Toronto address · Ward 14, Toronto-Danforth
42 Carlaw Ave
The City of Toronto has 4 Committee of Adjustment files on record for this address.
Building permits
The City lists no building permits for this address since 2017, and none still open from before.
Committee of Adjustment
This address's applications to the City's Committee of Adjustment since 2017, and any still open. A minor variance asks for a small exception to the zoning by-law, such as a little more height or a smaller setback; a consent divides a lot or grants an easement.
- Conditional consent
Consent · Lot addition
To obtain consent to sever a portion of the land for the purpose of a lot addition.
Decision: Approved (hearing Mar 18, 2026)
Filed Dec 2, 2025 · File B0075/25TEY
- Conditional consent
Consent · Sever lot
To obtain consent to sever the lot into two undersized residential lots.
Decision: Approved (hearing Mar 18, 2026)
Filed Jan 20, 2025 · 2 new lots · File B0006/25TEY
- Closed
Minor variance · New R building
To construct a new three-storey semi-detached dwelling (houseplex) with a front porch with stairs and rear balconies at the first and second storeys will be constructed. There will be a total of two residential dwelling units on this lot (one unit occupying the basement and ground floor levels and one unit occupying the second and third levels). The rear one-storey ancillary building (garage) will be demolished.
Decision: Approved (hearing Mar 18, 2026)
Filed Aug 28, 2024 · File A0855/24TEY
- Closed
Minor variance · New R building
To construct a new three-storey semi-detached dwelling (houseplex) with a front porch with stairs and rear balconies at the first and second storeys will be constructed. There will be a total of two residential dwelling units on this lot (one unit occupying the basement and ground floor levels and one unit occupying the second and third levels). The rear one-storey ancillary building (garage) will be demolished.
Decision: Approved (hearing Mar 18, 2026)
Filed Aug 28, 2024 · File A0854/24TEY
What’s planned nearby
Development sites within 500 m
- Under appeal
- Approved
462 Eastern Avenue and 150 Logan Avenue
1 storeys · Residential
310 m away · Condominium · Approved · filed Oct 21, 2024
- Under review
30 Booth Avenue, 21 Don Valley Parkway and 433 Eastern Avenue
48 storeys · Residential
420 m away · Site plan · Under review · filed Apr 27, 2023
- Approved
9 storeys · 78 homes · Mixed use
470 m away · Site plan · Approved · filed May 3, 2023
Neighbours’ Committee of Adjustment files within 250 m
103 Morse St · Minor variance
140 m away · filed Sep 16, 2026 · Accepted
21 Carlaw Ave · Minor variance
50 m away · filed Aug 25, 2026 · Postponed
555 Eastern Ave · Minor variance
To alter the existing one-storey, four-unit, commercial building by converting Unit 1 (abutting Eastern Avenue and Heward Avenue) into a showroom and vehicle service shop (BMW). There will be a total of five car lifts and four motorcycle repair bays within this unit. Also, five vehicular parking spaces (including two accessible parking spaces) will be provided on-site.
160 m away · filed Aug 18, 2025 · Approved
64 Logan Ave · Minor variance
To alter the existing three-storey semi-detached dwelling by enclosing the rear third storey roof deck for habitable space (new bedroom).
210 m away · filed Jul 25, 2025 · Approved
66 Logan Ave · Minor variance
To alter the existing three-storey semi-detached dwelling by enclosing the rear third storey roof deck for habitable space (new bedroom).
210 m away · filed Jul 25, 2025 · Approved
46 Carlaw Ave · Consent
To obtain consent to sever a portion of the land for the purpose of a lot addition.
10 m away · filed Jan 20, 2025 · Approved
44 Carlaw Ave · Consent
To obtain consent to sever a portion of the land for the purpose of a lot addition.
10 m away · filed Jan 20, 2025 · Approved
115 Logan Ave · Minor variance
To alter the existing two-and-one-half-storey semi-detached dwelling by constructing a new front covered porch with stairs.
200 m away · filed Oct 18, 2024 · Approved
From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.