The City of Toronto has 12 building permits since 2017 (5 still open) and 1 Committee of Adjustment file on record for this address.
Building permits
Every permit the City lists for this address since 2017, and any still open from before, newest first.
- Permit issued
Designated structure · Sign building permit related
1 ground sign**rouge valley community recreation centre**
Applied Sep 3, 2026 · issued Sep 10, 2026 · Permit 26 232158 DST
- Cancelled
Designated structure · Sign building permit related
1 Ground Sign
Applied May 8, 2026 · completed May 11, 2026 · Permit 26 157168 DST
- Closed
Fire and security upgrade · Electromagnetic locks
Installation of three electromagnetic maglocks
Applied Jan 15, 2025 · issued Feb 6, 2025 · completed Sep 15, 2025 · Permit 25 105014 FSU
- Cancelled
Partial permit · Partial permit - structural framing
Part Permit - construct new 3 storey community centre
Applied Jan 17, 2023 · completed Dec 13, 2023 · Permit 20 218077 STR
- Application on hold
Fire and security upgrade · Sprinklers
Fire Sprinkler system
Applied Dec 7, 2022 · Permit 22 237178 FSU
- Inspections under way
Drains and site services
Drain - construct new 3 storey community centre
Applied Nov 29, 2022 · issued Dec 14, 2022 · Permit 20 218077 DRN
- Cancelled
Conditional permit · Partial permit - foundation
Conditional Permit - Part Permit - construct new 3 storey community centre.
Applied Jul 26, 2022 · issued Aug 12, 2022 · completed Feb 24, 2023 · Permit 20 218077 FND
- Closed
Fire and security upgrade
FS - Sprinkler Shop Drawing - construct new 3 storey community centre
Applied Feb 9, 2022 · completed Dec 19, 2022 · Permit 20 218077 FSU
- Inspections under way
Plumbing
Plumbing - construct new 3 storey community centre
Applied Nov 13, 2020 · issued Mar 15, 2023 · Permit 20 218077 PLB
- Inspections under way
New building
Construct new 3 storey community centre
Applied Nov 13, 2020 · issued Jan 12, 2024 · Permit 20 218077 BLD
- Closed
Heating and ventilation
HVAC - construct new 3 storey community centre
Applied Nov 13, 2020 · issued Mar 15, 2023 · completed Nov 21, 2025 · Permit 20 218077 HVA
- Closed
Drains and site services · Site service
Drain - construct new 3 storey community centre
Applied Nov 13, 2020 · issued Aug 13, 2024 · completed May 13, 2025 · Permit 20 218077 STS
Committee of Adjustment
This address's applications to the City's Committee of Adjustment since 2017, and any still open. A minor variance asks for a small exception to the zoning by-law, such as a little more height or a smaller setback; a consent divides a lot or grants an easement.
- Closed
Minor variance · Other
To permit the redevelopment of the existing Joyce Trimmer Park, located north of Sheppard Avenue East and east of Conlins Road (unopened road allowance) for a new municipal community centre and day care facility. Cross-Reference Site Plan Control Application No. 20 122576 ESC 25 ECS
Decision: Approved (hearing Oct 20, 2021)
Filed Apr 28, 2020 · File A0081/20SC
What’s planned nearby
Development sites within 500 m
No rezoning, site plan, subdivision or condominium file open within 500 m, and no pre-construction project on the site.
Neighbours’ Committee of Adjustment files within 250 m
None on file since 2017.
From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.