- Closed
Small residential project · Multiple projects
REVISION 01: Kitchen window made slightly wider and existing decaying basement walkout to be rebuiltPROPOSAL TO CONSTRUCT NEW 1 STOREY SIDE ADDITION WITH A TOTAL OF 5.12 M² , INTERIOR ALTERATIONS ( 41.61M2) AND A NEW REAR COVERED DECK.
Applied May 13, 2024 · issued May 22, 2024 · completed Oct 30, 2024 · Permit 24 128520 BLD (revision 01)
- Closed
Small residential project · Multiple projects
Proposal to construct new 1 storey side addition with a total of 5.12 m² , interior alterations ( 41.61m2) and a new rear covered deck.
Applied Mar 22, 2024 · issued Apr 4, 2024 · completed Oct 30, 2024 · Permit 24 128520 BLD
- Closed
Plumbing
Plumbing - PROPOSAL TO CONSTRUCT NEW 1 STOREY SIDE ADDITION WITH A TOTAL OF 5.12 M² , INTERIOR ALTERATIONS ( 41.61M2) AND A NEW REAR COVERED DECK.
Applied Mar 22, 2024 · issued Apr 4, 2024 · completed Oct 30, 2024 · Permit 24 128520 PLB
- Inspections under way
Heating and ventilation
HVAC - Interior alterations to finish basement and replace basement slab. SFD.
Applied Jan 25, 2018 · issued Jan 25, 2018 · Permit 17 224521 HVA
- Closed
Small residential project · Interior alterations
Interior alterations to finish basement and replace basement slab. SFD.
Applied Aug 29, 2017 · issued Aug 30, 2017 · completed Aug 7, 2018 · Permit 17 224521 BLD
- Closed
Plumbing
Plumbing - Interior alterations to finish basement and replace basement slab. SFD.
Applied Aug 29, 2017 · issued Aug 30, 2017 · completed Aug 7, 2018 · Permit 17 224521 PLB
- Closed
Drains and site services
Drain - Interior alterations to finish basement and replace basement slab. SFD.
Applied Aug 29, 2017 · issued Aug 30, 2017 · completed Aug 7, 2018 · Permit 17 224521 DRN
Committee of Adjustment
This address's applications to the City's Committee of Adjustment since 2017, and any still open. A minor variance asks for a small exception to the zoning by-law, such as a little more height or a smaller setback; a consent divides a lot or grants an easement.
- Closed
Minor variance · R addition
To alter the existing two-and-one-half-storey detached dwelling by constructing a one-storey east side addition, and a rear ground level deck.
Decision: Approved (hearing Oct 19, 2022)
Filed Jul 3, 2022 · File A0804/22TEY
What’s planned nearby
Development sites within 500 m
- Approved
6 storeys · 29 homes · Mixed use
410 m away · Site plan · Approved · filed Mar 24, 2021
- Approved
89-91 Beaty Avenue and 1497-1501 Queen Street West
7 storeys · 141 homes · Mixed use
440 m away · Rezoning · Approved · filed Feb 17, 2026
- Under review
12 storeys · 249 homes · Mixed use
450 m away · Site plan · Under review · filed May 17, 2023
Neighbours’ Committee of Adjustment files within 250 m
93 MacDonell Ave · Minor variance
To legalize and to maintain the existing rear ground floor deck with stairs, as well as a one-storey side (south) addition above the existing basement walkout, which were constructed beyond/without an authorized building permit.
200 m away · filed Jul 28, 2026 · Approved
85 MacDonell Ave · Minor variance
To construct a new rear one-storey semi-detached ancillary building (greenhouse and storage shed), abutting the side (north) lot line and adjacent to the existing carport.
210 m away · filed Mar 31, 2026 · Approved
125 Sorauren Ave · Minor variance
To alter the existing three-storey detached dwelling (configured as a triplex and currently used as a one-unit dwelling) by constructing a front third-floor addition and a rear addition, with a rear ground floor patio and a rear second storey deck. The existing rear exterior staircase will be demolished. There will be a total of one residential dwelling unit on the lot.
90 m away · filed Feb 13, 2026 · Approved
19 Galley Ave · Minor variance
To alter the existing two-and-one-half-storey detached dwelling by constructing a front covered porch extension, a rear two-storey addition with a partially covered ground floor deck, and a third storey addition. Also, to construct a new one-storey ancillary building (detached garage) in the rear yard, abutting the laneway.
80 m away · filed Nov 10, 2025 · Approved
93 Pearson Ave · Minor variance
To alter the existing two-and-one-half-storey semi-detached dwelling by constructing a rear third storey dormer addition, ground floor addition and basement addition. Also, to construct a new rear ground floor deck with stairs.
210 m away · filed May 7, 2025 · Approved
21 Galley Ave · Minor variance
To alter the existing two-and-one-half-storey detached dwelling by constructing a rear third floor addition, and rear ground floor deck with stairs. The existing rear one-storey addition with stairs will be demolished.
80 m away · filed May 6, 2025 · Approved
73 Sorauren Ave · Minor variance
To alter the existing three-storey detached dwelling (Fife House Foundation) by constructing two third storey dormers on the south side. Also, to construct a south side exterior platforms/staircase to access the second and third levels.
100 m away · filed Apr 28, 2025 · Approved
164 MacDonell Ave · Minor variance
To construct a new two-storey ancillary building (containing a garage on the ground level and one garden suite on the second level) in the rear yard, abutting Garden Avenue. There will be a total of two residential dwelling units on this lot (one unit within the main dwelling and one unit within the ancillary building). The existing garage will be demolished.
220 m away · filed Apr 14, 2025 · Approved
From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.