Toronto address · Ward 17, Don Valley North
30 Shaughnessy Blvd
Shaughnessy Public School
The City of Toronto has 2 building permits since 2017 (2 still open) on record for this address.
Building permits
Every permit the City lists for this address since 2017, and any still open from before, newest first.
- Inspections under way
Addition or alteration · Interior alterations
interior alterations to library revitalization
Applied Sep 28, 2021 · issued Jan 10, 2022 · Permit 21 218899 BLD
- Inspections under way
Designated structure · Solar collector
Installation of a rooftop photovoltaic arry on an existing building.
Applied Aug 1, 2017 · issued Sep 8, 2017 · Permit 17 209577 DST
Committee of Adjustment
No applications to the City's Committee of Adjustment for this address since 2017. That's where an owner asks for a minor variance (a small exception to the zoning by-law) or a consent to divide a lot.
What’s planned nearby
Development sites within 500 m
No rezoning, site plan, subdivision or condominium file open within 500 m, and no pre-construction project on the site.
Neighbours’ Committee of Adjustment files within 250 m
28 Elfindale Cres · Minor variance
To alter the existing dwelling by constructing a two-storey rear addition on the west side and a second storey front addition above the existing garage. Please note, this application was previously deferred by the Committee of Adjustment on July 24, 2025.
140 m away · filed Jun 16, 2025 · Approved
20 Parfield Dr · Minor variance
To construct a second floor addition,, and a new covered porch.
190 m away · filed Oct 7, 2020 · Approved
23 Parfield Dr · Minor variance
To construct a second storey addition over the attached garage of the existing dwelling, in conjunction with other interior and exterior alterations.
240 m away · filed Sep 22, 2020 · Approved
36 George Henry Blvd · Minor variance
To construct a new two storey addition in the front of the dwelling, and a second storey addition above the existing garage and family room. Please note, this application was previously deferred Thursday, November 21, 2019, in order to allow the applicant an opportunity to meet with City Planning and Transportation Services to discuss their concerns.
240 m away · filed Oct 11, 2019 · Approved
18 Parfield Dr · Minor variance
To construct a second storey addition on the existing dwelling
180 m away · filed Apr 3, 2019 · Approved
15 Skyview Cres · Minor variance
To construct a new covered porch to the east portion of the existing dwelling, in conjunction with a new canopy to front of the dwelling.
220 m away · filed May 5, 2017 · Approved
From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.