The City of Toronto has 400 building permits since 2017 (161 still open) on record for this address.
Building permits
Every permit the City lists for this address since 2017, and any still open from before, newest first.
- Cancelled
Alternative solution
Alternative Solution Application for Deletion of Fire Alarm System Manual Pull Station from Residential Units -For Permit Applications: 19 214057 B01-B48, 19 220156 B01-B68, 19 220516 B01-B44, 19 213470 BLD. Three (3) townhouse and back-to-back stacked townhouse blocks consisting of 160 units, varying in height from 3 to 5 storeys and connected by a one level underground garage.
Applied Oct 26, 2020 · completed Oct 26, 2020 · Permit 20 210950 ALT
- Cancelled
Alternative solution
Alternative Solution Application for Deletion of Fire Alarm System Manual Pull Station from Residential Units -For Permit Applications: 19 214057 B01-B48, 19 220156 B01-B68, 19 220516 B01-B44, 19 213470 BLD. Three (3) townhouse and back-to-back stacked townhouse blocks consisting of 160 units, varying in height from 3 to 5 storeys and connected by a one level underground garage.
Applied Sep 2, 2020 · completed Sep 2, 2020 · Permit 20 188888 ALT
- Cancelled
Alternative solution
Alternative Solution Application for Deletion of Fire Alarm System Manual Pull Station from Residential Units -For Permit Applications: 19 214057 B01-B48, 19 220156 B01-B68, 19 220516 B01-B44, 19 213470 BLD. Three (3) townhouse and back-to-back stacked townhouse blocks consisting of 160 units, varying in height from 3 to 5 storeys and connected by a one level underground garage.
Applied Sep 2, 2020 · completed Nov 12, 2020 · Permit 20 188891 ALT
- Cancelled
Conditional permit · Partial permit - shoring
Conditional Permit - Part Permit - Construct one level underground parking garage for three blocks of townhouse 153 units, Block A,B,C
Applied Jun 30, 2020 · issued Sep 4, 2020 · completed May 17, 2022 · Permit 19 213470 SHO
- Cancelled
Alternative solution
Proposed standpipe in units
Applied Jan 7, 2020 · completed Jan 7, 2020 · Permit 20 101602 ALT
- Cancelled
Alternative solution
Proposed standpipe in units
Applied Jan 7, 2020 · completed Jan 7, 2020 · Permit 20 101601 ALT
- Approved
Alternative solution
Proposed standpipe system in units for all 3 blocks - (fire hose cabinest would be requird to be located in the residential suites) Blocks A, B and C
Applied Jan 7, 2020 · completed Jun 8, 2020 · Permit 20 101594 ALT
- Closed
Drains and site services
Drain - Construct one level underground parking garage for three blocks of townhouse 153 units, Block A,B,C
Applied Dec 4, 2019 · issued Oct 13, 2020 · completed Feb 5, 2026 · Permit 19 213470 DRN
- Closed
Heating and ventilation
HVAC - Construct one level underground parking garage for three blocks of townhouse 153 units, Block A,B,C
Applied Nov 15, 2019 · issued Dec 3, 2020 · completed May 15, 2026 · Permit 19 213470 HVA
- Closed
Plumbing
Plumbing - Construct one level underground parking garage for three blocks of townhouse 153 units, Block A,B,C
Applied Nov 15, 2019 · issued Oct 13, 2020 · completed Feb 5, 2026 · Permit 19 213470 PLB
- Closed
Fire and security upgrade
FS - Sprinkler Shop Drawing - Construct one level underground parking garage for three blocks of townhouse 153 units, Block A,B,C
Applied Nov 12, 2019 · issued Jul 14, 2025 · completed Jul 14, 2025 · Permit 19 213470 FSU
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220516 P15
Show 388 more permits
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P59
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P30
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P50
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P32
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P40
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220516 P33
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P33
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P04
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P39
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P52
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220516 P11
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P13
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220516 P21
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220516 P19
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P48
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P37
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P19
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220516 P25
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220516 P26
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P06
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P27
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P44
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P36
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P16
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P31
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220516 P36
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P58
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P27
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220516 P37
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220516 P39
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220516 P07
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220516 P34
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P02
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P46
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220516 P13
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220516 P40
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P23
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P41
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P26
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P25
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P04
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P34
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P46
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P02
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P67
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P03
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220516 P29
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P19
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 16, 2020 · Permit 19 214057 P01
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P06
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P63
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220516 P17
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P22
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P35
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P13
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220516 P09
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P42
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P17
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P09
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P05
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220516 P32
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220516 P18
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P25
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P18
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P10
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P18
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P11
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220516 P44
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220516 P05
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P33
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220516 P42
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220516 P24
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220516 P43
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P22
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P39
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P49
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220516 P14
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P10
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P56
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P34
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P54
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P57
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220516 P28
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P42
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P26
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P21
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P24
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220516 P06
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P20
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P16
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P62
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P35
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P21
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P65
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P32
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P28
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Nov 16, 2020 · Permit 19 220516 P01
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220516 P27
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P15
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P03
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P43
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P38
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220516 P08
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P45
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P12
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220516 P23
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 16, 2020 · Permit 19 220156 P01
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P07
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P05
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P09
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220516 P22
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220516 P16
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P66
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P36
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220516 P30
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P44
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P55
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220516 P10
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220516 P04
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P08
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P61
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P47
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P40
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P68
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P64
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P07
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P45
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220516 P03
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P12
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220516 P31
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P31
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P38
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P60
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P53
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P14
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P23
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P24
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P51
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P08
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220516 P38
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220516 P12
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P15
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P41
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P17
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P30
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P20
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P28
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 4, 2026 · Permit 19 220156 H21
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 4, 2026 · Permit 19 220156 H16
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 4, 2026 · Permit 19 220156 H17
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 4, 2026 · Permit 19 220156 H18
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 4, 2026 · Permit 19 220156 H19
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 4, 2026 · Permit 19 220156 H20
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Jun 25, 2021 · completed Jun 23, 2026 · Permit 19 220516 H40
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Jun 25, 2021 · completed Jun 23, 2026 · Permit 19 220516 H41
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Jun 25, 2021 · completed Jul 3, 2026 · Permit 19 220516 H42
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Jun 25, 2021 · completed Jul 3, 2026 · Permit 19 220516 H43
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Jun 25, 2021 · completed Jul 3, 2026 · Permit 19 220516 H44
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed May 25, 2026 · Permit 19 214057 H12
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed Jun 2, 2026 · Permit 19 214057 H48
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed May 25, 2026 · Permit 19 214057 H13
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed May 25, 2026 · Permit 19 214057 H14
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed May 25, 2026 · Permit 19 214057 H15
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed May 25, 2026 · Permit 19 214057 H16
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed May 25, 2026 · Permit 19 214057 H17
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed May 25, 2026 · Permit 19 214057 H18
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed May 25, 2026 · Permit 19 214057 H19
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed May 25, 2026 · Permit 19 214057 H20
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed Jun 1, 2026 · Permit 19 214057 H21
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed Jun 1, 2026 · Permit 19 214057 H22
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed Jun 1, 2026 · Permit 19 214057 H23
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 12, 2021 · completed Jun 1, 2026 · Permit 19 214057 H24
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 12, 2021 · completed Jun 1, 2026 · Permit 19 214057 H25
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed Jun 1, 2026 · Permit 19 214057 H26
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed Jun 1, 2026 · Permit 19 214057 H27
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed Jun 1, 2026 · Permit 19 214057 H28
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed Jun 1, 2026 · Permit 19 214057 H29
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed Jun 1, 2026 · Permit 19 214057 H30
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed Jun 1, 2026 · Permit 19 214057 H31
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed Jun 1, 2026 · Permit 19 214057 H32
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed Jun 1, 2026 · Permit 19 214057 H33
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed Jun 2, 2026 · Permit 19 214057 H34
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed Jun 2, 2026 · Permit 19 214057 H35
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed Jun 2, 2026 · Permit 19 214057 H36
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed Jun 2, 2026 · Permit 19 214057 H37
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed Jun 2, 2026 · Permit 19 214057 H38
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed Jun 2, 2026 · Permit 19 214057 H39
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed Jun 2, 2026 · Permit 19 214057 H40
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed Jun 2, 2026 · Permit 19 214057 H41
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 12, 2021 · completed Jun 2, 2026 · Permit 19 214057 H42
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed Jun 2, 2026 · Permit 19 214057 H43
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed Jun 2, 2026 · Permit 19 214057 H44
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed May 21, 2026 · Permit 19 214057 H01
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed May 21, 2026 · Permit 19 214057 H02
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed May 21, 2026 · Permit 19 214057 H03
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed May 22, 2026 · Permit 19 214057 H04
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed May 22, 2026 · Permit 19 214057 H05
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed May 22, 2026 · Permit 19 214057 H06
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed Jun 2, 2026 · Permit 19 214057 H45
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed Jun 2, 2026 · Permit 19 214057 H46
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed Jun 2, 2026 · Permit 19 214057 H47
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed May 22, 2026 · Permit 19 214057 H07
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed May 22, 2026 · Permit 19 214057 H08
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed May 22, 2026 · Permit 19 214057 H09
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed May 22, 2026 · Permit 19 214057 H10
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Apr 9, 2021 · completed May 22, 2026 · Permit 19 214057 H11
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 3, 2026 · Permit 19 220156 H05
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 3, 2026 · Permit 19 220156 H06
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 3, 2026 · Permit 19 220156 H07
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 3, 2026 · Permit 19 220156 H08
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 3, 2026 · Permit 19 220156 H09
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Jun 25, 2021 · completed Jun 19, 2026 · Permit 19 220516 H29
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Jun 25, 2021 · completed Jun 19, 2026 · Permit 19 220516 H30
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Jun 25, 2021 · completed Jun 19, 2026 · Permit 19 220516 H31
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Jun 25, 2021 · completed Jun 19, 2026 · Permit 19 220516 H32
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Jun 25, 2021 · completed Jun 19, 2026 · Permit 19 220516 H33
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Jun 25, 2021 · completed Jun 19, 2026 · Permit 19 220516 H34
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 5, 2026 · Permit 19 220156 H67
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 5, 2026 · Permit 19 220156 H28
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 11, 2026 · Permit 19 220156 H64
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 5, 2026 · Permit 19 220156 H65
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 9, 2026 · Permit 19 220156 H66
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 10, 2026 · Permit 19 220156 H68
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Jun 28, 2021 · completed Jun 16, 2026 · Permit 19 220516 H01
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 5, 2026 · Permit 19 220156 H29
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 5, 2026 · Permit 19 220156 H30
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 5, 2026 · Permit 19 220156 H31
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 3, 2026 · Permit 19 220156 H32
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 5, 2026 · Permit 19 220156 H33
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 4, 2026 · Permit 19 220156 H10
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 4, 2026 · Permit 19 220156 H11
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 4, 2026 · Permit 19 220156 H12
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 3, 2026 · Permit 19 220156 H13
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 4, 2026 · Permit 19 220156 H14
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Jun 25, 2021 · completed Jun 16, 2026 · Permit 19 220516 H02
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Jun 25, 2021 · completed Jun 16, 2026 · Permit 19 220516 H03
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Jun 25, 2021 · completed Jun 16, 2026 · Permit 19 220516 H04
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Jun 25, 2021 · completed Jun 16, 2026 · Permit 19 220516 H05
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Jun 25, 2021 · completed Jun 16, 2026 · Permit 19 220516 H06
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 5, 2026 · Permit 19 220156 H34
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 9, 2026 · Permit 19 220156 H35
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 9, 2026 · Permit 19 220156 H36
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 5, 2026 · Permit 19 220156 H37
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 9, 2026 · Permit 19 220156 H38
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 9, 2026 · Permit 19 220156 H39
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 4, 2026 · Permit 19 220156 H15
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Jun 25, 2021 · completed Jun 22, 2026 · Permit 19 220516 H35
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Jun 25, 2021 · completed Jun 22, 2026 · Permit 19 220516 H36
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Jun 25, 2021 · completed Jun 22, 2026 · Permit 19 220516 H37
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Jun 25, 2021 · completed Jun 22, 2026 · Permit 19 220516 H38
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Jun 25, 2021 · completed Jun 23, 2026 · Permit 19 220516 H39
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 9, 2026 · Permit 19 220156 H40
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 5, 2026 · Permit 19 220156 H41
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 9, 2026 · Permit 19 220156 H42
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 9, 2026 · Permit 19 220156 H43
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 10, 2026 · Permit 19 220156 H44
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 10, 2026 · Permit 19 220156 H45
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Jun 25, 2021 · completed Jun 16, 2026 · Permit 19 220516 H07
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Jun 25, 2021 · completed Jun 16, 2026 · Permit 19 220516 H08
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Jun 25, 2021 · completed Jun 16, 2026 · Permit 19 220516 H09
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Jun 25, 2021 · completed Jun 16, 2026 · Permit 19 220516 H10
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Jun 25, 2021 · completed Jun 16, 2026 · Permit 19 220516 H11
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Jun 25, 2021 · completed Jun 17, 2026 · Permit 19 220516 H12
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Jun 25, 2021 · completed Jun 17, 2026 · Permit 19 220516 H13
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Jun 25, 2021 · completed Jun 17, 2026 · Permit 19 220516 H14
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Jun 25, 2021 · completed Jun 17, 2026 · Permit 19 220516 H15
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Jun 25, 2021 · completed Jun 17, 2026 · Permit 19 220516 H16
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Jun 25, 2021 · completed Jun 17, 2026 · Permit 19 220516 H17
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 10, 2026 · Permit 19 220156 H46
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 10, 2026 · Permit 19 220156 H47
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 10, 2026 · Permit 19 220156 H48
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 10, 2026 · Permit 19 220156 H49
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 10, 2026 · Permit 19 220156 H50
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 10, 2026 · Permit 19 220156 H51
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Jun 25, 2021 · completed Jun 17, 2026 · Permit 19 220516 H18
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Jun 25, 2021 · completed Jun 17, 2026 · Permit 19 220516 H19
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Jun 25, 2021 · completed Jun 17, 2026 · Permit 19 220516 H20
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Jun 25, 2021 · completed Jun 17, 2026 · Permit 19 220516 H21
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Jun 25, 2021 · completed Jun 17, 2026 · Permit 19 220516 H22
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Jun 25, 2021 · completed Jun 18, 2026 · Permit 19 220516 H23
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 11, 2026 · Permit 19 220156 H52
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 11, 2026 · Permit 19 220156 H53
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 11, 2026 · Permit 19 220156 H54
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 11, 2026 · Permit 19 220156 H55
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 4, 2026 · Permit 19 220156 H56
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 11, 2026 · Permit 19 220156 H57
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 19, 2021 · completed Jun 3, 2026 · Permit 19 220156 H01
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 3, 2026 · Permit 19 220156 H02
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 3, 2026 · Permit 19 220156 H03
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Jun 25, 2021 · completed Jun 18, 2026 · Permit 19 220516 H24
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Jun 25, 2021 · completed Jun 18, 2026 · Permit 19 220516 H25
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Jun 25, 2021 · completed Jun 19, 2026 · Permit 19 220516 H26
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Jun 25, 2021 · completed Jun 17, 2026 · Permit 19 220516 H27
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Jun 25, 2021 · completed Jun 19, 2026 · Permit 19 220516 H28
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 3, 2026 · Permit 19 220156 H22
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 3, 2026 · Permit 19 220156 H23
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 5, 2026 · Permit 19 220156 H24
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 3, 2026 · Permit 19 220156 H25
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 5, 2026 · Permit 19 220156 H26
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 5, 2026 · Permit 19 220156 H27
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 5, 2026 · Permit 19 220156 H58
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 11, 2026 · Permit 19 220156 H59
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 11, 2026 · Permit 19 220156 H60
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 11, 2026 · Permit 19 220156 H61
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 11, 2026 · Permit 19 220156 H62
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 11, 2026 · Permit 19 220156 H63
- Closed
Heating and ventilation
HVAC - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Apr 14, 2021 · completed Jun 3, 2026 · Permit 19 220156 H04
- Closed
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · completed Nov 16, 2023 · Permit 19 220156 P29
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P14
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P48
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220516 P41
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220516 P35
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220516 P02
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P47
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P11
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P43
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK A -
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 214057 P29
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220156 P37
- Inspections under way
Plumbing
Plumbing - To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 18, 2019 · issued Nov 2, 2020 · Permit 19 220516 P20
- Approved
Alternative solution
Alternative Solution - Fire and Safety requirements to Part 3 of the 2012 OBC requirements- provide a standpipe and hose system in the townhouse blocks (A, B, C)- floor/roof fire seperation construction - exiting/egress for the North facing four storey non-stacked townhouses suites- exit exposure condition at the exterior stairsRefet to attached Evaluation of Alternative Solution form
Applied Sep 17, 2019 · completed Dec 13, 2019 · Permit 19 222889 ALT
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 13, 2019 · issued Oct 30, 2020 · completed Jul 16, 2026 · 1 home added · Permit 19 220516 B04
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 13, 2019 · issued Oct 30, 2020 · completed Jul 16, 2026 · 1 home added · Permit 19 220516 B05
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 13, 2019 · issued Oct 30, 2020 · completed Jul 16, 2026 · 1 home added · Permit 19 220516 B06
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 13, 2019 · issued Oct 30, 2020 · completed Jul 17, 2026 · 1 home added · Permit 19 220516 B07
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 13, 2019 · issued Oct 30, 2020 · completed Jul 17, 2026 · 1 home added · Permit 19 220516 B08
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 13, 2019 · issued Oct 30, 2020 · completed Jul 17, 2026 · 1 home added · Permit 19 220516 B09
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 13, 2019 · issued Oct 30, 2020 · completed Jul 20, 2026 · 1 home added · Permit 19 220516 B10
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 13, 2019 · issued Oct 30, 2020 · completed Jul 20, 2026 · 1 home added · Permit 19 220516 B11
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 13, 2019 · issued Oct 30, 2020 · completed Jul 20, 2026 · 1 home added · Permit 19 220516 B12
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 13, 2019 · issued Oct 30, 2020 · completed Jul 20, 2026 · 1 home added · Permit 19 220516 B13
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 13, 2019 · issued Oct 30, 2020 · completed Jul 20, 2026 · 1 home added · Permit 19 220516 B14
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 13, 2019 · issued Oct 30, 2020 · completed Jul 20, 2026 · 1 home added · Permit 19 220516 B15
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 13, 2019 · issued Oct 30, 2020 · completed Jul 16, 2026 · 1 home added · Permit 19 220516 B02
- Closed
New house · New building - lead
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 13, 2019 · issued Oct 30, 2020 · completed Jul 16, 2026 · 1 home added · Permit 19 220516 B01
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 13, 2019 · issued Oct 30, 2020 · completed Aug 5, 2026 · 1 home added · Permit 19 220516 B44
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 13, 2019 · issued Oct 30, 2020 · completed Aug 5, 2026 · 1 home added · Permit 19 220516 B43
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 13, 2019 · issued Oct 30, 2020 · completed Aug 5, 2026 · 1 home added · Permit 19 220516 B42
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 13, 2019 · issued Oct 30, 2020 · completed Aug 5, 2026 · 1 home added · Permit 19 220516 B41
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 13, 2019 · issued Oct 30, 2020 · completed Aug 5, 2026 · 1 home added · Permit 19 220516 B40
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 13, 2019 · issued Oct 30, 2020 · completed Aug 5, 2026 · 1 home added · Permit 19 220516 B39
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 13, 2019 · issued Oct 30, 2020 · completed Aug 4, 2026 · 1 home added · Permit 19 220516 B38
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 13, 2019 · issued Oct 30, 2020 · completed Aug 4, 2026 · 1 home added · Permit 19 220516 B37
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 13, 2019 · issued Oct 30, 2020 · completed Aug 4, 2026 · 1 home added · Permit 19 220516 B36
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 13, 2019 · issued Oct 30, 2020 · completed Aug 4, 2026 · 1 home added · Permit 19 220516 B35
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 13, 2019 · issued Oct 30, 2020 · completed Aug 4, 2026 · 1 home added · Permit 19 220516 B34
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 13, 2019 · issued Oct 30, 2020 · completed Jul 29, 2026 · 1 home added · Permit 19 220516 B33
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 13, 2019 · issued Oct 30, 2020 · completed Jul 29, 2026 · 1 home added · Permit 19 220516 B32
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 13, 2019 · issued Oct 30, 2020 · completed Jul 22, 2026 · 1 home added · Permit 19 220516 B22
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 13, 2019 · issued Oct 30, 2020 · completed Jul 23, 2026 · 1 home added · Permit 19 220516 B23
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 13, 2019 · issued Oct 30, 2020 · completed Jul 23, 2026 · 1 home added · Permit 19 220516 B24
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 13, 2019 · issued Oct 30, 2020 · completed Jul 23, 2026 · 1 home added · Permit 19 220516 B25
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 13, 2019 · issued Oct 30, 2020 · completed Jul 28, 2026 · 1 home added · Permit 19 220516 B26
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 13, 2019 · issued Oct 30, 2020 · completed Jul 28, 2026 · 1 home added · Permit 19 220516 B27
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 13, 2019 · issued Oct 30, 2020 · completed Jul 28, 2026 · 1 home added · Permit 19 220516 B28
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 13, 2019 · issued Oct 30, 2020 · completed Jul 28, 2026 · 1 home added · Permit 19 220516 B29
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 13, 2019 · issued Oct 30, 2020 · completed Jul 20, 2026 · 1 home added · Permit 19 220516 B16
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 13, 2019 · issued Oct 30, 2020 · completed Jul 21, 2026 · 1 home added · Permit 19 220516 B17
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 13, 2019 · issued Oct 30, 2020 · completed Jul 21, 2026 · 1 home added · Permit 19 220516 B18
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 13, 2019 · issued Oct 30, 2020 · completed Jul 22, 2026 · 1 home added · Permit 19 220516 B19
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 13, 2019 · issued Oct 30, 2020 · completed Jul 22, 2026 · 1 home added · Permit 19 220516 B20
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 13, 2019 · issued Oct 30, 2020 · completed Jul 22, 2026 · 1 home added · Permit 19 220516 B21
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 13, 2019 · issued Oct 30, 2020 · completed Jul 29, 2026 · 1 home added · Permit 19 220516 B31
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 13, 2019 · issued Oct 30, 2020 · completed Jul 16, 2026 · 1 home added · Permit 19 220516 B03
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK C
Applied Sep 13, 2019 · issued Oct 30, 2020 · completed Jul 28, 2026 · 1 home added · Permit 19 220516 B30
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 12, 2019 · issued Oct 30, 2020 · completed Jul 14, 2026 · 1 home added · Permit 19 220156 B64
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 12, 2019 · issued Oct 30, 2020 · completed Jul 14, 2026 · 1 home added · Permit 19 220156 B65
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 12, 2019 · issued Oct 30, 2020 · completed Jul 14, 2026 · 1 home added · Permit 19 220156 B66
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 12, 2019 · issued Oct 30, 2020 · completed Jul 14, 2026 · 1 home added · Permit 19 220156 B67
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 12, 2019 · issued Oct 30, 2020 · completed Jul 14, 2026 · 1 home added · Permit 19 220156 B68
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 12, 2019 · issued Oct 30, 2020 · completed Jul 2, 2026 · 1 home added · Permit 19 220156 B10
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 12, 2019 · issued Oct 30, 2020 · completed Jul 6, 2026 · 1 home added · Permit 19 220156 B20
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 12, 2019 · issued Oct 30, 2020 · completed Jul 6, 2026 · 1 home added · Permit 19 220156 B21
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 12, 2019 · issued Oct 30, 2020 · completed Jul 6, 2026 · 1 home added · Permit 19 220156 B22
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 12, 2019 · issued Oct 30, 2020 · completed Jul 6, 2026 · 1 home added · Permit 19 220156 B23
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 12, 2019 · issued Oct 30, 2020 · completed Jul 6, 2026 · 1 home added · Permit 19 220156 B24
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 12, 2019 · issued Oct 30, 2020 · completed Jul 7, 2026 · 1 home added · Permit 19 220156 B25
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 12, 2019 · issued Oct 30, 2020 · completed Jul 7, 2026 · 1 home added · Permit 19 220156 B26
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 12, 2019 · issued Oct 30, 2020 · completed Jul 7, 2026 · 1 home added · Permit 19 220156 B27
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 12, 2019 · issued Oct 30, 2020 · completed Jul 7, 2026 · 1 home added · Permit 19 220156 B28
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 12, 2019 · issued Oct 30, 2020 · completed Jul 7, 2026 · 1 home added · Permit 19 220156 B29
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 12, 2019 · issued Oct 30, 2020 · completed Jul 7, 2026 · 1 home added · Permit 19 220156 B30
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 12, 2019 · issued Oct 30, 2020 · completed Jul 7, 2026 · 1 home added · Permit 19 220156 B31
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 12, 2019 · issued Oct 30, 2020 · completed Jul 7, 2026 · 1 home added · Permit 19 220156 B32
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 12, 2019 · issued Oct 30, 2020 · completed Jul 7, 2026 · 1 home added · Permit 19 220156 B33
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 12, 2019 · issued Oct 30, 2020 · completed Jul 7, 2026 · 1 home added · Permit 19 220156 B34
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 12, 2019 · issued Oct 30, 2020 · completed Jul 7, 2026 · 1 home added · Permit 19 220156 B35
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 12, 2019 · issued Oct 30, 2020 · completed Jul 7, 2026 · 1 home added · Permit 19 220156 B36
- Closed
New house · New building
To construct three blocks of back to back stacked townhouses with connected one level underground parking garage - BLOCK B
Applied Sep 12, 2019 · issued Oct 30, 2020 · completed Jul 7, 2026 · 1 home added · Permit 19 220156 B37
Committee of Adjustment
No applications to the City's Committee of Adjustment for this address since 2017. That's where an owner asks for a minor variance (a small exception to the zoning by-law) or a consent to divide a lot.
What’s planned nearby
Development sites within 500 m
- Under review
11 storeys · 71 homes · Residential
150 m away · Rezoning · Under review · filed Jun 16, 2022
- Approved
177-181 Cocksfield Avenue and 824 Sheppard Avenue West
14 storeys · Mixed use
190 m away · Site plan · Approved · filed Jul 21, 2021
- Under review
9 storeys · 70 homes · Mixed use
490 m away · Site plan · Under review · filed Jul 12, 2022
Neighbours’ Committee of Adjustment files within 250 m
21 Norcross Rd · Minor variance
To construct a new two-storey detached dwelling with a covered front porch and rear deck.
160 m away · filed Jul 24, 2026 · Approved
824 Sheppard Ave W · Minor variance
To alter the development standards (as approved under Site Specific Zoning By-law 320-2022) for the 12-storey mixed use building including reducing the residential and visitor parking spaces, bicycle parking space rates, indoor amenity space and the first floor height.
140 m away · filed Nov 19, 2025 · Approved
28 Norcross Rd · Minor variance
To permit front yard parking.
170 m away · filed Nov 4, 2025 · Approved
216 Cocksfield Ave · Minor variance
To construct a new 2 storey detached dwelling with a rear deck and walk-out.
230 m away · filed Mar 27, 2025 · Approved
192 Cocksfield Ave · Minor variance
To permit the reduction of the number of required lawful parking spaces for the existing dwelling.
210 m away · filed Sep 5, 2024 · Approved
28 Dunsmore Gdns · Minor variance
To construct a first floor addition in the front, second floor addition, and interior alterations.
230 m away · filed Oct 18, 2021 · Approved
19 Norcross Rd · Minor variance
To construct a new dwelling.
150 m away · filed Dec 22, 2020 · Approved
28 Dunsmore Gdns · Minor variance
To construct a detached garage in the rear yard of the subject property.
230 m away · filed Oct 2, 2020 · Approved
From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.