Toronto address · Ward 20, Scarborough Southwest
1 Haig Ave
The City of Toronto has 5 building permits since 2017 (5 still open) and 1 Committee of Adjustment file on record for this address.
Building permits
Every permit the City lists for this address since 2017, and any still open from before, newest first.
- Inspections under way
Heating and ventilation
HVAC - The subject property is currently vacant. The existing frame shed to be demolished and a new 3-story dwelling shall be built.
Applied Sep 26, 2025 · issued Oct 7, 2025 · Permit 25 135989 HVA
- Revision issued
New house · New building
REVISION 01: Proposed Rear walkout stairs location revised. Fire shutters provided for windows. A roof access stairs is added.The subject property is currently vacant. The existing frame shed to be demolished and a new 3-story dwelling shall be built.
Applied Aug 6, 2025 · issued Sep 23, 2025 · Permit 25 135989 BLD (revision 01)
- Inspections under way
Plumbing
Plumbing - The subject property is currently vacant. The existing frame shed to be demolished and a new 3-story dwelling shall be built.
Applied Mar 27, 2025 · issued Jun 18, 2025 · Permit 25 135989 PLB
- Inspections under way
New house · New building
The subject property is currently vacant. The existing frame shed to be demolished and a new 3-story dwelling shall be built.
Applied Mar 27, 2025 · issued Aug 1, 2025 · 2 homes added · Permit 25 135989 BLD
- Permit issued
Drains and site services
Drain - The subject property is currently vacant. The existing frame shed to be demolished and a new 3-story dwelling shall be built.
Applied Mar 27, 2025 · issued Jun 18, 2025 · Permit 25 135989 DRN
Committee of Adjustment
This address's applications to the City's Committee of Adjustment since 2017, and any still open. A minor variance asks for a small exception to the zoning by-law, such as a little more height or a smaller setback; a consent divides a lot or grants an easement.
- Closed
Minor variance · New R building
To construct a new three-storey detached dwelling with a secondary suite in the basement. The existing frame shed will be demolished.
Decision: Approved (hearing Feb 12, 2025)
Filed Dec 6, 2024 · File A0307/24SC
What’s planned nearby
Development sites within 500 m
- Under review
8 storeys · 112 homes · Residential
420 m away · Site plan · Under review · filed Aug 9, 2021
Neighbours’ Committee of Adjustment files within 250 m
9 Haig Ave · Minor variance
To alter the existing two storey detached dwelling by constructing two storey addition with extended porch in the front yard and an extended deck in the rear yard. NOTE: This application was previously deferred at the Committee of Adjustment Hearing on Feburary 11, 2026.
30 m away · filed Jan 5, 2026 · Approved
74 Warden Ave · Minor variance
To permit a new driveway in the front yard.
30 m away · filed Sep 22, 2025 · Deferred
11 Crescentwood Rd · Minor variance
To demolish the existing 2-storey detached dwelling and construct a new 2-storey detached dwelling. This application was previously deferred at the December 4, 2024 hearing.
150 m away · filed Oct 7, 2024 · Approved
9 Crescentwood Rd · Minor variance
To demolish the existing dwelling and to construct a new two storey dwelling. This application was deferred from the December 4, 2024 hearing.
140 m away · filed Oct 4, 2024 · Approved
11 Crescentwood Rd · Minor variance
To demolish the existing 2-storey detached dwelling and construct a new 2-storey detached dwelling. This item was previously deferred at the July 24, 2024 hearing.
150 m away · filed May 10, 2024 · Refused
20 Haig Ave · Minor variance
To construct a new single detached dwelling. An associated Consent Application B0040/21SC was previously approved to sever the lot into two lots.
80 m away · filed Aug 2, 2022 · Approved
20 Haig Ave · Minor variance
To construct a new single detached dwelling. An associated Consent Application B0040/21SC was previously approved to sever the lot into two lots.
80 m away · filed Aug 2, 2022 · Approved
15 Haig Ave · Minor variance
To alter the existing two-storey dwelling by constructing a third-floor addition and a south side yard two-storey addition.
50 m away · filed May 19, 2022 · Refused
From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.