Toronto address · Ward 23, Scarborough North
30 Ulysses Pl
The City of Toronto has 4 building permits since 2017 (3 still open) on record for this address.
Building permits
Every permit the City lists for this address since 2017, and any still open from before, newest first.
- Inspections under way
Plumbing
Plumbing - Relocation of mechanical area to Southeast corner for convenient placement of new heat pump (replace ex. AC & gas furnace) and heat pump water heater (replace ex. gas water heater). All work in basement only incl. removing an ex. bathroom & adding a floor drain for the new mechanical area. Reinforcement of a load bearing wall and previously altered (assumed from install of ex. ductwork) floor joist to be done during replacement of ductwork. Mech. drawings originally submitted under permit #23 119258 MSA.
Applied Jul 4, 2023 · issued Jul 4, 2023 · Permit 23 132453 PLB
- Closed
Drains and site services
Drain - Relocation of mechanical area to Southeast corner for convenient placement of new heat pump (replace ex. AC & gas furnace) and heat pump water heater (replace ex. gas water heater). All work in basement only incl. removing an ex. bathroom & adding a floor drain for the new mechanical area. Reinforcement of a load bearing wall and previously altered (assumed from install of ex. ductwork) floor joist to be done during replacement of ductwork. Mech. drawings originally submitted under permit #23 119258 MSA.
Applied May 12, 2023 · issued May 26, 2023 · completed Jul 5, 2023 · Permit 23 132453 DRN
- Inspections under way
Small residential project · Interior alterations
Relocation of mechanical area to Southeast corner for convenient placement of new heat pump (replace ex. AC & gas furnace) and heat pump water heater (replace ex. gas water heater). All work in basement only incl. removing an ex. bathroom & adding a floor drain for the new mechanical area. Reinforcement of a load bearing wall and previously altered (assumed from install of ex. ductwork) floor joist to be done during replacement of ductwork. Mech. drawings originally submitted under permit #23 119258 MSA.
Applied Apr 11, 2023 · issued May 16, 2023 · Permit 23 132453 BLD
- Inspections under way
Heating and ventilation · HVAC: SFD/Semi/TH
Replace existing forced air heating with mixed ducted/ductless heat pump system
Applied Mar 2, 2023 · issued Sep 25, 2023 · Permit 23 119258 MSA
Committee of Adjustment
No applications to the City's Committee of Adjustment for this address since 2017. That's where an owner asks for a minor variance (a small exception to the zoning by-law) or a consent to divide a lot.
What’s planned nearby
Development sites within 500 m
- Under review
Neighbours’ Committee of Adjustment files within 250 m
36 Dunmail Dr · Minor variance
To construct a 2-storey dwelling rear addition. NOTE: This Revised Public Hearing Notice is being sent out to correctly identify all the variances being requested for variance 1.
210 m away · filed Jul 5, 2023 · Approved
From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.