The City of Toronto has 7 building permits since 2017 (3 still open) on record for this address.
Building permits
Every permit the City lists for this address since 2017, and any still open from before, newest first.
- Examiner's notice sent
Partial permit · Partial permit - foundation
Part Permit - Construct Milliken GO Transit station ancillary building, platforms, canopies, rail lines, pedestrian tunnels, parking, landscaping
Applied Aug 2, 2018 · Permit 18 177470 FND
- Examiner's notice sent
Partial permit · Partial permit - shoring
Part Permit - Construct Milliken GO Transit station ancillary building, platforms, canopies, rail lines, pedestrian tunnels, parking, landscaping
Applied Aug 2, 2018 · Permit 18 177470 SHO
- Approved
Alternative solution
AS-EXITINGConstruct Milliken GO Transit station ancillary building, platforms, canopies, rail lines, pedestrian tunnels, parking, landscaping
Applied Jun 13, 2018 · Permit 18 177496 ALT
- Pending cancellation
Addition or alteration · Multiple projects
Construct Milliken GO Transit station ancillary building, platforms, canopies, rail lines, pedestrian tunnels, parking, landscaping
Applied Jun 13, 2018 · Permit 18 177470 BLD
- Cancelled
Heating and ventilation
HVAC - Construct Milliken GO Transit station ancillary building, platforms, canopies, rail lines, pedestrian tunnels, parking, landscaping
Applied Jun 13, 2018 · completed Sep 18, 2019 · Permit 18 177470 HVA
- Cancelled
Plumbing
Plumbing - Construct Milliken GO Transit station ancillary building, platforms, canopies, rail lines, pedestrian tunnels, parking, landscaping
Applied Jun 13, 2018 · completed Sep 18, 2019 · Permit 18 177470 PLB
- Cancelled
Drains and site services · Inside and outside drains
Drain - Construct Milliken GO Transit station ancillary building, platforms, canopies, rail lines, pedestrian tunnels, parking, landscaping
Applied Jun 13, 2018 · completed Sep 18, 2019 · Permit 18 177470 STS
Committee of Adjustment
No applications to the City's Committee of Adjustment for this address since 2017. That's where an owner asks for a minor variance (a small exception to the zoning by-law) or a consent to divide a lot.
What’s planned nearby
Development sites within 500 m
No rezoning, site plan, subdivision or condominium file open within 500 m, and no pre-construction project on the site.
Neighbours’ Committee of Adjustment files within 250 m
4665 Steeles Ave E · Consent
To obtain consent to convert all existing temporary easements between 4665 Steeles Ave E (2321392 Ontario Ltd.) and 4675 Steeles Ave E (TSCC No. 1858) to permanent easements.
150 m away · filed Jun 14, 2018 · Application withdrawn
From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.