Toronto address · Ward 13, Toronto Centre
40 Gould St
The City of Toronto has 2 building permits since 2017 and 1 Committee of Adjustment file on record for this address.
Building permits
Every permit the City lists for this address since 2017, and any still open from before, newest first.
- Closed
Addition or alteration · Interior alterations
Proposed interior alterations to offices within an existing university building.
Applied Sep 1, 2019 · issued Sep 23, 2019 · completed Nov 3, 2020 · Permit 19 214849 BLD
- Closed
Heating and ventilation
HVAC - Proposed interior alterations to offices within an existing university building.
Applied Sep 1, 2019 · issued Oct 11, 2019 · completed Nov 12, 2019 · Permit 19 214849 HVA
Committee of Adjustment
This address's applications to the City's Committee of Adjustment since 2017, and any still open. A minor variance asks for a small exception to the zoning by-law, such as a little more height or a smaller setback; a consent divides a lot or grants an easement.
- Closed
Minor variance · Other
To construct cooling towers on the roof of an existing three-storey university building.
Decision: Approved (hearing Jun 12, 2019)
Filed Feb 13, 2019 · File A0140/19TEY
What’s planned nearby
Development sites within 500 m
- Under review
- Approved
53 storeys · 591 homes · Mixed use
220 m away · Site plan · Approved · filed Aug 31, 2021
- Under review
- Under review
348-356 Yonge Street, 2 Elm Avenue and 8 Elm Street
819 homes · Residential
240 m away · Condominium · Under review · filed Sep 17, 2021
- Under review
595 Bay Street and 306 Yonge Street
25 storeys · 224 homes · Mixed use
250 m away · Subdivision · Under review · filed Nov 8, 2021
- Under review
20 Gerrard Street East and 21 McGill Street
7 storeys · Residential
250 m away · Site plan · Under review · filed May 25, 2026
Neighbours’ Committee of Adjustment files within 250 m
332 Yonge St · Minor variance
To permit a new eating establishment with karaoke rooms on the second storey (with an increased total floor area), and an eating establishment on the ground floor with washrooms and storage located in the basement, within the existing two-storey commercial building.
220 m away · filed Jul 24, 2026 · Hearing scheduled
50 Gerrard St E · Consent
To obtain consent to sever a portion of stratified land (air-rights above an elevation of 121 m) for the purpose of a lot addition.
210 m away · filed May 15, 2026 · Postponed
8 Elm St · Consent
To obtain consent to sever the property into two lots, as well as maintaining existing easements/rights-of-way.
240 m away · filed Feb 23, 2024 · Approved
50 Gerrard St E · Minor variance
To alter the development standards for a residential building approved under Site Specific Zoning By-law 1070-2004(OLT) by updating the mechanical systems (including new rooftop enclosed elements and conduit risers at exterior facade of building), which requires modification of the exterior cladding to extend approximately 140 mm beyond the existing cladding.
210 m away · filed Nov 14, 2023 · Approved
340 Yonge St · Minor variance
To permit an amusement arcade use (claw machines) on the ground level of the existing three-storey commercial building.
200 m away · filed Sep 8, 2023 · Approved
137 Bond St · Minor variance
To alter the existing three-storey building by constructing an east side five-storey addition above, a rear eight-storey addition, front and west side third storey dormer additions, with a fourth storey rooftop terrace, and green roofs on the second, sixth, seventh, and eighth storey. The building will be used to facilitate the University Health and Wellness programs.
50 m away · filed Apr 6, 2023 · Approved
363 Yonge St · Minor variance
To alter the development standards, as approved for a 85-storey mixed-use building (under Site Specific Zoning By-laws 1301-2019 (LPAT) and 1302-2019 (LPAT)).
190 m away · filed Dec 30, 2022 · Approved
65 Dundas St E · Minor variance
To convert the existing hotel building into an apartment building with a total of 280 affordable housing units.
230 m away · filed Aug 16, 2022 · Approved
From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.