The City of Toronto has 62 building permits since 2017 (15 still open) and 2 Committee of Adjustment files on record for this address.

Building permits

Every permit the City lists for this address since 2017, and any still open from before, newest first.

  • Heating and ventilation

    Hvac - proposed new mechanical cooling units, and interior alterations.

    Applied Feb 9, 2026 · issued Mar 13, 2026 · Permit 26 114741 HVA

    Inspections under way
  • Addition or alteration · Other

    Proposed new mechanical cooling units, and interior alterations.

    Applied Feb 9, 2026 · issued Mar 13, 2026 · Permit 26 114741 BLD

    Inspections under way
  • Addition or alteration · Other

    REVISION - revised layoutNEW MECHANICAL COOLING UNITS, AND INTERIOR ALTERATIONS.

    Applied Nov 24, 2025 · issued Feb 24, 2026 · completed Jul 3, 2026 · Permit 25 121674 BLD (revision 02)

    Closed
  • Addition or alteration · Other

    Rev 01: interior layout changes, relocate exit doors (see cover letter)NEW MECHANICAL COOLING UNITS, AND INTERIOR ALTERATIONS.

    Applied Jul 3, 2025 · issued Aug 26, 2025 · completed Jul 3, 2026 · Permit 25 121674 BLD (revision 01)

    Closed
  • Heating and ventilation

    Hvac - new mechanical cooling units, and interior alterations.

    Applied Feb 25, 2025 · issued Jul 8, 2025 · completed Jun 2, 2026 · Permit 25 121674 HVA

    Closed
  • Addition or alteration · Other

    New mechanical cooling units, and interior alterations.

    Applied Feb 25, 2025 · issued Apr 8, 2025 · completed Jul 3, 2026 · Permit 25 121674 BLD

    Closed
  • Fire and security upgrade · Sprinklers

    Alter existing Vesda system and Pre-action sprinkler system to suite new Hot Aisle Containment as per the NFPA requirements.

    Applied Oct 30, 2023 · issued Nov 3, 2023 · completed Mar 1, 2024 · Permit 23 220331 FSU

    Closed
  • Fire and security upgrade · Electromagnetic locks

    Provide the second floor VTL/TAPE silo room entry and exit points ( 2 Locations) with an electromagnetic locking susthem that complies with both the OBC, and associated modifications to the fire alarm system to accommodate the 2 new electromagnetic locks and power door operator.

    Applied Feb 14, 2023 · issued Mar 17, 2023 · Permit 23 113663 FSU

    Inspections under way
  • Addition or alteration · Interior alterations

    Proposal for interior alterations to an existing bank - BMO

    Applied Jul 12, 2022 · issued Sep 13, 2022 · Permit 22 175469 BLD

    Inspections under way
  • Plumbing

    Plumbing - Proposal for interior alterations to an existing bank - BMO

    Applied Jul 12, 2022 · issued Sep 13, 2022 · Permit 22 175469 PLB

    Inspections under way
  • Heating and ventilation

    HVAC - Proposal for interior alterations to an existing bank - BMO

    Applied Jul 12, 2022 · issued Sep 13, 2022 · Permit 22 175469 HVA

    Inspections under way
  • Addition or alteration · Multiple projects

    REVISION 03 - Proposal to update the design of fire protection and suppression system.Revision 02 - RELOCATION OF FIRE RATED SEPARATION FROM GRID LINE "F" TO "Fx" REFER TO PLANRevision 01 - REVISION TO BUILDING PERMIT #20-181761 BLD TO INCLUDE: - ELECTRICAL ROOM (291); - CORRIDOR; - WAITING AREA (290); - ATM LAB (293)Proposal for a new mechanical room cooling units building addition and interior alterations in the exsiting office building (BMO SCC CCB DATA CENTER FITOUT).

    Applied May 10, 2022 · issued Jul 8, 2022 · completed Oct 2, 2022 · Permit 20 181761 BLD (revision 03)

    Closed
Show 50 more permits
  • Addition or alteration · Multiple projects

    Revision 02 - RELOCATION OF FIRE RATED SEPARATION FROM GRID LINE "F" TO "Fx" REFER TO PLANRevision 01 - REVISION TO BUILDING PERMIT #20-181761 BLD TO INCLUDE: - ELECTRICAL ROOM (291); - CORRIDOR; - WAITING AREA (290); - ATM LAB (293)Proposal for a new mechanical room cooling units building addition and interior alterations in the exsiting office building (BMO SCC CCB DATA CENTER FITOUT).

    Applied Sep 28, 2021 · issued Oct 20, 2021 · completed Oct 2, 2022 · Permit 20 181761 BLD (revision 02)

    Closed
  • Heating and ventilation

    Revision 01 - REVISION TO BUILDING PERMIT #20-181761 BLD TO INCLUDE: - ELECTRICAL ROOM (291); - CORRIDOR; - WAITING AREA (290); - ATM LAB (293)HVAC - Proposal for a new mechanical room cooling units building addition and interior alterations in the exsiting office building (BMO SCC CCB DATA CENTER FITOUT).

    Applied Apr 8, 2021 · issued Apr 14, 2021 · completed Aug 2, 2022 · Permit 20 181761 HVA (revision 01)

    Closed
  • Plumbing

    Revision 01 - REVISION TO BUILDING PERMIT #20-181761 BLD TO INCLUDE: - ELECTRICAL ROOM (291); - CORRIDOR; - WAITING AREA (290); - ATM LAB (293)Plumbing - Proposal for a new mechanical room cooling units building addition and interior alterations in the exsiting office building (BMO SCC CCB DATA CENTER FITOUT).

    Applied Apr 8, 2021 · issued Apr 14, 2021 · completed Aug 2, 2022 · Permit 20 181761 PLB (revision 01)

    Closed
  • Fire and security upgrade · Electromagnetic locks

    Electromagnetic lock permit for door 285a

    Applied Apr 7, 2021 · issued May 7, 2021 · completed Oct 2, 2022 · Permit 21 137082 FSU

    Closed
  • Addition or alteration · Multiple projects

    Revision 01 - REVISION TO BUILDING PERMIT #20-181761 BLD TO INCLUDE: - ELECTRICAL ROOM (291); - CORRIDOR; - WAITING AREA (290); - ATM LAB (293)Proposal for a new mechanical room cooling units building addition and interior alterations in the exsiting office building (BMO SCC CCB DATA CENTER FITOUT).

    Applied Apr 7, 2021 · issued Jun 7, 2021 · completed Oct 2, 2022 · Permit 20 181761 BLD (revision 01)

    Closed
  • Heating and ventilation

    Revision #01 - HVAC - Changes to reduce the scope of interior ductwork - Bank of Montreal - Building C - Floor 3

    Applied Mar 14, 2021 · issued Mar 18, 2021 · completed Jan 24, 2024 · Permit 19 254054 HVA (revision 02)

    Closed
  • Plumbing

    Revision #01 - Changes to reduce the scope of interior work - Bank of Montreal - Building C - Floor 3

    Applied Mar 14, 2021 · issued Mar 18, 2021 · completed Jan 24, 2024 · Permit 19 254054 PLB (revision 02)

    Closed
  • Heating and ventilation

    Revision #01 - HVAC - Changes to reduce the scope of interior ductwork.HVAC - Interior Alterations to Bank of Montreal - Building C - Floor 3

    Applied Dec 22, 2020 · completed Jan 25, 2021 · Permit 19 254054 HVA (revision 01)

    Cancelled
  • Plumbing

    Revision #01 - Changes to reduce the scope of interior work.Plumbing - Interior Alterations to Bank of Montreal - Building C - Floor 3

    Applied Dec 22, 2020 · completed Jan 25, 2021 · Permit 19 254054 PLB (revision 01)

    Cancelled
  • Addition or alteration · Interior alterations

    Revision #01 - Changes to reduce the scope of interior work.Interior Alterations to Bank of Montreal - Building C - Floor 3

    Applied Dec 22, 2020 · issued Mar 2, 2021 · Permit 19 254054 BLD (revision 01)

    Revision issued
  • Heating and ventilation

    HVAC - Proposal for a new mechanical room cooling units building addition and interior alterations in the exsiting office building (BMO SCC CCB DATA CENTER FITOUT).

    Applied Aug 17, 2020 · issued Dec 4, 2020 · completed Aug 2, 2022 · Permit 20 181761 HVA

    Closed
  • Plumbing

    Plumbing - Proposal for a new mechanical room cooling units building addition and interior alterations in the exsiting office building (BMO SCC CCB DATA CENTER FITOUT).

    Applied Aug 17, 2020 · issued Dec 4, 2020 · completed Aug 2, 2022 · Permit 20 181761 PLB

    Closed
  • Addition or alteration · Multiple projects

    Proposal for a new mechanical room cooling units building addition and interior alterations in the exsiting office building (BMO SCC CCB DATA CENTER FITOUT).

    Applied Aug 17, 2020 · issued Dec 4, 2020 · completed Oct 2, 2022 · Permit 20 181761 BLD

    Closed
  • Heating and ventilation

    HVAC - Interior Alterations to Bank of Montreal - Building C - Floor 3

    Applied Jan 23, 2020 · issued Jan 24, 2020 · completed Jan 24, 2024 · Permit 19 254054 HVA

    Closed
  • Plumbing

    Plumbing - Interior Alterations to Bank of Montreal - Building C - Floor 3

    Applied Jan 23, 2020 · issued Jan 24, 2020 · completed Jan 24, 2024 · Permit 19 254054 PLB

    Closed
  • Addition or alteration · Interior alterations

    Interior Alterations to Bank of Montreal - Building C - Floor 3

    Applied Nov 26, 2019 · issued Jan 20, 2020 · Permit 19 254054 BLD

    Inspections under way
  • Addition or alteration · Interior alterations

    Proposed interior alterations to accommodate the replacement of a high-voltage switch in an existing office space.

    Applied Sep 15, 2019 · issued Oct 15, 2019 · Permit 19 221393 BLD

    Inspections under way
  • Heating and ventilation

    HVAC - Proposed interior alterations to accommodate the replacement of a high-voltage switch in an existing office space.

    Applied Sep 15, 2019 · issued Oct 15, 2019 · completed Feb 1, 2022 · Permit 19 221393 HVA

    Closed
  • Addition or alteration · Interior alterations

    Interior alterations to the 3rd floor washrooms upgrades

    Applied Feb 28, 2019 · issued Mar 19, 2019 · Permit 19 120258 BLD

    Inspections under way
  • Plumbing

    Plumbing - Interior alterations to the 3rd floor washrooms upgrades

    Applied Feb 28, 2019 · issued Mar 19, 2019 · completed Dec 7, 2023 · Permit 19 120258 PLB

    Closed
  • Heating and ventilation

    HVAC - Interior alterations to the 3rd floor washrooms upgrades

    Applied Feb 28, 2019 · issued Mar 19, 2019 · completed Dec 7, 2023 · Permit 19 120258 HVA

    Closed
  • Heating and ventilation

    HVAC - Interior alterations to office space and addition of servery space (sinks) in cafeteria on 3rd floor (main floor) of existing building, upgrades to tables and flooring in cafeteria

    Applied Feb 11, 2019 · issued Mar 11, 2019 · completed Nov 19, 2019 · Permit 19 114293 HVA

    Closed
  • Plumbing

    Plumbing - Interior alterations to office space and addition of servery space (sinks) in cafeteria on 3rd floor (main floor) of existing building, upgrades to tables and flooring in cafeteria

    Applied Feb 11, 2019 · issued Mar 11, 2019 · completed Nov 19, 2019 · Permit 19 114293 PLB

    Closed
  • Addition or alteration · Interior alterations

    Interior alterations to office space and addition of servery space (sinks) in cafeteria on 3rd floor (main floor) of existing building, upgrades to tables and flooring in cafeteria

    Applied Feb 11, 2019 · issued Mar 11, 2019 · completed Jan 28, 2020 · Permit 19 114293 BLD

    Closed
  • Plumbing

    Plumbing - Proposal for alterations to office cafeteria space

    Applied Jan 28, 2019 · issued Feb 11, 2019 · completed Nov 19, 2019 · Permit 19 109087 PLB

    Closed
  • Addition or alteration · Interior alterations

    Interior alterations - washroom is fixtures and finishes refresh. (floors 1-4)

    Applied Jan 28, 2019 · issued Feb 11, 2019 · completed Mar 30, 2025 · Permit 19 109140 BLD

    Closed
  • Addition or alteration · Interior alterations

    Proposal for alterations to office cafeteria space

    Applied Jan 28, 2019 · issued Feb 11, 2019 · completed Jan 28, 2020 · Permit 19 109087 BLD

    Closed
  • Heating and ventilation

    Hvac - interior alterations - washroom is fixtures and finishes refresh. (floors 1-4)

    Applied Jan 28, 2019 · issued Feb 11, 2019 · completed Dec 7, 2023 · Permit 19 109140 HVA

    Closed
  • Heating and ventilation

    HVAC - Proposal for alterations to office cafeteria space

    Applied Jan 28, 2019 · issued Feb 11, 2019 · completed Nov 19, 2019 · Permit 19 109087 HVA

    Closed
  • Plumbing

    Plumbing - INTERIOR ALTERATIONS - WASHROOM IS FIXTURES AND FINISHES REFRESH. (FLOORS 1-4)

    Applied Jan 28, 2019 · issued Feb 11, 2019 · completed Dec 7, 2023 · Permit 19 109140 PLB

    Closed
  • Fire and security upgrade · Sprinklers

    Additional sprinklers unit 02-04

    Applied Nov 21, 2018 · issued Nov 22, 2018 · completed Aug 1, 2019 · Permit 18 259391 FSU

    Closed
  • Heating and ventilation

    HVAC - Proposed Interior Alterations to existing office space on floor 02.

    Applied Oct 4, 2018 · issued Nov 5, 2018 · completed Aug 19, 2019 · Permit 18 237723 HVA

    Closed
  • Addition or alteration · Interior alterations

    Proposed Interior Alterations to existing office space on floor 02.

    Applied Oct 4, 2018 · issued Nov 5, 2018 · completed Oct 11, 2019 · Permit 18 237723 BLD

    Closed
  • Fire and security upgrade · Electromagnetic locks

    REV. #1 -revised notes and specs for mag locksProposal to install two mag locks in the new enclosed access corridor

    Applied Dec 9, 2016 · issued Dec 16, 2016 · completed Feb 13, 2018 · Permit 15 268429 FSU (revision 01)

    Closed
  • Fire and security upgrade · Electromagnetic locks

    Proposal to install two mag locks in the new enclosed access corridor

    Applied Dec 23, 2015 · issued Jan 5, 2016 · completed Feb 13, 2018 · Permit 15 268429 FSU

    Closed
  • Drains and site services · Site service

    Proposal to relocate storm and sanitary sewers to accommodate a new generator plant and to add two catch basins (CB 4 &5) and two manholes MH6B & MH9)

    Applied Dec 23, 2015 · issued Jan 27, 2016 · Permit 15 268534 STS

    Inspections under way
  • Addition or alteration · Multiple projects

    REV #1-GENERATOR PLANT ENCLOSURE & EMERGENCY PLANT, INTERIOR ALTERATIONS TO MEETING ROOM FOR BMOinterior alterations to office area, add floor area adjacent to office, new venting for hvac

    Applied Aug 31, 2015 · issued Feb 8, 2016 · completed Jul 28, 2020 · Permit 15 165486 BLD (revision 01)

    Closed
  • Heating and ventilation

    REV #1-GENERATOR PLANT ENCLOSURE & EMERGENCY PLANT, INTERIOR ALTERATIONS TO MEETING ROOM FOR BMOHVAC - interiro alterations to office area, add floor area adjacent to office, new venting for hvac

    Applied Aug 31, 2015 · issued Dec 17, 2015 · completed Mar 16, 2020 · Permit 15 165486 HVA (revision 01)

    Closed
  • Fire and security upgrade

    FS - Sprinkler Shop Drawing - interiror alterations to office area, add floor area adjacent to office, new venting for hvac

    Applied Aug 21, 2015 · completed Jul 3, 2020 · Permit 15 165486 FSU

    Closed
  • Drains and site services · Site service

    Proposal to relocate existing storm and sanitary sewers

    Applied Aug 5, 2015 · issued Aug 14, 2015 · Permit 15 202217 STS

    Inspections under way
  • Heating and ventilation

    HVAC - interiro alterations to office area, add floor area adjacent to office, new venting for hvac

    Applied May 29, 2015 · issued Aug 24, 2015 · completed Mar 16, 2020 · Permit 15 165486 HVA

    Closed
  • Addition or alteration · Multiple projects

    interiror alterations to office area, add floor area adjacent to office, new venting for hvac

    Applied May 29, 2015 · issued Aug 24, 2015 · completed Jul 28, 2020 · Permit 15 165486 BLD

    Closed
  • Heating and ventilation

    HVAC - interior alterations to staff entrance vestibule

    Applied Jul 22, 2011 · issued Aug 22, 2011 · completed Dec 7, 2023 · Permit 11 244048 HVA

    Closed
  • Addition or alteration · Interior alterations

    interior alterations to staff entrance vestibule

    Applied Jul 22, 2011 · issued Aug 9, 2011 · Permit 11 244048 BLD

    Permit issued
  • Addition or alteration · Interior alterations

    interior alterations to add in air conditioner

    Applied Jun 1, 2011 · issued Jul 8, 2011 · Permit 11 207432 BLD

    Permit issued
  • Heating and ventilation

    HVAC - interior alterations to add in air conditioner

    Applied Jun 1, 2011 · issued Jul 8, 2011 · completed Dec 7, 2023 · Permit 11 207432 HVA

    Closed
  • Plumbing

    revision #1 for base building upgrades for cafeteria renovations and the Tim Hortons installation

    Applied May 11, 2011 · issued May 31, 2011 · completed May 31, 2018 · Permit 10 315781 PLB (revision 01)

    Closed
  • Plumbing

    Plumbing - Adding a Tim Horton's kiosk to existing building

    Applied Dec 16, 2010 · issued Jan 24, 2011 · completed May 31, 2018 · Permit 10 315781 PLB

    Closed
  • Fire and security upgrade

    FS - Sprinkler Shop Drawing - interior alterations to existing resource centre, storage rooms, and 2nd flr to classrooms

    Applied Sep 27, 2010 · Permit 10 252611 FSU

    Application on hold
  • Heating and ventilation

    HVAC - Demolish Walls, add doors

    Applied Sep 21, 2009 · issued Oct 28, 2009 · completed Aug 19, 2020 · Permit 09 170992 HVA

    Closed

Committee of Adjustment

This address's applications to the City's Committee of Adjustment since 2017, and any still open. A minor variance asks for a small exception to the zoning by-law, such as a little more height or a smaller setback; a consent divides a lot or grants an easement.

  • Minor variance · Other

    To alter the development standards for the employment development as it relates to parking.

    Decision: Approved (hearing Dec 3, 2025)

    Filed Oct 8, 2025 · File A0220/25SC

    Closed
  • Consent · Sever lot

    Proposal to sever the existing property into two land parcels/lots and create a private sewer easement. There are no associated minor variance applications with this severance proposal. NOTE: The application was deferred on October 13, 2022 in order to allow additional time for City of Toronto staff to finalize comments on the proposed severance of the property.

    Decision: Approved (hearing Nov 10, 2022)

    Filed Feb 8, 2022 · 1 new lot · File B0009/22SC

    Closed

What’s planned nearby

Development sites within 500 m

No rezoning, site plan, subdivision or condominium file open within 500 m, and no pre-construction project on the site.

Neighbours’ Committee of Adjustment files within 250 m

  • 3550 Pharmacy Ave · Minor variance

    To alter the development standards for the employment development as it relates to parking.

    180 m away · filed Oct 17, 2025 · Approved

Everything planned in Scarborough-Agincourt

From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.