Toronto address · Ward 9, Davenport
631 Gladstone Ave
The City of Toronto has 1 building permit since 2017 on record for this address.
Building permits
Every permit the City lists for this address since 2017, and any still open from before, newest first.
- Closed
Drains and site services · Back water valve (Sewer only)
Back Water Valve and drain repairs.
Applied Dec 12, 2019 · issued Dec 12, 2019 · completed Sep 17, 2025 · Permit 19 260480 DRN
Committee of Adjustment
No applications to the City's Committee of Adjustment for this address since 2017. That's where an owner asks for a minor variance (a small exception to the zoning by-law) or a consent to divide a lot.
What’s planned nearby
Development sites within 500 m
- Approved
- Under review
1141 Bloor Street West, 90 Croatia Street and 980 Dufferin Street
22 storeys · 264 homes · Mixed use
420 m away · Site plan · Under review · filed Feb 27, 2026
- Approved
Neighbours’ Committee of Adjustment files within 250 m
1045 Dufferin St · Minor variance
To construct a new three-storey building (utility (switchgear) facility). There will be two front yard parking spaces. A Site Plan Control application (File Number 25 166590 STE 09 SA) is currently under review.
240 m away · filed Feb 13, 2026 · Approved
91 Salem Ave · Minor variance
To alter the existing two-and-one-half-storey detached dwelling by constructing a new front one-storey addition with stairs, a front basement walkout, and a rear one-storey addition with a wood landing. The existing rear ground floor deck will be maintained and unaltered.
220 m away · filed Oct 23, 2025 · Approved
1081 Dufferin St · Minor variance
To construct a new one-storey detached ancillary building (two-car garage), in the rear yard of the existing two-storey detached dwelling.
140 m away · filed May 20, 2025 · Approved
57 Bartlett Ave · Minor variance
To alter the existing two-storey townhouse dwelling by constructing a rear second storey addition (cantilevered at the rear portion).
170 m away · filed Mar 19, 2025 · Approved
79 Bartlett Ave · Minor variance
To alter the existing two-storey semi-detached dwelling by constructing a rear walkway. Also, to alter the existing one-storey ancillary building (rear detached garage, abutting the laneway) by constructing a complete second storey addition for one laneway suite. There will be a total of two residential dwelling units on this lot (one in the main dwelling and one in the ancillary building).
120 m away · filed Oct 24, 2024 · Approved
1064 Dufferin St · Minor variance
To alter the existing two-and-one-half-storey detached dwelling (duplex) by converting the existing rear one-storey ancillary building (detached garage) into one garden suite. There will be a total of three residential dwelling units on this lot (two units within the dwelling and one unit within the ancillary building).
220 m away · filed Jul 19, 2024 · Approved
1119 Dufferin St · Minor variance
To construct a new three-storey detached dwelling (triplex) with rear decks on the ground, second, and third levels, a front third storey rooftop terrace above the front cantilevered second storey portion of the dwelling, and a front landing with stairs.
110 m away · filed Mar 4, 2024 · Approved
99 Bartlett Ave · Minor variance
To alter the existing two-and-one-half-storey semi-detached dwelling by reconstructing the front stairs, and enclosing the front porch.
100 m away · filed Feb 13, 2024 · Approved
From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.