The City of Toronto has 2 building permits since 2017 on record for this address.
Building permits
Every permit the City lists for this address since 2017, and any still open from before, newest first.
- Closed
Plumbing
Plumbing - Construct interior alterations through dwelling
Applied Feb 24, 2021 · issued Mar 4, 2021 · completed Jan 18, 2024 · Permit 21 119738 PLB
- Closed
Small residential project · Interior alterations
Construct interior alterations through dwelling
Applied Feb 24, 2021 · issued Mar 4, 2021 · completed Jun 3, 2021 · Permit 21 119738 BLD
Committee of Adjustment
No applications to the City's Committee of Adjustment for this address since 2017. That's where an owner asks for a minor variance (a small exception to the zoning by-law) or a consent to divide a lot.
What’s planned nearby
Development sites within 500 m
No rezoning, site plan, subdivision or condominium file open within 500 m, and no pre-construction project on the site.
Neighbours’ Committee of Adjustment files within 250 m
12 St Hubert Ave · Minor variance
To construct a new two-storey detached dwelling (including basement) with an integral garage, a widened driveway, a covered front porch with stairs, a rear first storey deck with stairs, and a rear basement walkout. The existing rear one-storey detached ancillary building (garage) will be demolished.
240 m away · filed Mar 10, 2026 · Approved
12 St Hubert Ave · Minor variance
To construct a new two-storey detached dwelling with an integral garage, a front porch, a rear ground floor deck, a rear basement walkout, and a widened driveway. The existing rear one-storey detached ancillary building (garage) will be demolished.
240 m away · filed Dec 31, 2025 · Refused
39 Memorial Park Ave · Minor variance
To alter the existing one-storey detached dwelling by constructing a complete second storey addition, a rear two-storey addition with a first floor deck and stairs, and a new front patio with a canopy.
150 m away · filed Jan 27, 2025 · Approved
190 Donlands Ave · Consent
To obtain consent to sever a portion of land for the purpose of a lot addition.
240 m away · filed May 14, 2024 · Application withdrawn
8 St Hubert Ave · Minor variance
To alter the existing one-storey detached dwelling by constructing front, rear and south side ground floor additions, a complete second storey addition, a partial south side third storey addition, a new front porch, a front integral garage, a rear ground floor deck, a south side entrance, a rear basement walkout, and front and rear second storey balconies. There will be a total of two units (one secondary suite in the basement) within this dwelling.
230 m away · filed Mar 4, 2024 · Approved
29 Memorial Park Ave · Minor variance
To alter the existing two-storey detached dwelling by constructing a rear two-storey addition and a ground floor deck. Also, to permit an existing undersized vehicular parking space width and an increased building height which was constructed beyond the limits of the previously approved building permit.
130 m away · filed Sep 19, 2023 · Approved
188 Donlands Ave · Minor variance
To construct a new two-storey semi-detached ancillary building (containing one laneway suite with a rear [west] second storey juliette balcony), in the rear yard, abutting the laneway. The existing ancillary building (semi-detached garage) in the rear yard, will be demolished. Also, the existing two-storey detached main dwelling will be maintained and unaltered.
240 m away · filed Aug 21, 2023 · Approved
190 Donlands Ave · Minor variance
To construct a new two-storey semi-detached ancillary building (containing one laneway suite with a rear [west] second storey juliette balcony), in the rear yard, abutting the laneway and Kings Park Boulevard. The existing ancillary building (semi-detached garage) in the rear yard, will be demolished. Also, the existing two-storey detached main dwelling will be maintained and unaltered.
240 m away · filed Aug 21, 2023 · Approved
From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.