Sample data. These listings are fictional examples used to demonstrate the site. No MLS or board data is displayed.

Shaun Lovell, Real Estate SalespersonRight At Home Realty, Brokerage289-813-3318

Toronto address · Ward 14, Toronto-Danforth

375 Eastern Ave

The City of Toronto has 19 building permits since 2017 (13 still open) and 2 Committee of Adjustment files on record for this address.

Building permits

Every permit the City lists for this address since 2017, and any still open from before, newest first.

  • Temporary structure · Other temporary tents

    Proposed installation of 30'x40' Tent. Install is Sept 26th and removal is Sept 26th. Tent will be staked to ground

    Applied Sep 24, 2025 · completed Sep 28, 2025 · Permit 25 230028 TPS

    Cancelled
  • Drains and site services

    REV 01 - Revision to drain permitDrain - Proposal for New construction of East Harbour Transit Hub station at Lakeshore East rail corridor

    Applied Aug 22, 2025 · issued Sep 16, 2025 · Permit 24 250161 DRN (revision 01)

    Revision issued
  • Alternative solution

    Proposal for alternative solution related to fire protection and life safety, as they relate to East Harbour Transit Hub (Project), located in Toronto, ON

    Applied Jul 18, 2025 · completed Sep 2, 2025 · Permit 25 196114 ALT

    Approved
  • Drains and site services

    Drain - Proposal for New construction of East Harbour Transit Hub station at Lakeshore East rail corridor

    Applied May 27, 2025 · issued Jul 23, 2025 · Permit 24 250161 DRN

    Inspections under way
  • Drains and site services · Site service

    Drain - Proposal for New construction of East Harbour Transit Hub station at Lakeshore East rail corridor

    Applied May 27, 2025 · issued May 11, 2026 · Permit 24 250161 STS

    Permit issued
  • Alternative solution

    Alternative Solution: applicable building code requirements, relative to fire protection and life safety, as they relate to East Harbour Transit Hub (Project), located in Toronto, ON.Part 6

    Applied May 14, 2025 · completed Jul 18, 2025 · Permit 25 159189 ALT

    Approved
  • Alternative solution

    Alternative Solution: applicable building code requirements, relative to fire protection and life safety, as they relate to East Harbour Transit Hub (Project), located in Toronto, ON.Travel Distance within Service Areas

    Applied May 14, 2025 · completed Sep 29, 2025 · Permit 25 159168 ALT

    Approved
  • Alternative solution

    Alternative Solution: applicable building code requirements, relative to fire protection and life safety, as they relate to East Harbour Transit Hub (Project), located in Toronto, ON. Part 2

    Applied May 14, 2025 · completed Oct 7, 2025 · Permit 25 159173 ALT

    Approved
  • Alternative solution

    Alternative Solution: applicable building code requirements, relative to fire protection and life safety, as they relate to East Harbour Transit Hub (Project), located in Toronto, ON.Part 3

    Applied May 14, 2025 · completed Sep 22, 2025 · Permit 25 159178 ALT

    Approved
  • Alternative solution

    Alternative Solution: applicable building code requirements, relative to fire protection and life safety, as they relate to East Harbour Transit Hub (Project), located in Toronto, ON.Part 4Alternative solution for Fire Department Access ( additional description added by OBC examiner)

    Applied May 14, 2025 · completed Oct 7, 2025 · Permit 25 159183 ALT

    Approved
  • Alternative solution

    Alternative Solution: applicable building code requirements, relative to fire protection and life safety, as they relate to East Harbour Transit Hub (Project), located in Toronto, ON.Part 5

    Applied May 14, 2025 · completed Sep 26, 2025 · Permit 25 159187 ALT

    Approved
  • Temporary structure · Other temporary tents

    Proposal for Installation of one 30 x 40 frame tent for staff event. Installation date May 7th and removal May 9th

    Applied May 6, 2025 · completed May 9, 2025 · Permit 25 154646 TPS

    Cancelled
Show 7 more permits
  • Partial permit · Partial permit - foundation

    Part Permit - Proposal for New construction of East Harbour Transit Hub station at Lakeshore East rail corridor

    Applied Feb 25, 2025 · issued Apr 17, 2026 · completed Apr 20, 2026 · Permit 24 250161 FND

    Closed
  • Heating and ventilation

    HVAC - Proposal for New construction of East Harbour Transit Hub station at Lakeshore East rail corridor

    Applied Dec 13, 2024 · issued Apr 17, 2026 · Permit 24 250161 HVA

    Inspections under way
  • Plumbing

    Plumbing - Proposal for New construction of East Harbour Transit Hub station at Lakeshore East rail corridor

    Applied Dec 13, 2024 · issued Apr 17, 2026 · Permit 24 250161 PLB

    Inspections under way
  • New building

    Proposal for New construction of East Harbour Transit Hub station at Lakeshore East rail corridor

    Applied Dec 13, 2024 · issued Apr 20, 2026 · Permit 24 250161 BLD

    Inspections under way
  • Temporary structure · Certified tents

    Installation of one 30 x 40 frame tent (certified 14-219367) for staff BBQ. Installation date Oct 9 and removal October 11th

    Applied Oct 9, 2024 · issued Oct 11, 2024 · completed Sep 15, 2025 · Permit 24 224363 TPS

    Closed
  • Temporary structure · Certified tents

    Installation of one 30' x 40" frame tent (Cert#14 219367) anchored with stakes, for a staff BBQ on May 9 2024. Installation: May 8 2024 Removal: May 10 2024

    Applied May 13, 2024 · completed May 13, 2024 · Permit 24 147569 TPS

    Cancelled
  • Temporary structure · Other temporary tents

    Installation of one 30' x 40" frame tent (Cert#14 219367) anchored with stakes into ground for a staff BBQ on Friday September 15 2023. Installation to begin on sep 13 2023 and tent will be removed by Sep 18 2023

    Applied Sep 14, 2023 · issued Sep 15, 2023 · completed Sep 15, 2025 · Permit 23 202283 TPS

    Closed

Committee of Adjustment

This address's applications to the City's Committee of Adjustment since 2017, and any still open. A minor variance asks for a small exception to the zoning by-law, such as a little more height or a smaller setback; a consent divides a lot or grants an easement.

  • Consent · Re-establish Easement/ROW

    To obtain consent to create an easement/right-of-way for utilities.

    Decision: Approved (hearing Jul 26, 2017)

    Filed Apr 10, 2017 · File B0026/17TEY

    Closed
  • Consent · Re-establish Easement/ROW

    To obtain a consent to re-establish an easement/right-of-way for vehicular access.

    Decision: Approved (hearing Jul 26, 2017)

    Filed Mar 27, 2017 · File B0034/17TEY

    Closed

What’s planned nearby

Development sites within 500 m

Neighbours’ Committee of Adjustment files within 250 m

  • 64 Saulter St · Minor variance

    To alter the existing two-storey row house dwelling by constructing a complete third storey addition (attic space which will be used as habitable space).

    240 m away · filed Nov 13, 2025 · Approved

  • 18 Mc Gee St · Minor variance

    To alter the existing two-and-one-half-storey semi-detached dwelling by constructing a front porch canopy, a front second storey addition, and a complete third storey addition.

    180 m away · filed Oct 2, 2025 · Approved

  • 14 Mc Gee St · Minor variance

    To alter the existing two-and-one-half-storey semi-detached dwelling by constructing a complete third storey addition.

    180 m away · filed Jul 10, 2025 · Approved

  • 24 Lewis St · Consent

    To obtain consent to sever a portion of land for the purpose of a lot addition.

    180 m away · filed May 2, 2025 · Approved

  • 24 Lewis St · Minor variance

    To construct a new three-storey 16-unit apartment building that will span over 3 lots (municipally known as 24 Lewis Street, 26 Lewis Street and 26B Lewis Street). This apartment building will contain a total of six residential dwelling units, with front and rear basement walkouts, front and rear porches (platforms) with stairs, front and rear second storey balconies, front and rear rooftop patios with access enclosures, no long-term bicycle parking spaces, and no automobile parking spaces. Also, to construct a one-storey detached ancillary building in the rear yard (one garden suite) with a…

    180 m away · filed May 2, 2025 · Approved

  • 26 Lewis St · Minor variance

    To construct a new three-storey 16-unit apartment building that will span over 3 lots (municipally known as 24 Lewis Street, 26 Lewis Street and 26B Lewis Street). This apartment building will contain a total of four residential dwelling units, with front and rear basement walkouts, front and rear porches (platforms) with stairs, front and rear second storey balconies, front and rear rooftop patios with access enclosures, no long-term bicycle parking spaces, and no automobile parking spaces.

    180 m away · filed May 2, 2025 · Approved

  • 26 Lewis St · Consent

    To obtain consent to sever a portion of land for the purpose of a lot addition and to create new easements/rights-of-way.

    180 m away · filed May 2, 2025 · Approved

  • 44 Saulter St · Minor variance

    To alter the existing two-storey townhouse dwelling (with two residential dwelling units) by constructing a new rear second storey deck with stairs.

    180 m away · filed Feb 12, 2024 · Approved

Everything planned in Toronto-Danforth

From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.