Building permits
Every permit the City lists for this address since 2017, and any still open from before, newest first.
- Revision issued
New building
Revision #3 - Reorganize 5 units see bubbled areas.Rev #02 - Proposal to reorganize (7) units.-cancelled Rev 01: DIVIDE 7 2-BEDROOM UNITS INTO 14 1-BEDROOM UNITS - SEE BUBBLED AREAS.Proposed construction of a new 8 storey condominium building with 2.5 levels of underground parking.
Applied Dec 8, 2020 · issued Jan 6, 2021 · 9 homes added · Permit 18 114665 BLD (revision 03)
- Revision issued
Heating and ventilation
Revision #2 was cancelled this is revision 3 to match the building plans. -Reorganize 5 units see bubbled area.Rev 01: DIVIDE 7 2-BEDROOM UNITS INTO 14 1-BEDROOM UNITS - SEE BUBBLED AREAS.HVAC - Proposed construction of a new 8 storey condominium building with 2.5 levels of underground parking.
Applied Dec 8, 2020 · issued Dec 16, 2020 · Permit 18 114665 HVA (revision 02)
- Revision issued
Plumbing
Rev #02 - Proposal to reorganize (7) units.Plumbing - Proposed construction of a new 8 storey condominium building with 2.5 levels of underground parking.
Applied Oct 6, 2020 · issued Oct 8, 2020 · Permit 18 114665 PLB (revision 02)
- Cancelled
New building
Rev #02 - Proposal to reorganize (7) units.Rev 01: DIVIDE 7 2-BEDROOM UNITS INTO 14 1-BEDROOM UNITS - SEE BUBBLED AREAS.Proposed construction of a new 8 storey condominium building with 2.5 levels of underground parking.
Applied Oct 5, 2020 · completed Oct 30, 2020 · Permit 18 114665 BLD (revision 02)
- Revision issued
Plumbing
Plumbing - Proposed construction of a new 8 storey condominium building with 2.5 levels of underground parking.
Applied Jul 24, 2020 · issued Aug 12, 2020 · Permit 18 114665 PLB (revision 01)
- Revision issued
Heating and ventilation
Rev 01: DIVIDE 7 2-BEDROOM UNITS INTO 14 1-BEDROOM UNITS - SEE BUBBLED AREAS.HVAC - Proposed construction of a new 8 storey condominium building with 2.5 levels of underground parking.
Applied Jul 13, 2020 · issued Aug 12, 2020 · Permit 18 114665 HVA (revision 01)
- Revision issued
New building
Rev 01: DIVIDE 7 2-BEDROOM UNITS INTO 14 1-BEDROOM UNITS - SEE BUBBLED AREAS.Proposed construction of a new 8 storey condominium building with 2.5 levels of underground parking.
Applied Jul 13, 2020 · issued Oct 27, 2020 · Permit 18 114665 BLD (revision 01)
- Closed
Conditional permit · New building
Conditional Permit - Proposed construction of a new 8 storey condominium building with 2.5 levels of underground parking.
Applied Sep 5, 2019 · issued Oct 9, 2019 · completed Jan 27, 2020 · Permit 18 114665 BLD
- Inspections under way
Drains and site services · Inside and outside drains
Drain - Proposed construction of a new 8 storey condominium building with 2.5 levels of underground parking.
Applied Nov 12, 2018 · issued Nov 19, 2018 · Permit 18 114665 STS
- Inspections under way
Drains and site services
Drain - Proposed construction of a new 8 storey condominium building with 2.5 levels of underground parking.
Applied Nov 9, 2018 · issued Dec 4, 2018 · Permit 18 114665 DRN
- Superseded
Partial permit · Partial permit - structural framing
Part Permit - Proposed construction of a new 8 storey condominium building with 2.5 levels of underground parking.
Applied Oct 26, 2018 · completed Oct 9, 2019 · Permit 18 114665 STR
- Cancelled
Partial permit · Partial permit - foundation
Part Permit - Proposed construction of a new 8 storey condominium building with 2.5 levels of underground parking.
Applied Sep 5, 2018 · completed Oct 31, 2018 · Permit 18 114665 FND
Show 8 more permits
- Closed
Partial permit · Partial permit - shoring
Part Permit - Proposed construction of a new 8 storey condominium building with 2.5 levels of underground parking.
Applied Aug 9, 2018 · issued Aug 24, 2018 · completed Oct 31, 2018 · Permit 18 114665 SHO
- Inspections under way
Plumbing
Plumbing - Proposed construction of a new 8 storey condominium building with 2.5 levels of underground parking.
Applied Feb 7, 2018 · issued Jun 4, 2019 · Permit 18 114665 PLB
- Inspections under way
Heating and ventilation
HVAC - Proposed construction of a new 8 storey condominium building with 2.5 levels of underground parking.
Applied Feb 7, 2018 · issued Jun 4, 2019 · Permit 18 114665 HVA
- Cancelled
Plumbing
Plumbing - Construction of a new 8 storey condominium building with 2.5 levels of underground parking
Applied Nov 17, 2017 · completed Jan 5, 2018 · Permit 17 264095 PLB
- Cancelled
New building
Construction of a new 8 storey condominium building with 2.5 levels of underground parking
Applied Nov 17, 2017 · completed Jan 5, 2018 · 99 homes added · Permit 17 264095 BLD
- Cancelled
Heating and ventilation
HVAC - Construction of a new 8 storey condominium building with 2.5 levels of underground parking
Applied Nov 17, 2017 · completed Jan 5, 2018 · Permit 17 264095 HVA
- Inspections under way
Demolition
Proposed demolition of existing building
Applied Sep 19, 2017 · issued Oct 11, 2017 · Permit 17 235384 DEM
- Cancelled
Heating and ventilation
HVAC - 110m2 temporary sales office
Applied Apr 8, 2014 · completed Feb 12, 2025 · Permit 14 139882 HVA
Committee of Adjustment
This address's applications to the City's Committee of Adjustment since 2017, and any still open. A minor variance asks for a small exception to the zoning by-law, such as a little more height or a smaller setback; a consent divides a lot or grants an easement.
- Closed
Minor variance · Other
To permit additional variances for the 9 storey apartment building consisting of 104 residential dwelling units. A previous Minor Variance application (A0189/20SC) considered by the Committee on September 23, 2020 refused a request for 106 units. The applicant has revised the application and wishes to return to the Committee.
Decision: Approved (hearing Nov 24, 2020)
Filed Oct 14, 2020 · File A0243/20SC
- Closed
Minor variance · Other
To permit additional variances for the 9 storey apartment building consisting of 106 residential dwelling units. A previous Committee of Adjustment application (A0035/19SC) permitted variances for lot coverage and floor area. The development was the subject of a combined Official Plan and Zoning By-law Amendment application (File No. 15 245019 ESC 36 OZ). On October 4, 2017, City Council approved the application and adopted amendments to the Scarborough Village Community Zoning By-law No. 10010 and the Toronto Zoning By-law No. 569-2013 to permit the development. The proposed building setback…
Decision: Refused (hearing Sep 23, 2020)
Filed Aug 18, 2020 · File A0189/20SC
- Closed
Minor variance · New R building
This application is for variances for a proposed nine storey residential building with 99 dwelling units at 3655 Kingston Road. The development was the subject of a combined Official Plan and Zoning By-law Amendment application (File No. 15 245019 ESC 36 OZ). On October 4, 2017, City Council approved the application and adopted amendments to the Scarborough Village Community Zoning By-law No. 10010 and the Toronto Zoning By-law No. 569-2013 to permit the development. The Zoning By-law amendments were based on incorrect site statistics. As a result, the amendment to the Scarborough Village Com…
Decision: Approved (hearing Feb 28, 2019)
Filed Feb 1, 2019 · File A0035/19SC
What’s planned nearby
Development sites within 500 m
- Under review
20 storeys · 384 homes · Residential
370 m away · Site plan · Under review · filed Apr 28, 2023
Neighbours’ Committee of Adjustment files within 250 m
44 Muir Dr · Minor variance
To construct a two-storey rear and north side addition and a second storey addition over the existing dwelling.
90 m away · filed Feb 16, 2017 · Approved
From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.