 2012 · issued Apr 17, 2012 · Permit 12 149909 BLD
- Inspections under way
Heating and ventilation
HVAC - Rebuild an existing second floor rear addition with deck above, interior alterations, new rear landing, raise third floor dormer height for existing stairs headroom.
Applied Apr 5, 2012 · issued May 10, 2012 · Permit 12 149909 HVA
- Inspections under way
Plumbing
Plumbing - Rebuild an existing second floor rear addition with deck above, interior alterations, new rear landing, raise third floor dormer height for existing stairs headroom.
Applied Apr 5, 2012 · issued Apr 17, 2012 · Permit 12 149909 PLB
- Inspections under way
Small residential project · Finishing basements
interior alterations and finishing of basement
Applied Mar 16, 2012 · issued Mar 22, 2012 · Permit 12 138077 BLD
- Inspections under way
Plumbing · Fixtures/Roof Drains: SFD
Proposal to replace piping and existing plumbing fixtures including raplacement of inside sanitary piping in basement.
Applied Mar 7, 2012 · issued Mar 7, 2012 · Permit 12 133645 PSA
Committee of Adjustment
No applications to the City's Committee of Adjustment for this address since 2017. That's where an owner asks for a minor variance (a small exception to the zoning by-law) or a consent to divide a lot.
What’s planned nearby
Development sites within 500 m
- Approved
70 homes · Residential
310 m away · Condominium · Approved · filed Mar 1, 2023
Neighbours’ Committee of Adjustment files within 250 m
216 Pacific Ave · Consent
To obtain consent to sever the property into two residential lots and to create a new easement/right-of-way.
230 m away · filed Sep 14, 2026 · Accepted
165 High Park Ave · Minor variance
To alter the existing two-and-one-half-storey detached dwelling by constructing front and rear third storey additions (dormers), a rear third storey balcony, and a rear ground floor deck with stairs. Also, to permit and maintain the existing front one storey addition (front porch enclosure). The existing rear one-storey ancillary building (garage/storage) will be altered within the limits of the zoning by-law(s).
150 m away · filed Apr 24, 2026 · Approved
178 Quebec Ave · Minor variance
To alter the existing two-and-one-half-storey semi-detached dwelling by constructing a rear one-storey addition with a deck and stairs. The existing secondary suite (located in the basement) will be removed.
190 m away · filed Jan 6, 2026 · Approved
232 High Park Ave · Minor variance
To construct an in-ground swimming pool in the rear yard of the property.
250 m away · filed Jul 16, 2024 · Approved
154 High Park Ave · Minor variance
To construct a new two-storey detached dwelling with a front integral garage, front and rear covered porches, a rear second storey balcony, a rear in-ground swimming pool, and a rear outdoor recreational court. Also, to construct a new one-storey ancillary building (cabana) in the rear yard.
110 m away · filed May 2, 2023 · Approved
267 Humberside Ave · Minor variance
To alter the existing two-storey detached dwelling by constructing a rear two-storey addition with a ground floor deck and to install a secondary suite within the basement. Also, to rebuild the enclosed front porch with stairs.
190 m away · filed Oct 14, 2022 · Approved
76 Pine Crest Rd · Minor variance
To alter the existing two-storey detached dwelling by constructing a below grade basement addition with a deck and staircase above, as well as an attached one-storey garage (for one parking space).
230 m away · filed May 12, 2022 · Approved
215 High Park Ave · Consent
To create a new easement/right-of-way in order to extend the existing easement/right-of-way for pedestrian access.
230 m away · filed Apr 8, 2022 · Approved
From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.