Toronto address · Ward 13, Toronto Centre
99 Dalhousie St
Metta Housing Co-Op
The City of Toronto has 1 building permit since 2017 (1 still open) on record for this address.
Building permits
Every permit the City lists for this address since 2017, and any still open from before, newest first.
- Permit issued
Fire and security upgrade · Fire alarm
replace fire alarm system on all floors, parking levels and penthouse
Applied Mar 14, 2018 · issued Apr 12, 2018 · Permit 18 129123 FSU
Committee of Adjustment
No applications to the City's Committee of Adjustment for this address since 2017. That's where an owner asks for a minor variance (a small exception to the zoning by-law) or a consent to divide a lot.
What’s planned nearby
Development sites within 500 m
- Approved
53 storeys · 591 homes · Mixed use
90 m away · Site plan · Approved · filed Aug 31, 2021
- Under review
32 storeys · 315 homes · Mixed use
190 m away · Rezoning · Under review · filed Mar 31, 2026
- Under review
- Under review
- Under review
- Under review
24 storeys · 256 homes · Residential
250 m away · Site plan · Under review · filed Sep 1, 2022
Neighbours’ Committee of Adjustment files within 250 m
53 Mutual St · Minor variance
To alter the existing two-and-one-half-storey attached building by increasing the non-residential floor space index.
150 m away · filed Jul 23, 2025 · Approved
225 Jarvis St · Minor variance
To alter the development standards of the 49-storey mixed-use building (as approved under Site Specific Zoning By-laws 764-2020(OMB) and 765-2020(OMB)) by increasing the total/residential gross floor area (from the first storey to the 20th storey). Also, to reduce the number of required parking spaces on-site. The total number of hotel suites (215 suites) and residential dwelling units (580 units) will be maintained.
190 m away · filed Mar 4, 2025 · Approved
75 Mutual St · Minor variance
To alter the existing three-storey detached building by constructing a fourth storey addition, and a rear four-storey addition. This building will contain a total of 18 dwelling rooms (multi-tenant house).
100 m away · filed Dec 9, 2024 · Approved
203 Jarvis St · Consent
To obtain consent to a strata severance and to create various easements/rights-of-way.
220 m away · filed Sep 17, 2024 · Approved
225 Jarvis St · Minor variance
To permit access to the loading area of the 49-storey mixed-use building (as approved under Site Specific Zoning By-laws 764-2020(OMB) and 765-2020(OMB)) from the abutting street on the east side of the building (George Street). This mixed-use building will contain 215 hotel suites, one ground floor restaurant use, and 580 residential dwelling units.
190 m away · filed Jun 22, 2024 · Approved
203 Jarvis St · Minor variance
To alter the development standards for the 32-storey mixed-use building (as approved under Site Specific Zoning By-law 683-2020(LPAT)) by reducing the width of the bicycle parking spaces.
220 m away · filed Oct 23, 2023 · Approved
244 Church St · Minor variance
To alter the development standards (approved by Site Specific Zoning By-law 517-2021 and 518-2021), for a 52-storey mixed-use building, with four levels of underground parking, by reducing the required retail/visitor parking spaces.
100 m away · filed Oct 17, 2023 · Approved
202 Jarvis St · Minor variance
To construct a new 14-storey building (the 15th storey will be used for mechanical equipment) with a front third storey roof terrace, east and west side roof terraces on the third, fifth and seventh storey, a rear seventh storey roof terrace, and a complete roof terrace on the roof level. The mixed-use building will contain classroom spaces, faculty offices, and common areas for academic purposes.
150 m away · filed May 23, 2023 · Approved
From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.