The City of Toronto has 7 building permits since 2017 and 1 Committee of Adjustment file on record for this address.
Building permits
Every permit the City lists for this address since 2017, and any still open from before, newest first.
- Closed
Drains and site services
Drain - Construction of a pool cabana with sanitary and food prep facilities
Applied Nov 1, 2024 · issued Nov 1, 2024 · completed Nov 12, 2024 · Permit 24 187532 DRN
- Closed
Plumbing
Plumbing - Construction of a pool cabana with sanitary and food prep facilities
Applied Nov 1, 2024 · issued Nov 1, 2024 · completed Nov 12, 2024 · Permit 24 187532 PLB
- Closed
Heating and ventilation
HVAC - Construction of a pool cabana with sanitary and food prep facilities
Applied Nov 1, 2024 · issued Nov 21, 2024 · completed Jan 16, 2025 · Permit 24 187532 HVA
- Closed
Drains and site services · Back water valve (Sewer only)
Install BWV
Applied Aug 26, 2024 · issued Aug 27, 2024 · completed Sep 17, 2024 · Permit 24 203571 DRN
- Closed
Small residential project · Accessory Building(s)
Construction of a pool cabana with sanitary and food prep facilities
Applied Jul 25, 2024 · issued Oct 25, 2024 · completed Jan 24, 2025 · Permit 24 187532 BLD
- Closed
Plumbing
Plumbing - Partial basement finish.
Applied Sep 6, 2011 · issued Sep 6, 2011 · completed Jun 1, 2018 · Permit 11 268119 PLB
- Closed
Small residential project · Finishing basements
Partial basement finish.
Applied Sep 2, 2011 · issued Sep 6, 2011 · completed Jun 1, 2018 · Permit 11 268119 BLD
Committee of Adjustment
This address's applications to the City's Committee of Adjustment since 2017, and any still open. A minor variance asks for a small exception to the zoning by-law, such as a little more height or a smaller setback; a consent divides a lot or grants an easement.
- Closed
Minor variance · R addition
To construct a two-storey rear addition.
Decision: Approved (hearing Oct 26, 2017)
Filed Jul 21, 2017 · File A0697/17EYK
What’s planned nearby
Development sites within 500 m
No rezoning, site plan, subdivision or condominium file open within 500 m, and no pre-construction project on the site.
Neighbours’ Committee of Adjustment files within 250 m
4 Sixth St · Minor variance
To construct a second and third storey addition above the existing detached dwelling.
90 m away · filed Aug 11, 2025 · Approved
62 Seventh St · Minor variance
To construct a new duplex with an attached garage.
250 m away · filed Apr 11, 2025 · Refused
53 Lake Shore Dr · Minor variance
To construct a second storey addition above the existing dwelling, to reconfigure the existing basment walkout and a new covered deck along the south side.
130 m away · filed Oct 4, 2024 · Approved
47 Emerald Cres · Minor variance
To construct a two-storey east side addition including an attached garage. The altered dwelling will contain a secondary dwelling unit.
170 m away · filed May 31, 2024 · Hearing scheduled
62 Seventh St · Minor variance
To construct a two-storey rear addition, a second storey addition above the existing dwelling and a second storey rear platform. A previous Committee of Adjustment application (A0119/23EYK) approved a variance related to floor space index.
250 m away · filed May 21, 2024 · Approved
92 Lake Shore Dr · Minor variance
To construct a second storey rear addition, a partial third storey addition that will include a front platform, and a deck in the rear yard.
200 m away · filed Feb 1, 2024 · Approved
62 Seventh St · Minor variance
To construct a two-storey rear and south side addiiton.
250 m away · filed Mar 15, 2023 · Approved
5 Seventh St · Minor variance
To construct a new detached dwelling with an attached garage.
120 m away · filed Feb 17, 2022 · Approved
From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.