Toronto address · Ward 3, Etobicoke-Lakeshore
45 Eighth St
The City of Toronto has 5 building permits since 2017 and 1 Committee of Adjustment file on record for this address.
Building permits
Every permit the City lists for this address since 2017, and any still open from before, newest first.
- Closed
Heating and ventilation
HVAC - Proposed new three storey dwelling with attched garage c/w front porch, rear deck and walkout.
Applied Sep 14, 2021 · issued Sep 23, 2021 · completed Aug 18, 2022 · Permit 21 162134 HVA
- Closed
Plumbing
Plumbing - Proposed new two storey dwelling with attched garage c/w front porch, rear deck, basement walkout.
Applied May 28, 2021 · issued Jun 24, 2021 · completed Aug 24, 2022 · Permit 21 162134 PLB
- Closed
New house · New building
Proposed new three storey dwelling with attched garage c/w front porch, rear deck and walkout.
Applied May 28, 2021 · issued Jun 24, 2021 · completed Jan 31, 2023 · 1 home added · Permit 21 162134 BLD
- Closed
Demolition
Proposed Demolition to the existing single family dwelling.
Applied May 28, 2021 · issued Jun 24, 2021 · completed Jan 6, 2022 · Permit 21 162160 DEM
- Closed
Drains and site services
Drain - Proposed new two storey dwelling with attched garage c/w front porch, rear deck, basement walkout.
Applied May 28, 2021 · issued Jun 24, 2021 · completed Aug 18, 2022 · Permit 21 162134 DRN
Committee of Adjustment
This address's applications to the City's Committee of Adjustment since 2017, and any still open. A minor variance asks for a small exception to the zoning by-law, such as a little more height or a smaller setback; a consent divides a lot or grants an easement.
- Closed
Minor variance · New R building
To construct a new detached dwelling with an attached garage.
Decision: Approved (hearing Mar 9, 2021)
Filed Dec 11, 2020 · File A0513/20EYK
What’s planned nearby
Development sites within 500 m
No rezoning, site plan, subdivision or condominium file open within 500 m, and no pre-construction project on the site.
Neighbours’ Committee of Adjustment files within 250 m
73 Tenth St · Minor variance
To construct a one-storey rear addition and a new rear deck.
250 m away · filed Dec 2, 2025 · Approved
46 Tenth St · Minor variance
To maintain the existing front porch that is currently uncer construction.
240 m away · filed Sep 26, 2025 · Approved
16 Eighth St · Minor variance
To enclose the existing front porch.
120 m away · filed Apr 24, 2025 · Approved
62 Seventh St · Minor variance
To construct a new duplex with an attached garage.
60 m away · filed Apr 11, 2025 · Refused
69 Tenth St · Minor variance
To construct a two-storey rear addition including a deck in the rear yard.
240 m away · filed Aug 9, 2024 · Approved
47 Emerald Cres · Minor variance
To construct a two-storey east side addition including an attached garage. The altered dwelling will contain a secondary dwelling unit.
210 m away · filed May 31, 2024 · Hearing scheduled
72 Seventh St · Minor variance
To legalize and to maintain the existing building that is currently under construction by constructing a two-storey rear addition, a one-storey rear addition and to create a secondary suite.
80 m away · filed May 29, 2024 · Approved
62 Seventh St · Minor variance
To construct a two-storey rear addition, a second storey addition above the existing dwelling and a second storey rear platform. A previous Committee of Adjustment application (A0119/23EYK) approved a variance related to floor space index.
60 m away · filed May 21, 2024 · Approved
From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.