Toronto address · Ward 11, University-Rosedale
65 Pendrith St
The City of Toronto has 1 building permit since 2017 on record for this address.
Building permits
Every permit the City lists for this address since 2017, and any still open from before, newest first.
- Cancelled
Drains and site services · Back water valve (Sewer only)
Back Water Valve Permit
Applied Feb 23, 2024 · completed Aug 20, 2024 · Permit 24 118210 DRN
Committee of Adjustment
No applications to the City's Committee of Adjustment for this address since 2017. That's where an owner asks for a minor variance (a small exception to the zoning by-law) or a consent to divide a lot.
What’s planned nearby
Development sites within 500 m
No rezoning, site plan, subdivision or condominium file open within 500 m, and no pre-construction project on the site.
Neighbours’ Committee of Adjustment files within 250 m
139 Christie St · Minor variance
To construct a new three-storey detached dwelling (houseplex) with a rear basement walkout, a front ground floor bay window a front ground floor covered garbage storage area and front planter box, a side (north) yard main entrance on the ground floor, the second and third floors of the side (north) portion of the dwelling will be cantilevered with a canopy, three rear platforms (stair landings on all three levels) with rear exterior staircases (leading to all levels). Also, to construct a new rear two-storey detached ancillary building (laneway suite) containing one residential dwelling unit…
250 m away · filed Mar 17, 2026 · Approved
778 Crawford St · Minor variance
To alter the existing two-storey detached dwelling by constructing a rear two-storey addition with basement, and a rear second storey balcony.
230 m away · filed Jan 16, 2026 · Approved
30 Pendrith St · Minor variance
To alter the existing two-storey detached dwelling by extending the rear second storey balcony by reconstructing the rear exterior platform/staircase (leading to the second level). Also, to alter the existing rear one-storey detached ancillary building (garage abutting the laneway) by constructing a complete second storey addition (to contain one laneway suite) with a side (south) exterior platform/staircase to access the second level. The existing ground floor deck (with stairs) on the south side of the ancillary building, will be maintained and unaltered.
110 m away · filed Jan 9, 2026 · Approved
132 Christie St · Minor variance
To construct a two-storey ancillary building (containing a laneway suite) in the rear yard of the property.
210 m away · filed Jun 16, 2025 · Application withdrawn
61 Pendrith St · Minor variance
To alter the existing two-storey detached dwelling by constructing a complete third storey addition, and a rear two-storey addition with a third storey terrace above. Also, to reduce the size of the existing one-storey ancillary building (detached garage in the rear yard, abutting the side (east) laneway).
20 m away · filed Jan 6, 2025 · Approved
76 Garnet Ave · Minor variance
To alter the existing two-storey detached dwelling (duplex) by constructing a front basement walkout, a front covered porch, a rear cantilevered second storey addition above the existing rear one-storey addition and a rear ground floor deck. The existing deck will be demolished. There will be a total of two residential dwelling units on this lot.
250 m away · filed Aug 27, 2024 · Approved
16 Essex St · Minor variance
To construct a swimming pool at the rear of the two-storey detached dwelling.
220 m away · filed Aug 29, 2022 · Approved
45 Pendrith St · Minor variance
To legalize and to maintain the existing two-storey semi-detached dwelling which was not constructed in accordance with OMB Decision Case No. PL160231.
40 m away · filed Mar 4, 2022 · Approved
From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.