Toronto address · Ward 11, University-Rosedale
355 Clinton St
The City of Toronto has 5 building permits since 2017 and 1 Committee of Adjustment file on record for this address.
Building permits
Every permit the City lists for this address since 2017, and any still open from before, newest first.
- Closed
Plumbing
Rev01- revised Plumbing Data Sheet to include new info for a drain permit for new drain layout in the basement to accommodate relocation of basement bathroom/fixtures, as well as inclusion of a new sump pump.Plumbing - Proposal to construct a ground floor rear addition with a roof deck, interior alterations on the 2nd and 3rd floor, and new detached rear garage.
Applied Oct 4, 2022 · issued Oct 11, 2022 · completed May 24, 2024 · Permit 22 162429 PLB (revision 01)
- Closed
Drains and site services
Drain - Proposal to construct a ground floor rear addition with a roof deck, interior alterations on the 2nd and 3rd floor, and new detached rear garage.
Applied Oct 4, 2022 · issued Oct 6, 2022 · completed May 24, 2024 · Permit 22 162429 DRN
- Closed
Heating and ventilation
HVAC - Proposal to construct a ground floor rear addition with a roof deck, interior alterations on the 2nd and 3rd floor, and new detached rear garage.
Applied Oct 3, 2022 · issued Oct 4, 2022 · completed May 24, 2024 · Permit 22 162429 HVA
- Closed
Plumbing
Plumbing - Proposal to construct a ground floor rear addition with a roof deck, interior alterations on the 2nd and 3rd floor, and new detached rear garage.
Applied Jun 15, 2022 · issued Jul 29, 2022 · completed May 24, 2024 · Permit 22 162429 PLB
- Closed
Small residential project · Multiple projects
Proposal to construct a ground floor rear addition with a roof deck, interior alterations on the 2nd and 3rd floor, and new detached rear garage.
Applied Jun 15, 2022 · issued Jul 29, 2022 · completed May 24, 2024 · Permit 22 162429 BLD
Committee of Adjustment
This address's applications to the City's Committee of Adjustment since 2017, and any still open. A minor variance asks for a small exception to the zoning by-law, such as a little more height or a smaller setback; a consent divides a lot or grants an easement.
- Closed
Minor variance · R addition
To alter the existing 2½-storey semi-detached dwelling by constructing a one-storey rear addition, a rear deck and a rear second storey rooftop deck. Also, to construct a one-storey ancillary building (detached garage) in the rear yard, abutting the laneway.
Decision: Approved (hearing Mar 23, 2022)
Filed Nov 22, 2021 · File A1429/21TEY
What’s planned nearby
Development sites within 500 m
No rezoning, site plan, subdivision or condominium file open within 500 m, and no pre-construction project on the site.
Neighbours’ Committee of Adjustment files within 250 m
679 Euclid Ave · Minor variance
To alter the existing two-and-one-half storey semi-detached dwelling by constructing a rear one-storey ground floor addition with a second storey terrace above, and a new rear ground floor deck with stairs. The existing rear walkout basement, rear enclosed porch with stairs, and rear storage space will be demolished.
200 m away · filed Jun 16, 2026 · Hearing scheduled
270 Clinton St · Minor variance
To alter the existing two-storey semi-detached dwelling by constructing a complete thrid storey addition, a rear three-storey addition (at the southwest portion of the dwelling) with a basement addition below, a covered front porch with stairs, a rear third storey deck (above the second floor), a rear ground floor deck with stairs, and a rear basement walkout. Also, to construct a new one-storey detached ancillary building (two-car garage with a storage area) and a driveway, in the rear yard, abutting the laneway.
220 m away · filed Jan 21, 2026 · Approved
421 Grace St · Minor variance
To alter the existing two-and-one-half-storey semi-detached dwelling by constructing a rear second storey addition with a rear box bay window, a third storey addition with a rear partially covered rooftop deck and green roof (above the second floor), a new covered front porch with stairs (the enclosed portion of the existing front porch will be demolished), a front basement window well, and a rear entrance canopy.
200 m away · filed Sep 29, 2025 · Approved
684 Manning Ave · Minor variance
To construct a new three-storey detached dwelling (fourplex) with front and rear stairs (providing access to the ground level), front and rear second and third storey balconies, a rear waste bin enclosure, and two bicycle parking spaces. The existing rear one-storey ancillary building (detached garage, abutting the laneway) will be maintained and unaltered. There will be a total of four residential dwelling units on this lot.
180 m away · filed May 1, 2025 · Approved
699 Bloor St W · Minor variance
To alter the existing three-storey mixed-use building by reconstructing the rear second storey addition, and to construct a rear third storey covered terrace (above the new second storey addition). There will be one eating establishment that will occupy the ground floor and basement, and three residential dwelling units that will occupy the second and third floors of this building.
50 m away · filed Nov 4, 2024 · Approved
283 Clinton St · Minor variance
To alter the existing two-storey townhouse dwelling by constructing two-storey addition (along the north side wall), and a rear ground floor deck. The existing rear one-storey addition (mudroom) will be demolished.
210 m away · filed Jul 4, 2024 · Approved
381 Grace St · Minor variance
To construct a new two-storey ancillary building (containing a garden suite) with skylights, located in the rear yard of the existing two-storey semi-detached dwelling.
230 m away · filed Feb 17, 2023 · Approved
632 Euclid Ave · Minor variance
To alter the existing two-and-one-half-storey semi-detached dwelling by reconstructing the front porch and stairs, and constructing a new rear ground level deck. Also, to construct a one-storey ancillary building (detached garage) in the rear yard, abutting the laneway.
210 m away · filed Feb 7, 2023 · Approved
From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.