Sample data. These listings are fictional examples used to demonstrate the site. No MLS or board data is displayed.

Shaun Lovell, Real Estate SalespersonRight At Home Realty, Brokerage289-813-3318

Toronto address · Ward 20, Scarborough Southwest

733 Birchmount Rd

The City of Toronto has 18 building permits since 2017 (5 still open) on record for this address.

Building permits

Every permit the City lists for this address since 2017, and any still open from before, newest first.

  • Heating and ventilation

    Rev 2 - Proposed revision to include range hood on branch.HVAC - Demolition of existing place of worship and construction of new 1844.21m2 (total) place of worship.1280.50m2 ground floor gfa.

    Applied Oct 26, 2018 · issued Nov 9, 2018 · completed Feb 10, 2020 · Permit 14 209528 HVA (revision 02)

    Closed
  • New building

    Rev 04 - Revision to relocate office.Demolition of existing place of worship and construction of new 1844.21m2 (total) place of worship.1280.50m2 ground floor gfa.

    Applied Sep 19, 2018 · issued Nov 13, 2018 · Permit 14 209528 BLD (revision 04)

    Revision issued
  • New building

    REV 03 - Proposed revision for Fire Protection - Sprinkler Systems - to add dry sprinkler heads to north, south and east canopies.Demolition of existing place of worship and construction of new 1844.21m2 (total) place of worship.1280.50m2 ground floor gfa.

    Applied Aug 28, 2018 · issued Sep 18, 2018 · Permit 14 209528 BLD (revision 03)

    Revision issued
  • Plumbing

    REVISION #3: Storm water harvest systemRev 02 - Proposed revision to drainage.Plumbing - Demolition of existing place of worship and construction of new 1844.21m2 (total) place of worship.1280.50m2 ground floor gfa.

    Applied Jul 31, 2018 · issued Aug 14, 2018 · completed Dec 23, 2021 · Permit 14 209528 PLB (revision 03)

    Closed
  • Plumbing

    Rev 02 - Proposed revision to drainge.Plumbing - Demolition of existing place of worship and construction of new 1844.21m2 (total) place of worship.1280.50m2 ground floor gfa.

    Applied Jul 12, 2018 · issued Jul 12, 2018 · completed Dec 23, 2021 · Permit 14 209528 PLB (revision 02)

    Closed
  • Heating and ventilation

    Rev 1 - Proposed revision to HVAC plan.HVAC - Demolition of existing place of worship and construction of new 1844.21m2 (total) place of worship.1280.50m2 ground floor gfa.

    Applied May 3, 2018 · issued Jun 1, 2018 · completed Feb 10, 2020 · Permit 14 209528 HVA (revision 01)

    Closed
  • Plumbing

    Rev 1 - Proposed revision to plumbing layout Plumbing - Demolition of existing place of worship and construction of new 1844.21m2 (total) place of worship.1280.50m2 ground floor gfa.

    Applied May 3, 2018 · issued May 31, 2018 · completed Dec 23, 2021 · Permit 14 209528 PLB (revision 01)

    Closed
  • Drains and site services · Site service

    Revision #01 - Changes to proposed sanitary pump and off-line jellyfish treatment unit for a new place of worship building.Site servicing for a new Place of Worship

    Applied Apr 13, 2018 · issued Jul 12, 2018 · completed Dec 23, 2021 · Permit 15 160046 STS (revision 01)

    Closed
  • New building

    REVISION #2: INTERIOR FINISHES - Building 7 New deities housing within the buildingRev 01 - Proposed revision as per drawings.Demolition of existing place of worship and construction of new 1844.21m2 (total) place of worship.1280.50m2 ground floor gfa.

    Applied Mar 16, 2018 · issued Oct 24, 2018 · Permit 14 209528 BLD (revision 02)

    Revision issued
  • New building

    Rev 01 - Proposed revision as per drawings.Demolition of existing place of worship and construction of new 1844.21m2 (total) place of worship.1280.50m2 ground floor gfa.

    Applied Jan 19, 2018 · issued Feb 14, 2018 · Permit 14 209528 BLD (revision 01)

    Revision issued
  • Fire and security upgrade

    FS - Sprinkler Shop Drawing - Demolition of existing place of worship and construction of new 1844.21m2 (total) place of worship.1280.50m2 ground floor gfa.

    Applied May 5, 2016 · completed Jan 24, 2018 · Permit 14 209528 FSU

    Closed
  • Drains and site services · Site service

    Site servicing for a new Place of Worship

    Applied May 20, 2015 · issued Jun 2, 2015 · completed Dec 23, 2021 · Permit 15 160046 STS

    Closed
Show 6 more permits
  • Plumbing

    Plumbing - Demolition of existing place of worship and construction of new 1844.21m2 (total) place of worship.1280.50m2 ground floor gfa.

    Applied May 15, 2015 · issued Jan 9, 2018 · completed Dec 23, 2021 · Permit 14 209528 PLB

    Closed
  • Drains and site services

    Drain - Demolition of existing place of worship and construction of new 1844.21m2 (total) place of worship.1280.50m2 ground floor gfa.

    Applied Nov 7, 2014 · issued Jun 18, 2015 · completed Dec 21, 2021 · Permit 14 209528 DRN

    Closed
  • Demolition

    Demolish existing one storey Place of Worship for new Place of Worship

    Applied Nov 5, 2014 · issued Mar 4, 2015 · completed Oct 24, 2018 · Permit 14 248454 DEM

    Closed
  • Heating and ventilation

    HVAC - Demolition of existing place of worship and construction of new 1844.21m2 (total) place of worship.1280.50m2 ground floor gfa.

    Applied Aug 21, 2014 · issued Dec 21, 2017 · completed Feb 10, 2020 · Permit 14 209528 HVA

    Closed
  • New building

    Demolition of existing place of worship and construction of new 1844.21m2 (total) place of worship.1280.50m2 ground floor gfa.

    Applied Aug 20, 2014 · issued May 20, 2016 · Permit 14 209528 BLD

    Inspections under way
  • Addition or alteration · Addition(s)

    addition to south side of building

    Applied Jul 13, 2005 · issued Nov 4, 2009 · completed Dec 19, 2018 · Permit 05 159106 BLD

    Closed

Committee of Adjustment

No applications to the City's Committee of Adjustment for this address since 2017. That's where an owner asks for a minor variance (a small exception to the zoning by-law) or a consent to divide a lot.

What’s planned nearby

Development sites within 500 m

No rezoning, site plan, subdivision or condominium file open within 500 m, and no pre-construction project on the site.

Neighbours’ Committee of Adjustment files within 250 m

  • 4 Chelwood Rd · Minor variance

    The applicant is seeking relief from the provisions of the Zoning By-law to construct a two storey side addition to the existing semi-detached dwelling.

    150 m away · filed Mar 20, 2018 · Approved

Everything planned in Scarborough Southwest

From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.