The City of Toronto has 9 building permits since 2017 (5 still open) on record for this address.

Building permits

Every permit the City lists for this address since 2017, and any still open from before, newest first.

  • Designated structure · Sign building permit related

    2 wall signs + 1 ground sign**48 lowe's place**

    Applied Apr 1, 2026 · completed May 4, 2026 · Permit 26 137871 DST

    Cancelled
  • Conditional permit · New building

    Conditional Permit - Construction of new telecommunications and data processing facility complete with associated site works and MEP service Infrastructure

    Applied Mar 6, 2025 · issued Apr 8, 2025 · Permit 23 169869 BLD

    Inspections under way
  • Partial permit · Partial permit - structural framing

    Part Permit - Construction of new telecommunications and data processing facility complete with associated site works and MEP service Infrastructure

    Applied Nov 13, 2024 · completed Apr 8, 2025 · Permit 23 169869 STR

    Superseded
  • Partial permit · Partial permit - foundation

    Part Permit - Construction of new telecommunications and data processing facility complete with associated site works and MEP service Infrastructure

    Applied Aug 16, 2024 · completed Feb 3, 2025 · Permit 23 169869 FND

    Superseded
  • Drains and site services

    Drain - Construction of new telecommunications and data processing facility complete with associated site works and MEP service Infrastructure

    Applied Aug 12, 2024 · issued Mar 3, 2025 · Permit 23 169869 DRN

    Inspections under way
  • Drains and site services · Inside and outside drains

    Drain - Construction of new telecommunications and data processing facility complete with associated site works and MEP service Infrastructure

    Applied Aug 12, 2024 · Permit 23 169869 STS

    Under review
  • Fire and security upgrade

    FS - Sprinkler Shop Drawing - Construction of new telecommunications and data processing facility complete with associated site works and MEP service Infrastructure

    Applied Jun 7, 2024 · issued May 5, 2025 · completed May 5, 2025 · Permit 23 169869 FSU

    Closed
  • Heating and ventilation

    HVAC - Construction of new telecommunications and data processing facility complete with associated site works and MEP service Infrastructure

    Applied Jul 5, 2023 · issued Mar 12, 2025 · Permit 23 169869 HVA

    Inspections under way
  • Plumbing

    Plumbing - Construction of new telecommunications and data processing facility complete with associated site works and MEP service Infrastructure

    Applied Jul 5, 2023 · issued Mar 4, 2025 · Permit 23 169869 PLB

    Inspections under way

Committee of Adjustment

No applications to the City's Committee of Adjustment for this address since 2017. That's where an owner asks for a minor variance (a small exception to the zoning by-law) or a consent to divide a lot.

What’s planned nearby

Development sites within 500 m

No rezoning, site plan, subdivision or condominium file open within 500 m, and no pre-construction project on the site.

Neighbours’ Committee of Adjustment files within 250 m

None on file since 2017.

Everything planned in Etobicoke North

From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.