Toronto address · Ward 5, York South-Weston
247 Gary Dr
The City of Toronto has 2 building permits since 2017 (1 still open) on record for this address.
Building permits
Every permit the City lists for this address since 2017, and any still open from before, newest first.
- Closed
Drains and site services · Back water valve (Sewer only)
Applied Jun 13, 2024 · issued Jul 9, 2024 · completed Oct 22, 2024 · Permit 24 164700 DRN
- Inspections under way
Small residential project · Addition(s)
Rear two storey addition
Applied Dec 23, 2002 · issued Feb 26, 2003 · Permit 02 197549 BLD
Committee of Adjustment
No applications to the City's Committee of Adjustment for this address since 2017. That's where an owner asks for a minor variance (a small exception to the zoning by-law) or a consent to divide a lot.
What’s planned nearby
Development sites within 500 m
No rezoning, site plan, subdivision or condominium file open within 500 m, and no pre-construction project on the site.
Neighbours’ Committee of Adjustment files within 250 m
254 Gary Dr · Minor variance
To construct a new detached dwelling with an attached garage.
60 m away · filed Feb 19, 2026 · Approved
254 Gary Dr · Minor variance
To construct a new fourplex.
60 m away · filed Feb 19, 2026 · Approved
254 Gary Dr · Consent
To obtain consent to sever the property into two undersized residential lots.
60 m away · filed Feb 19, 2026 · Approved
17 Wendell Ave · Minor variance
To construct a one-storey front and rear addition, a new front porch and a rear yard deck. A previous Committee of Adjustment application (A0039/22EYK) approved variances relating to front yard setback, side yard setback, building length, first floor height, exterior stairs providing pedestrian access and driveway width.
110 m away · filed Jun 17, 2022 · Approved
17 Wendell Ave · Minor variance
To construct a one-storey front and rear addition, a new front porch and a rear yard deck.
110 m away · filed Jan 18, 2022 · Approved
24 Howbert Dr · Minor variance
To construct a new detached dwelling.
240 m away · filed Jul 27, 2018 · Approved
235 Gary Dr · Minor variance
To construct a one-storey rear addition.
60 m away · filed May 28, 2018 · Approved
273 Gary Dr · Minor variance
To construct a second storey rear addition.
130 m away · filed Mar 15, 2018 · Approved
From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.