The City of Toronto has 2 building permits since 2017 and 1 Committee of Adjustment file on record for this address.
Building permits
Every permit the City lists for this address since 2017, and any still open from before, newest first.
- Closed
Plumbing
Plumbing - Proposal for second storey addition.
Applied Jul 25, 2025 · issued Aug 8, 2025 · completed Dec 19, 2025 · Permit 25 199930 PLB
- Closed
Small residential project · Addition(s)
Proposal for second storey addition.
Applied Jul 25, 2025 · issued Aug 8, 2025 · completed Dec 19, 2025 · Permit 25 199930 BLD
Committee of Adjustment
This address's applications to the City's Committee of Adjustment since 2017, and any still open. A minor variance asks for a small exception to the zoning by-law, such as a little more height or a smaller setback; a consent divides a lot or grants an easement.
- Closed
Minor variance · R addition
To alter the existing two-storey townhouse dwelling by constructing a rear second storey addition (cantilevered at the rear portion).
Decision: Approved (hearing May 7, 2025)
Filed Mar 19, 2025 · File A0189/25TEY
What’s planned nearby
Development sites within 500 m
- Approved
- Under review
1141 Bloor Street West, 90 Croatia Street and 980 Dufferin Street
22 storeys · 264 homes · Mixed use
390 m away · Site plan · Under review · filed Feb 27, 2026
Neighbours’ Committee of Adjustment files within 250 m
1045 Dufferin St · Minor variance
To construct a new three-storey building (utility (switchgear) facility). There will be two front yard parking spaces. A Site Plan Control application (File Number 25 166590 STE 09 SA) is currently under review.
220 m away · filed Feb 13, 2026 · Approved
91 Salem Ave · Minor variance
To alter the existing two-and-one-half-storey detached dwelling by constructing a new front one-storey addition with stairs, a front basement walkout, and a rear one-storey addition with a wood landing. The existing rear ground floor deck will be maintained and unaltered.
140 m away · filed Oct 23, 2025 · Approved
1081 Dufferin St · Minor variance
To construct a new one-storey detached ancillary building (two-car garage), in the rear yard of the existing two-storey detached dwelling.
200 m away · filed May 20, 2025 · Approved
79 Bartlett Ave · Minor variance
To alter the existing two-storey semi-detached dwelling by constructing a rear walkway. Also, to alter the existing one-storey ancillary building (rear detached garage, abutting the laneway) by constructing a complete second storey addition for one laneway suite. There will be a total of two residential dwelling units on this lot (one in the main dwelling and one in the ancillary building).
80 m away · filed Oct 24, 2024 · Approved
1064 Dufferin St · Minor variance
To alter the existing two-and-one-half-storey detached dwelling (duplex) by converting the existing rear one-storey ancillary building (detached garage) into one garden suite. There will be a total of three residential dwelling units on this lot (two units within the dwelling and one unit within the ancillary building).
250 m away · filed Jul 19, 2024 · Approved
99 Bartlett Ave · Minor variance
To alter the existing two-and-one-half-storey semi-detached dwelling by reconstructing the front stairs, and enclosing the front porch.
130 m away · filed Feb 13, 2024 · Approved
129 Shanly St · Minor variance
To alter the existing two-storey semi-detached dwelling by constructing a complete third storey addition, a rear second storey addition, a rear ground floor deck (to replace the existing rear ground floor deck), a front second floor box bay window (to replace the existing bay window) with a front third storey balcony above, and second and third floor rear balconies.
150 m away · filed Nov 22, 2023 · Approved
27 Southview Ave · Minor variance
To alter the existing two-storey semi-detached dwelling by a complete third storey addition, and a rear one-storey with a roof deck above. Also, to reconstruct the front porch and stairs.
240 m away · filed Jul 21, 2023 · Approved
From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.