Corktown Station (Ontario Line) Emergency Exit Building

The City of Toronto has 16 building permits since 2017 (11 still open) on record for this address.

Building permits

Every permit the City lists for this address since 2017, and any still open from before, newest first.

  • Fire and security upgrade

    FS - Sprinkler Shop Drawing - To construct new Ontario Line transit - Corktown Transit Station

    Applied May 28, 2026 · Permit 23 172470 FSU

    Application on hold
  • Conditional permit · Partial permit - structural framing

    Conditional Permit - Part Permit - To construct new Ontario Line transit - Corktown Transit Station

    Applied Dec 11, 2025 · issued Feb 19, 2026 · Permit 23 172470 STR

    Inspections under way
  • Plumbing

    Plumbing - To construct new Ontario Line transit - Corktown Transit Station

    Applied Dec 3, 2025 · issued Feb 19, 2026 · Permit 23 172470 PLB

    Inspections under way
  • Heating and ventilation

    HVAC - To construct new Ontario Line transit - Corktown Transit Station

    Applied Dec 2, 2025 · issued Feb 27, 2026 · Permit 23 172470 HVA

    Permit issued
  • Alternative solution

    Alternative solution related to standpipe for Corktown Station - ADS 39

    Applied Jul 17, 2025 · Permit 25 195337 ALT

    Deficiency notice issued
  • Alternative solution

    Proposal for Alternative Solution related to Station Emergency Power - Corktown Station - ADS 37

    Applied Jul 16, 2025 · Permit 25 194753 ALT

    Deficiency notice issued
  • Drains and site services

    Drain - To construct new Ontario Line transit - Corktown Transit Station

    Applied Mar 12, 2025 · issued Mar 25, 2025 · Permit 23 172470 DRN

    Inspections under way
  • Alternative solution

    Elevator shaft resistance rating - Corktown Station

    Applied Jan 8, 2025 · Permit 25 102313 ALT

    Deficiency notice issued
  • Alternative solution

    An alternative solution approach to building code compliance is proposed relative to the 2012 Ontario Building Code for the egress requirements in the rapid transit station

    Applied Dec 13, 2024 · Permit 24 250138 ALT

    Deficiency notice issued
  • Partial permit · Partial permit - foundation

    Part Permit - To construct new Ontario Line transit - Corktown Transit Station

    Applied Sep 24, 2024 · completed Feb 19, 2026 · Permit 23 172470 FND

    Superseded
  • Alternative solution

    Omission of sprinklers serving the escalator steel truss enclosures at OL- Corktown Station

    Applied Aug 2, 2024 · Permit 24 192173 ALT

    Deficiency notice issued
  • Partial permit · Partial permit - shoring

    Part Permit - To construct new Ontario Line transit - Corktown Transit Station

    Applied Feb 27, 2024 · completed Mar 17, 2025 · Permit 23 172470 SHO

    Superseded
Show 4 more permits
  • Temporary structure · Certified tents

    Proposal to erect 2 temporary certified tents; one 50m X 30m (#14-219343) and one 25m X 20m (#14-219338) for an archeological dig related to Metrolinx's Ontario Line Project. To be installed on November 8th, 2023 and dismantled on January 5th, 2024.

    Applied Nov 2, 2023 · issued Nov 7, 2023 · completed Dec 5, 2023 · Permit 23 221407 TPS

    Closed
  • Addition or alteration · Other

    Permit for secant wall/slurry wall in relation to new Corktown station. No excavation.

    Applied Oct 31, 2023 · issued Nov 28, 2023 · completed Dec 20, 2024 · Permit 23 220694 BLD

    Closed
  • New building

    To construct new Ontario Line transit - Corktown Transit Station

    Applied Jul 11, 2023 · Permit 23 172470 BLD

    Under review
  • Demolition

    Proposal to demolish the existing 2 storey retail store to the finished floor elevation.

    Applied Oct 8, 2021 · issued Nov 16, 2021 · completed Sep 23, 2022 · Permit 21 223820 DEM

    Closed

Committee of Adjustment

No applications to the City's Committee of Adjustment for this address since 2017. That's where an owner asks for a minor variance (a small exception to the zoning by-law) or a consent to divide a lot.

What’s planned nearby

Development sites within 500 m

Neighbours’ Committee of Adjustment files within 250 m

  • 550 Adelaide St E · Minor variance

    To alter the development standards as approved under Site Specific Zoning By-law 1306-2023, by increasing the maximum residential gross floor area from 19,800 m² to 24,000 m², the total gross floor area (for residential and non-residential uses) from 21,000 m² to 25,000 m², and the building height from 29 storeys (93 m) to 37 storeys (116.25 m). Also, to reduce the minimum required first storey height from 4.5 m to 2.74 m to accommodate the previously approved mezzanine within the automotive dealership. There will be a total of 302 residential dwelling units on this lot. A Site Plan Control a…

    220 m away · filed Aug 28, 2026 · Postponed

  • 280 King St E · Minor variance

    To permit laboratory and office uses within this existing building.

    180 m away · filed Jun 14, 2022 · Approved

  • 63 Berkeley St · Minor variance

    To convert the existing two-and-one-half-storey office building into a three-storey live-work unit by constructing a rear third storey addition.

    140 m away · filed Aug 13, 2021 · Approved

  • 63 Berkeley St · Minor variance

    To alter the existing three-storey commercial building by enclosing the rear third storey patio, constructing a rear first storey Juliette balcony and converting the building use to residential.

    140 m away · filed Feb 14, 2020 · Approved

  • 280 King St E · Consent

    To obtain consent to sever for the purpose of a lot addition.

    180 m away · filed Aug 20, 2018 · Approved

  • 280 King St E · Minor variance

    To maintain the existing eight-storey office building on a reduced lot that was created by Consent Application B0082/18TEY, which altered the northeast rear lot line.

    180 m away · filed Aug 20, 2018 · Approved

  • 501 Adelaide St E · Consent

    To obtain consent to create an easement/right-of-way for the purpose of vehicular passage, vehicular parking, pedestrian access, construction, maintenance and repair of the driveway.

    180 m away · filed Jun 6, 2018 · Approved

  • 351 King St E · Minor variance

    To modify the redevelopment plan for a 17-storey office building, approved under Site-specific By-law 818-2013 (as amended by Site-specific By-law 401-2014), by constructing a mezzanine within a ground floor eating establishment.

    120 m away · filed Jan 24, 2018 · Approved

Everything planned in Toronto Centre

From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.