Toronto address · Ward 7, Humber River-Black Creek
3950 Keele St
Finch West Station
The City of Toronto has 12 building permits since 2017 (2 still open) on record for this address.
Building permits
Every permit the City lists for this address since 2017, and any still open from before, newest first.
- Permit issued
Addition or alteration · Interior alterations
Interior alterations to the concourse level of Finch West Subway station to relocate and exiting faregate line and Presto vending machines
Applied Jun 29, 2022 · issued Nov 8, 2022 · Permit 22 169794 BLD
- Closed
Heating and ventilation
Revision 01 - to TTC Finch West Station for the mechanical systemHVAC - Finch West subway station and Bus terminal at Keele for the Spadina Subway Extension.. West subway entrance at 3950 Keele. East subway entrance and bus terminal at 3965 Keele.
Applied Nov 2, 2017 · issued Nov 27, 2017 · completed May 18, 2018 · Permit 11 107269 HVA (revision 01)
- Closed
Drains and site services · Inside and outside drains
Revision 01 - to TTC Finch West Station for the site servicingDrain - Finch West subway station and Bus terminal at Keele for the Spadina Subway Extension.. West subway entrance at 3950 Keele. East subway entrance and bus terminal at 3965 Keele.
Applied Nov 2, 2017 · issued Dec 5, 2017 · completed May 18, 2018 · Permit 11 107269 STS (revision 01)
- Closed
New building
Revision 01 - to TTC Finch West Station for the architectural, structural and fire alarm systemFinch West subway station and Bus terminal at Keele for the Spadina Subway Extension.. West subway entrance at 3950 Keele. East subway entrance and bus terminal at 3965 Keele.
Applied Nov 2, 2017 · issued Dec 5, 2017 · completed Feb 19, 2019 · Permit 11 107269 BLD (revision 01)
- Closed
Plumbing
Revision 01 - to TTC Finch West Station for the plumbing systemPlumbing - Finch West subway station and Bus terminal at Keele for the Spadina Subway Extension.. West subway entrance at 3950 Keele. East subway entrance and bus terminal at 3965 Keele.
Applied Nov 2, 2017 · issued Dec 5, 2017 · completed May 18, 2018 · Permit 11 107269 PLB (revision 01)
- Approved
Alternative solution
Alternative Solution relating to the proposed omission of fire hose cabinetsin the train tunnels within 20 m of the platform at the Finch West Subway Station
Applied Jan 9, 2017 · completed Feb 26, 2017 · Permit 17 102271 ALT
- Closed
Conditional permit · New building
STRUCTURAL Conditional Permit - Finch West Bus terminal at Keele for the Spadina Subway Extension. West subway entrance at 3950 Keele including East subway entrance and bus terminal at 3965 Keele.
Applied Oct 25, 2011 · issued Feb 8, 2012 · completed Oct 20, 2017 · Permit 11 107269 STR (revision 01)
- Closed
Conditional permit · New building
STRUCTURAL Conditional Permit - Finch West subway station ONLY at Keele for the Spadina Subway Extension.. West subway entrance at 3950 Keele. Does not include East subway entrance and bus terminal at 3965 Keele
Applied Apr 26, 2011 · issued Jun 2, 2011 · completed Oct 20, 2017 · Permit 11 107269 STR
- Closed
Plumbing
Plumbing - Finch West subway station and Bus terminal at Keele for the Spadina Subway Extension.. West subway entrance at 3950 Keele. East subway entrance and bus terminal at 3965 Keele.
Applied Feb 9, 2011 · issued Jun 12, 2012 · completed May 18, 2018 · Permit 11 107269 PLB
- Closed
Heating and ventilation
HVAC - Finch West subway station and Bus terminal at Keele for the Spadina Subway Extension.. West subway entrance at 3950 Keele. East subway entrance and bus terminal at 3965 Keele.
Applied Feb 9, 2011 · issued Jun 15, 2012 · completed May 18, 2018 · Permit 11 107269 HVA
- Closed
Drains and site services · Inside and outside drains
Drain - Finch West subway station and Bus terminal at Keele for the Spadina Subway Extension.. West subway entrance at 3950 Keele. East subway entrance and bus terminal at 3965 Keele.
Applied Feb 9, 2011 · issued Jun 12, 2012 · completed May 18, 2018 · Permit 11 107269 STS
- Closed
New building
Finch West subway station and Bus terminal at Keele for the Spadina Subway Extension.. West subway entrance at 3950 Keele. East subway entrance and bus terminal at 3965 Keele.
Applied Jan 14, 2011 · issued Oct 20, 2017 · completed Feb 19, 2019 · Permit 11 107269 BLD
Committee of Adjustment
No applications to the City's Committee of Adjustment for this address since 2017. That's where an owner asks for a minor variance (a small exception to the zoning by-law) or a consent to divide a lot.
What’s planned nearby
Development sites within 500 m
- Under review
43 storeys · 1,100 homes · Mixed use
170 m away · Rezoning · Under review · filed Dec 27, 2023
- Under review
1285-1325 Finch Avenue West and 30 Tangiers Road
15 storeys · 803 homes · Residential
210 m away · Site plan · Under review · filed Apr 29, 2022
Neighbours’ Committee of Adjustment files within 250 m
None on file since 2017.
From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.