The City of Toronto has 7 building permits since 2017 (7 still open) on record for this address.
Building permits
Every permit the City lists for this address since 2017, and any still open from before, newest first.
- Inspections under way
Drains and site services · Inside and outside drains
Drain - To construct new second floor level addition within an existing warehouse space, to create an office space. Propose partial interior alterations within the first storey warehouse area for office use.Proposed temporary electrical room next to an existing hydro vault at ground floor level. Phase One.This permit is for Phase One Only. (no new additions; interior alt only)
Applied May 8, 2015 · issued Jun 1, 2015 · Permit 12 293664 STS
- Revision issued
Addition or alteration · Multiple projects
Revision 02 - adding new washrooms on 2nd floor and convert 3500sqft on groundfloor to office space(Revision 01 - Construction of mezzanine (scope of work the same; however change of design team, therefore different drawings))(To construct new second floor level addition within an existing warehouse space, to create an office space. Propose partial interior alterations within the first storey warehouse area for office use.Proposed temporary electrical room next to an existing hydro vault at ground floor level. Phase One.This permit is for Phase One Only. (no new additions; interior alt only))
Applied Nov 28, 2013 · issued Dec 30, 2013 · Permit 12 293664 BLD (revision 02)
- Revision issued
Addition or alteration · Multiple projects
Revision 01 - Construction of mezzanine (scope of work the same; however change of design team, therefore different drawings)(To construct new second floor level addition within an existing warehouse space, to create an office space. Propose partial interior alterations within the first storey warehouse area for office use.Proposed temporary electrical room next to an existing hydro vault at ground floor level. Phase One.This permit is for Phase One Only. (no new additions; interior alt only))
Applied Jul 18, 2013 · issued Sep 3, 2013 · Permit 12 293664 BLD (revision 01)
- Inspections under way
Addition or alteration · Multiple projects
To construct new second floor level addition within an existing warehouse space, to create an office space. Propose partial interior alterations within the first storey warehouse area for office use.Proposed temporary electrical room next to an existing hydro vault at ground floor level. Phase One.This permit is for Phase One Only. (no new additions; interior alt only)
Applied Dec 13, 2012 · issued Mar 4, 2013 · Permit 12 293664 BLD
- Inspections under way
Heating and ventilation
HVAC - replace and relocate existing diesel generator to the outside and convert the generator room top to an electrical room.
Applied Jun 29, 2011 · issued Aug 5, 2011 · Permit 11 228941 HVA
- Inspections under way
Heating and ventilation
HVAC - Interior alteration on second floor of an office building to alter existing and to construct new washroom.
Applied Dec 23, 2010 · issued Jan 25, 2011 · Permit 10 319213 HVA
- Inspections under way
Plumbing
Plumbing - Interior alteration on second floor of an office building to alter existing and to construct new washroom.
Applied Dec 23, 2010 · issued Jan 25, 2011 · Permit 10 319213 PLB
Committee of Adjustment
No applications to the City's Committee of Adjustment for this address since 2017. That's where an owner asks for a minor variance (a small exception to the zoning by-law) or a consent to divide a lot.
What’s planned nearby
Development sites within 500 m
No rezoning, site plan, subdivision or condominium file open within 500 m, and no pre-construction project on the site.
Neighbours’ Committee of Adjustment files within 250 m
None on file since 2017.
From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.