The City of Toronto has 23 building permits since 2017 (6 still open) on record for this address.
Building permits
Every permit the City lists for this address since 2017, and any still open from before, newest first.
- Cancelled
Alternative solution
This alternative solution proposal is being submitted to determine if the City of Toronto will permit the use of FM Global design standards to protect the AutoStore System where NFPA 13 is silent.
Applied Dec 16, 2022 · completed Apr 3, 2025 · Permit 22 240303 ALT
- Approved
Alternative solution
Alterative solution proposal is being submitted to determine if the City of Toronto will permit the use of FM Global design standards to protect hanging garment storage where NFPA 13 is silent
Applied Oct 24, 2022 · completed Jan 23, 2023 · Permit 22 220918 ALT
- Inspections under way
Addition or alteration · Interior alterations
Interior alteration for replacement of existing storage system to new shelf and rack system.
Applied Oct 13, 2022 · issued Jan 27, 2023 · Permit 22 216536 BLD
- Cancelled
Heating and ventilation
HVAC - Interior alteration to accomodate Automated storage system within an existing warehouse space. No exterior work, no change of use, exiting or occupant load.New Roof top unit added along with structural supports. Sprinklers adjustment for automated storage area.
Applied Sep 12, 2022 · completed Apr 3, 2025 · Permit 22 202207 HVA
- Cancelled
Addition or alteration · Interior alterations
Interior alteration to accomodate Automated storage system within an existing warehouse space. No exterior work, no change of use, exiting or occupant load.New Roof top unit added along with structural supports. Sprinklers adjustment for automated storage area.
Applied Sep 12, 2022 · completed Apr 3, 2025 · Permit 22 202207 BLD
- Cancelled
Heating and ventilation
HVAC - Interior construction for adding mezzanine level in current 48" high ceiling warehouse - Hudson Bay Warehouse, Scope of work mechanical and electrical, sprinklers
Applied Sep 21, 2021 · completed Oct 14, 2021 · Permit 21 215861 HVA
- Cancelled
Alternative solution
Alternative Solution proposal is being submitted to determine if the City of Toronto will permit the use of FM Global design standards to protect hanging garment storage where NFPA 13 is silent.
Applied Sep 21, 2021 · completed Oct 14, 2021 · Permit 21 215877 ALT
- Cancelled
Addition or alteration · Addition(s)
Interior construction for adding mezzanine level in current 48" high ceiling warehouse - Hudson Bay Warehouse, Scope of work mechanical and electrical, sprinklers
Applied Sep 21, 2021 · completed Oct 14, 2021 · Permit 21 215861 BLD
- Closed
Fire and security upgrade · Sprinklers
upgrade sprinkler system
Applied Sep 1, 2021 · issued Sep 9, 2021 · completed Mar 29, 2023 · Permit 21 207128 FSU
- Inspections under way
Addition or alteration · Interior alterations
Proposal for interior alterations "Hudson's Bay Company"
Applied Apr 29, 2021 · issued Jul 21, 2021 · Permit 21 147971 BLD
- Inspections under way
Plumbing
Plumbing - Proposal for interior alterations "Hudson's Bay Company"
Applied Apr 29, 2021 · issued Jul 21, 2021 · Permit 21 147971 PLB
- Inspections under way
Heating and ventilation
HVAC - Proposal for interior alterations "Hudson's Bay Company"
Applied Apr 29, 2021 · issued Jul 21, 2021 · Permit 21 147971 HVA
Show 11 more permits
- Application on hold
Fire and security upgrade
FS - Sprinkler Shop Drawing - Proposed interior alterations in building 4 south east corner for cafeteria.
Applied Sep 1, 2017 · Permit 17 202182 FSU
- Closed
Addition or alteration · Interior alterations
Proposed interior alterations in building 4 south east corner for cafeteria.
Applied Jul 20, 2017 · issued Sep 5, 2017 · completed Feb 26, 2018 · Permit 17 202182 BLD
- Closed
Heating and ventilation
HVAC - Proposed interior alterations in building 4 south east corner for cafeteria.
Applied Jul 20, 2017 · issued Sep 12, 2017 · completed Feb 27, 2018 · Permit 17 202182 HVA
- Closed
Plumbing
Plumbing - Proposed interior alterations in building 4 south east corner for cafeteria.
Applied Jul 20, 2017 · issued Sep 7, 2017 · completed Feb 27, 2018 · Permit 17 202182 PLB
- Closed
Fire and security upgrade · Fire alarm
Fire alarm to 1 building, areas 2 -6 and 1storey
Applied Jul 4, 2017 · issued Aug 2, 2017 · completed Sep 18, 2018 · Permit 17 191589 FSU
- Cancelled
Fire and security upgrade
FS - Sprinkler Shop Drawing - interior alterations to create employee break room, w/c, enlarge doors
Applied Dec 7, 2016 · completed Feb 3, 2017 · Permit 16 250522 FSU
- Cancelled
Heating and ventilation
HVAC - interior alterations to create employee break room, w/c, enlarge doors
Applied Nov 14, 2016 · issued Dec 12, 2016 · completed Feb 3, 2017 · Permit 16 250522 HVA
- Cancelled
Addition or alteration · Interior alterations
interior alterations to create employee break room, w/c, enlarge doors
Applied Nov 14, 2016 · issued Dec 12, 2016 · completed Feb 3, 2017 · Permit 16 250522 BLD
- Cancelled
Plumbing
Plumbing - interior alterations to create employee break room, w/c, enlarge doors
Applied Nov 14, 2016 · issued Dec 12, 2016 · completed Feb 3, 2017 · Permit 16 250522 PLB
- Closed
Addition or alteration · Other
Proposal to replace existing rooftop units and add new rooftop units along with structural upgrades for an existing warehouse. Application to be read in conjunction with 16-194785-MSA
Applied Aug 29, 2016 · issued Nov 21, 2016 · completed Jun 2, 2017 · Permit 16 214680 BLD
- Closed
Heating and ventilation · Other
Replace existing rooftop AC units and make up air heater
Applied Jul 21, 2016 · issued Sep 9, 2016 · completed Jun 1, 2017 · Permit 16 194785 MSA
Committee of Adjustment
No applications to the City's Committee of Adjustment for this address since 2017. That's where an owner asks for a minor variance (a small exception to the zoning by-law) or a consent to divide a lot.
What’s planned nearby
Development sites within 500 m
- Submitted
46 storeys · 1,881 homes · Mixed use
430 m away · Rezoning · Submitted · filed Jul 7, 2025
- Under review
46 storeys · Not stated in the file
430 m away · Subdivision · Under review · filed Jun 30, 2025
Neighbours’ Committee of Adjustment files within 250 m
None on file since 2017.
From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.