The City of Toronto has 6 building permits since 2017 (4 still open) on record for this address.

Building permits

Every permit the City lists for this address since 2017, and any still open from before, newest first.

  • Fire and security upgrade

    FS - Sprinkler Shop Drawing - Proposal for Interior alteration includes demolition of existing premises, installation of new partitions, and the addition of a new plumbing

    Applied Jul 20, 2025 · Permit 25 155241 FSU

    Application on hold
  • Plumbing

    Plumbing - Proposal for Interior alteration includes demolition of existing premises, installation of new partitions, and the addition of a new plumbing

    Applied May 6, 2025 · issued Jul 28, 2025 · Permit 25 155241 PLB

    Inspections under way
  • Addition or alteration · Interior alterations

    Proposal for Interior alteration includes demolition of existing premises, installation of new partitions, and the addition of a new plumbing

    Applied May 6, 2025 · issued Jul 21, 2025 · Permit 25 155241 BLD

    Inspections under way
  • Heating and ventilation

    HVAC - Proposal for Interior alteration includes demolition of existing premises, installation of new partitions, and the addition of a new plumbing

    Applied May 6, 2025 · issued Jul 28, 2025 · Permit 25 155241 HVA

    Inspections under way
  • Addition or alteration · Interior alterations

    Proposal to construct new room within existing manufacturing building to house vacuum equipment. Changes to mechanical to suite new vacuum system.

    Applied Jun 22, 2018 · issued Jul 25, 2018 · completed Feb 6, 2019 · Permit 18 182871 BLD

    Closed
  • Heating and ventilation

    HVAC - Proposal to construct new room within existing manufacturing building to house vacuum equipment. Changes to mechanical to suite new vacuum system.

    Applied Jun 22, 2018 · issued Aug 9, 2018 · completed Feb 8, 2019 · Permit 18 182871 HVA

    Closed

Committee of Adjustment

No applications to the City's Committee of Adjustment for this address since 2017. That's where an owner asks for a minor variance (a small exception to the zoning by-law) or a consent to divide a lot.

What’s planned nearby

Development sites within 500 m

No rezoning, site plan, subdivision or condominium file open within 500 m, and no pre-construction project on the site.

Neighbours’ Committee of Adjustment files within 250 m

  • 18 Progress Ave · Minor variance

    To permit the addition of a second-storey to the building for expansion of the existing place of worship and community service uses. Overflow parking is to be accommodated on the adjacent property located at 12 Progress Avenue. NOTE: Site Plan Control Application 07 100252 ESC 40 SA was approved on September 23, 2009 for a place of worship and a day care facility.

    190 m away · filed Aug 13, 2021 · Refused

  • 1 William Kitchen Rd · Minor variance

    This application is for a proposal to reduce the parking requirement for the Kennedy Commons power centre. The zoning by-law requires parking to be provided at a minimum rate of 4.8 spaces/100 m2 of total gross floor area for financial institutions, personal service shop, restaurants, retail stores including lumber yards, building supply warehouses & places of entertainment, and 5.0 spaces/100 m2 for a fitness centre. The owners are requesting a variance to establish a new uniform rate of 3.8 spaces/100 m2 of total gross floor area.

    100 m away · filed Apr 30, 2014 · Approved

  • 30 Progress Ave · Minor variance

    Proposed place of worship in existing 816 square metre industrial building. Phase 1 to consist of Place of Worship in half the building with the other half remaining industrial uses. Phase II proposes entire use of building as place of worship

    120 m away · filed Jun 14, 2013 · Application withdrawn

Everything planned in Scarborough Centre

From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.