Toronto address · Ward 5, York South-Weston
24 Lapp St
The City of Toronto has 5 building permits since 2017 and 1 Committee of Adjustment file on record for this address.
Building permits
Every permit the City lists for this address since 2017, and any still open from before, newest first.
- Closed
Heating and ventilation
HVAC - To construct a new detached dwelling with a rear basement walkout. The existing rear detached garage will be maintained.
Applied Nov 1, 2018 · issued Nov 16, 2018 · completed Apr 5, 2019 · Permit 17 147982 HVA
- Closed
Drains and site services
Drain - To construct a new detached dwelling with a rear basement walkout. The existing rear detached garage will be maintained.
Applied Oct 31, 2018 · issued Oct 31, 2018 · completed Mar 20, 2019 · Permit 17 147982 DRN
- Closed
Plumbing
Plumbing - To construct a new detached dwelling with a rear basement walkout. The existing rear detached garage will be maintained.
Applied Apr 24, 2017 · issued Jul 6, 2017 · completed Oct 30, 2019 · Permit 17 147982 PLB
- Closed
New house · New building
To construct a new detached dwelling with a rear basement walkout. The existing rear detached garage will be maintained.
Applied Apr 24, 2017 · issued Jul 6, 2017 · completed Oct 31, 2019 · 1 home added · Permit 17 147982 BLD
- Closed
Demolition
Demo existing sfd due to fire damage
Applied Nov 2, 2016 · issued Apr 25, 2017 · completed Apr 5, 2019 · 1 home removed · Permit 16 245916 DEM
Committee of Adjustment
This address's applications to the City's Committee of Adjustment since 2017, and any still open. A minor variance asks for a small exception to the zoning by-law, such as a little more height or a smaller setback; a consent divides a lot or grants an easement.
- Closed
Minor variance · New R building
To construct a new detached dwelling with a rear basement walkout. The existing rear detached garage will be maintained.
Decision: Approved (hearing Mar 23, 2017)
Filed Feb 21, 2017 · File A0157/17EYK
What’s planned nearby
Development sites within 500 m
- Under appeal
12 storeys · 263 homes · Residential
120 m away · Rezoning · Under appeal · filed Mar 17, 2022
Neighbours’ Committee of Adjustment files within 250 m
47 Lapp St · Minor variance
To construct a new laneway suite in the rear yard.
80 m away · filed May 16, 2023 · Approved
26 Lapp St · Minor variance
To construct a two-storey rear addition and a new detached garage in the rear yard.
0 m away · filed May 24, 2022 · Approved
41 Lapp St · Minor variance
To construct a new detached garage.
60 m away · filed Mar 8, 2022 · Approved
268 Weston Rd · Minor variance
To legalize and to maintain the existing one-storey rear additon.
210 m away · filed Jan 6, 2021 · Approved
258 Weston Rd · Minor variance
To construct a basement walkout in the front yard and a new front porch.
240 m away · filed Dec 19, 2019 · Approved
109 Northland Ave · Minor variance
To construct a new detached dwelling.
250 m away · filed Dec 10, 2019 · Approved
422 Maybank Ave · Minor variance
To construct a new detached garage.
150 m away · filed Oct 16, 2019 · Approved
346 Weston Rd · Consent
Section 57(1) of The Planning Act allows the assignment of authority to the Secretary-Treasurer, Committee of Adjustment or his/her designate to approve a Validation of Title.
250 m away · filed May 29, 2019 · Approved
From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.