Toronto address · Ward 11, University-Rosedale
27 Cluny Dr
The City of Toronto has 9 building permits since 2017 on record for this address.
Building permits
Every permit the City lists for this address since 2017, and any still open from before, newest first.
- Closed
Drains and site services
Revision to allow roof drainage down pipe from rear half of the roof to discharged onto grade in the rear yard rather than into the storm drainage pipe in the sub-basement level and the discharged water to flow over the surface to the rear catch basin for drainage. Also see STS revision.
Applied Dec 15, 2016 · issued Dec 21, 2016 · completed Mar 14, 2019 · Permit 15 230062 DRN (revision 02)
- Closed
Drains and site services · Site service
Revision to allow roof drainage down pipe from rear half of the roof to discharged onto grade in the rear yard rather than into the storm drainage pipe in the sub-basement level and the discharged water to flow over the surface to the rear catch basin for drainage. Also see DRN revision.
Applied Dec 15, 2016 · issued Dec 21, 2016 · completed Mar 14, 2019 · Permit 15 230268 STS (revision 02)
- Closed
Drains and site services
Revise below grade drains. Also see STS revision.
Applied Oct 13, 2016 · issued Oct 20, 2016 · completed Mar 14, 2019 · Permit 15 230062 DRN (revision 01)
- Closed
Drains and site services · Site service
Revise below grade drains. Also see DRN revision.
Applied Oct 13, 2016 · issued Oct 26, 2016 · completed Mar 14, 2019 · Permit 15 230268 STS (revision 01)
- Closed
Heating and ventilation
HVAC - Proposal to construct a 3 storey SFD with 2 basement levels. See PPR, COA, and Demo.
Applied Sep 29, 2015 · issued Feb 18, 2016 · completed Mar 14, 2019 · Permit 15 230062 HVA
- Closed
Drains and site services · Site service
Site servicing in connection to BLD 15 230062.
Applied Sep 29, 2015 · issued Mar 8, 2016 · completed Mar 14, 2019 · Permit 15 230268 STS
- Closed
Plumbing
Plumbing - Proposal to construct a 3 storey SFD with 2 basement levels. See PPR, COA, and Demo.
Applied Sep 29, 2015 · issued Feb 18, 2016 · completed Mar 14, 2019 · Permit 15 230062 PLB
- Closed
New house · New building
Proposal to construct a 3 storey SFD with 2 basement levels. See PPR, COA, and Demo.
Applied Sep 29, 2015 · issued Feb 18, 2016 · completed Mar 14, 2019 · 1 home added · Permit 15 230062 BLD
- Closed
Drains and site services
Drain - Proposal to construct a 3 storey SFD with 2 basement levels. See PPR, COA, and Demo.
Applied Sep 29, 2015 · issued Feb 18, 2016 · completed Mar 14, 2019 · Permit 15 230062 DRN
Committee of Adjustment
No applications to the City's Committee of Adjustment for this address since 2017. That's where an owner asks for a minor variance (a small exception to the zoning by-law) or a consent to divide a lot.
What’s planned nearby
Development sites within 500 m
- Approved
12 storeys · 24 homes · Mixed use
370 m away · Site plan · Approved · filed Nov 14, 2024
- Approved
- Under appeal
- Approved
2 storeys · Not stated in the file
460 m away · Site plan · Approved · filed Aug 19, 2025
- Approved
25 McMurrich Street and 906 Yonge Street
19 storeys · 401 homes · Mixed use
470 m away · Site plan · Approved · filed Nov 3, 2021
- Under review
1087-1091 Yonge Street and 9 Price Street
35 storeys · 235 homes · Mixed use
470 m away · Rezoning · Under review · filed May 28, 2025
Neighbours’ Committee of Adjustment files within 250 m
50 Crescent Rd · Minor variance
To alter the three-storey detached dwelling (currently under construction) by shifting the basement car lift and ground floor opening (car lift shaft area) closer to the front (south) lot line, resulting in an increase to the previously approved building length as approved under Minor Variance Decision A1247/21TEY.
130 m away · filed Mar 26, 2025 · Approved
78 Crescent Rd · Minor variance
To alter the existing three-storey detached dwelling by enclosing the existing third storey (west side) deck. Also, to construct a new rear third storey deck. There are three residential dwelling units on this site.
150 m away · filed Mar 18, 2025 · Deferred
25 Roxborough St E · Minor variance
To alter the existing two-and-one-half-storey detached dwelling by constructing a rear third storey addition with a balcony at the southeast corner, rear one-storey and two-storey additions (the existing rear addition will be demolished), a front basement walkout, a rear ground floor covered landing with stairs, and a rear ground floor deck.
210 m away · filed Dec 13, 2024 · Approved
12 Cluny Dr · Minor variance
To construct a new three-storey detached dwelling with an integral garage, partial second and third floor green roofs, a rear third floor rooftop terrace (above the second floor), and a rear ground floor terrace with an in-ground pool.
80 m away · filed Dec 13, 2024 · Approved
41 Roxborough St E · Minor variance
To alter the existing three-storey detached dwelling by constructing a third storey front addition with a front bay window. The existing ancillary building (detached garage, in the rear yard) will be maintained and unaltered. The site has heritage designation.
170 m away · filed Apr 17, 2024 · Approved
85 Crescent Rd · Minor variance
To alter the existing two-and-one-half-storey detached dwelling by constructing a rear three-storey addition, with a rear covered ground floor terrace, and a rear third storey balcony.
170 m away · filed Nov 23, 2023 · Approved
91 Crescent Rd · Minor variance
To alter the existing three-storey detached dwelling by constructing a rear three-storey addition, with a side east ground floor deck with staircase, a rear basement walkout, rear first storey juliette balconies, and a rear third storey deck.
210 m away · filed Nov 15, 2023 · Approved
25 Roxborough St E · Minor variance
To alter the existing two-and-one-half-storey detached dwelling by constructing a rear three-storey addition, with a west side basement walkout, a rear ground floor deck, and rear second and third storey roof decks. Also, to reconstruct the existing one-storey ancillary building (detached garage), in the rear yard.
210 m away · filed Mar 16, 2023 · Deferred
From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.