The City of Toronto has 6 building permits since 2017 on record for this address.
Building permits
Every permit the City lists for this address since 2017, and any still open from before, newest first.
- Closed
Plumbing
Plumbing - New stairs to basement through mudroom on the main floor, close existing staircase. Alterations to basement and new walkout.
Applied Jun 29, 2023 · issued Jul 4, 2023 · completed Aug 11, 2026 · Permit 23 167620 PLB
- Closed
Small residential project · Multiple projects
New stairs to basement through mudroom on the main floor, close existing staircase. Alterations to basement and new walkout. The existing rear deck to be removed.
Applied Jun 29, 2023 · issued Jul 4, 2023 · completed Aug 11, 2026 · Permit 23 167620 BLD
- Closed
Drains and site services
Drain - New stairs to basement through mudroom on the main floor, close existing staircase. Alterations to basement and new walkout.
Applied Jun 29, 2023 · issued Jul 4, 2023 · completed Aug 11, 2026 · Permit 23 167620 DRN
- Closed
Drains and site services · Back water valve (Sewer only)
Proposal for Backwater Valve.
Applied Jun 2, 2021 · issued Jun 2, 2021 · completed Jun 7, 2021 · Permit 21 164609 DRN
- Closed (dormant)
Plumbing
Plumbing - Rear addition. CofA final & binding (#A332/03M) - Addition(s)
Applied Aug 5, 2003 · issued Aug 5, 2003 · completed Jun 8, 2026 · Permit 03 163292 PLB
- Closed (dormant)
Small residential project · Addition(s)
Rear addition. CofA final & binding (#A332/03M)
Applied Aug 5, 2003 · issued Aug 5, 2003 · completed Jun 8, 2026 · Permit 03 163292 BLD
Committee of Adjustment
No applications to the City's Committee of Adjustment for this address since 2017. That's where an owner asks for a minor variance (a small exception to the zoning by-law) or a consent to divide a lot.
What’s planned nearby
Development sites within 500 m
No rezoning, site plan, subdivision or condominium file open within 500 m, and no pre-construction project on the site.
Neighbours’ Committee of Adjustment files within 250 m
212 Douglas Ave · Minor variance
To construct a new detached dwelling with an integral garage.
170 m away · filed Feb 20, 2026 · Approved
239 Bedford Park Ave · Minor variance
To construct a second storey addition to the existing detached garage and convert into a Laneway Suite.
220 m away · filed Apr 9, 2025 · Approved
243 Bedford Park Ave · Minor variance
To construct a new detached dwelling.
220 m away · filed Dec 30, 2024 · Approved
252 Douglas Ave · Minor variance
To construct a new detached dwelling.
200 m away · filed Dec 11, 2024 · Approved
208 Douglas Ave · Minor variance
To construct a new detached dwelling with a detached garage in the rear yard..
170 m away · filed May 18, 2024 · Approved
140 Chatsworth Dr · Minor variance
To alter the existing building by constructing a rear second floor deck on existing roof.
150 m away · filed Mar 21, 2024 · Approved
237 Bedford Park Ave · Minor variance
Proposal for a new three-storey single family dwelling with detached rear yard garage.
220 m away · filed Aug 25, 2023 · Approved
177 Glengarry Ave · Minor variance
To construct a new dwelling.
110 m away · filed Jul 5, 2023 · Approved
From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.