Sample data. These listings are fictional examples used to demonstrate the site. No MLS or board data is displayed.

Shaun Lovell, Real Estate SalespersonRight At Home Realty, Brokerage289-813-3318

Toronto address · Ward 6, York Centre

3933 Keele St

Finch West Station

The City of Toronto has 19 building permits since 2017 (8 still open) on record for this address.

Building permits

Every permit the City lists for this address since 2017, and any still open from before, newest first.

  • Alternative solution

    The Rapid Transit Stations of the Finch West LRT are required to comply with Section 3.13 of the OBC. Based on the acceptable solutions in the OBC, the fire alarm system at a rapid transit station is required to be monitored the central supervising station which is required to conform to CAN/ULC-S561, under the two following provisions:¿Sentence 3.13.5.4.(1): Each rapid transit station shall be monitored by a central supervising station conforming to CAN/ULC-S561, ¿Installation and Services for Fire Signal Receiving Centres and Systems¿, and¿Sentence 3.13.5.6.(2): The annunciator at a rapid t…

    Applied Nov 1, 2024 · completed Nov 28, 2024 · Permit 24 233965 ALT

    Approved
  • Alternative solution

    Finch West LRT Station (FWS) will be the terminus station at the east end of the Finch West Light Rail Transit (FWLRT) System. The station will be located at 3933 Keele Street, Toronto, ON. FWS is an enclosed station with an underground central platform. The platform will be accessible via the concourse level located below the platform which will in turn be connected to an at-grade entrance building. Additionally, the station will serve as an interchange station, providing FWLRT passengers with access to Line 1 of the TTC subway system via an underground walkway from the concourse.The design…

    Applied Mar 12, 2024 · completed Mar 12, 2024 · Permit 24 124469 000

    Cancelled
  • Alternative solution

    OBC does not permit the installation of electromagnetic locks on exit and access to exit doors serving floor areas in assembly occupancies which have occupant loads greaterthan 100 persons.

    Applied Mar 12, 2024 · completed Apr 23, 2024 · Permit 24 124581 ALT

    Approved
  • Fire and security upgrade · Electromagnetic locks

    Installation of eight electomagnetic locking devices

    Applied Jan 12, 2024 · issued Apr 23, 2024 · Permit 24 104174 FSU

    Permit issued
  • Alternative solution

    Omission of Strobe Lights in Public Areas of FWS

    Applied Feb 23, 2023 · completed Dec 13, 2023 · Permit 23 116949 ALT

    Approved
  • Alternative solution

    n lieu of providing a 1-h fire-rating or wired glass for the elevator shafts, a qualitative engineering analysis of the elevators, their shafts, and their surrounding areas have been conducted to demonstrate that the proposed elevator shafts will not negatively impact the fire and life safety strategy of the station. Further, this analysis has determined that the proposed 0-h elevator shafts will be able to achieve an equivalent level of performance to that required by Division B of the OBC and meet all applicable objectives and functional statements

    Applied Nov 16, 2022 · completed Dec 12, 2022 · Permit 22 230028 ALT

    Approved
  • Alternative solution

    Number of exists from fan plant area at Finch West Station (FWLRT)

    Applied Mar 18, 2022 · completed Sep 29, 2022 · Permit 22 124146 ALT

    Approved
  • Alternative solution

    Extended travel distance from west ancillary space - Finch West Station - (FWLRT)

    Applied Mar 18, 2022 · completed Aug 19, 2022 · Permit 22 124148 ALT

    Approved
  • Conditional permit · Partial permit - structural framing

    Conditional Permit - Part Permit - Construction of the Finch West Station - end terminal of the FWLRT

    Applied Oct 25, 2021 · issued Dec 3, 2021 · completed Feb 4, 2022 · Permit 19 242126 STR

    Closed
  • Alternative solution

    Omit sprinklers in the steel truss escalator enclosures

    Applied Sep 27, 2021 · completed Nov 12, 2021 · Permit 21 217910 ALT

    Approved
  • Conditional permit · Partial permit - foundation

    Conditional Permit - Part Permit - Construction of the Finch West Station - end terminal of the FWLRT

    Applied Mar 19, 2021 · issued Jun 14, 2021 · completed Dec 3, 2021 · Permit 19 242126 FND

    Closed
  • Conditional permit · Partial permit - shoring

    Conditional Permit - Part Permit - Construction of the Finch West Station - end terminal of the FWLRT Installation of Piling on private property only and no excavation for Finch West Stn, part of the Finch West LRT.

    Applied Dec 2, 2019 · issued Jan 30, 2020 · completed Jun 14, 2021 · Permit 19 242126 SHO

    Closed
Show 7 more permits
  • Heating and ventilation

    HVAC - Construction of the Finch West Station - end terminal of the FWLRT

    Applied Oct 29, 2019 · issued Dec 3, 2021 · completed Aug 21, 2025 · Permit 19 242126 HVA

    Closed
  • Drains and site services

    Drain - Construction of the Finch West Station - end terminal of the FWLRT

    Applied Oct 29, 2019 · issued Jun 14, 2021 · completed Aug 20, 2025 · Permit 19 242126 DRN

    Closed
  • Plumbing

    Plumbing - Construction of the Finch West Station - end terminal of the FWLRT

    Applied Oct 29, 2019 · issued Dec 3, 2021 · completed Aug 20, 2025 · Permit 19 242126 PLB

    Closed
  • Drains and site services · Site service

    Site Services - FWLRT - End terminalDrain - Construction of the Finch West Station - end terminal of the FWLRT

    Applied Oct 29, 2019 · issued Feb 3, 2022 · completed Aug 20, 2025 · Permit 19 242126 STS

    Closed
  • New building

    Construction of the Finch West Station - end terminal of the FWLRT

    Applied Oct 28, 2019 · issued Dec 15, 2023 · completed Aug 28, 2025 · Permit 19 242126 BLD

    Closed
  • Drains and site services · Site service

    Temporary site services for construction site

    Applied Oct 22, 2019 · issued Oct 28, 2019 · completed Oct 30, 2025 · Permit 19 239323 STS

    Closed
  • Demolition

    Petro Canada - One storey service station

    Applied Sep 18, 2008 · issued Oct 10, 2008 · completed Jan 19, 2017 · Permit 08 204847 DEM

    Closed

Committee of Adjustment

No applications to the City's Committee of Adjustment for this address since 2017. That's where an owner asks for a minor variance (a small exception to the zoning by-law) or a consent to divide a lot.

What’s planned nearby

Development sites within 500 m

Neighbours’ Committee of Adjustment files within 250 m

  • 3915 Keele St · Minor variance

    To alter the existing commercial building by constructing a one-storey addition (storage space) on the north side of the building.

    150 m away · filed Apr 30, 2025 · Approved

  • 3905 Keele St · Minor variance

    The proposal to request a relief from minimum number of parking required for a day nursery with outdoor play areas.(The application was deferred from the hearing of 15 August 2024)

    190 m away · filed Jul 2, 2024 · Approved

Everything planned in York Centre

From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.