Toronto address · Ward 20, Scarborough Southwest
5 Crescentwood Rd
The City of Toronto has 6 building permits since 2017 on record for this address.
Building permits
Every permit the City lists for this address since 2017, and any still open from before, newest first.
- Closed
New house · New building
Revision to add two new second storey windows and add additional skylights.
Applied May 31, 2016 · issued Sep 1, 2016 · completed Mar 5, 2021 · Permit 15 237375 BLD (revision 01)
- Closed
Heating and ventilation
HVAC - Proposal to construct a 2-storey dwelling with integral garage, unfinished basement
Applied Jan 15, 2016 · issued May 4, 2016 · completed Mar 5, 2021 · Permit 15 237375 HVA
- Closed
Plumbing
Plumbing - Proposal to construct a 2-storey dwelling with integral garage, unfinished basement
Applied Oct 14, 2015 · issued Dec 24, 2015 · completed Mar 5, 2021 · Permit 15 237375 PLB
- Closed
New house · New building
Proposal to construct a 2-storey dwelling with integral garage, unfinished basement
Applied Oct 14, 2015 · issued Dec 24, 2015 · completed Mar 5, 2021 · 1 home added · Permit 15 237375 BLD
- Closed
Demolition
demolish existing 2 storey house
Applied Oct 14, 2015 · issued Dec 24, 2015 · completed Mar 5, 2021 · 1 home removed · Permit 15 237379 DEM
- Closed
Drains and site services
Drain - Proposal to construct a 2-storey dwelling with integral garage, unfinished basement
Applied Oct 14, 2015 · issued Dec 24, 2015 · completed Mar 5, 2021 · Permit 15 237375 DRN
Committee of Adjustment
No applications to the City's Committee of Adjustment for this address since 2017. That's where an owner asks for a minor variance (a small exception to the zoning by-law) or a consent to divide a lot.
What’s planned nearby
Development sites within 500 m
No rezoning, site plan, subdivision or condominium file open within 500 m, and no pre-construction project on the site.
Neighbours’ Committee of Adjustment files within 250 m
5 Queensgrove Rd · Minor variance
To construct a new two-storey detached dwelling including a rear deck and rear second floor balcony. The existing one storey single detached dwelling will be demolished.
210 m away · filed May 4, 2026 · Approved
9 Haig Ave · Minor variance
To alter the existing two storey detached dwelling by constructing two storey addition with extended porch in the front yard and an extended deck in the rear yard. NOTE: This application was previously deferred at the Committee of Adjustment Hearing on Feburary 11, 2026.
120 m away · filed Jan 5, 2026 · Approved
74 Warden Ave · Minor variance
To permit a new driveway in the front yard.
80 m away · filed Sep 22, 2025 · Deferred
1 Haig Ave · Minor variance
To construct a new three-storey detached dwelling with a secondary suite in the basement. The existing frame shed will be demolished.
110 m away · filed Dec 6, 2024 · Approved
32 Crescentwood Rd · Minor variance
To construct a new three-storey detached building with an integral double garage, front second storey balcony, front third storey rooftop patio, rear basement walkout and rear ground floor deck. The existing one-storey detached dwelling and detached garage will be demolished. There will be a total of two dwelling units on the lot. This application was previously deferred at the March 12, 2025 hearing.
230 m away · filed Dec 5, 2024 · Approved
11 Crescentwood Rd · Minor variance
To demolish the existing 2-storey detached dwelling and construct a new 2-storey detached dwelling. This application was previously deferred at the December 4, 2024 hearing.
70 m away · filed Oct 7, 2024 · Approved
9 Crescentwood Rd · Minor variance
To demolish the existing dwelling and to construct a new two storey dwelling. This application was deferred from the December 4, 2024 hearing.
50 m away · filed Oct 4, 2024 · Approved
11 Crescentwood Rd · Minor variance
To demolish the existing 2-storey detached dwelling and construct a new 2-storey detached dwelling. This item was previously deferred at the July 24, 2024 hearing.
70 m away · filed May 10, 2024 · Refused
From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.