The City of Toronto has 4 building permits since 2017 and 3 Committee of Adjustment files on record for this address.

Building permits

Every permit the City lists for this address since 2017, and any still open from before, newest first.

  • Heating and ventilation

    HVAC - Construction of a new 2 storey single family dwelling with integral garage and finished basement

    Applied May 11, 2017 · issued Jun 21, 2017 · completed Aug 22, 2018 · Permit 17 158139 HVA

    Closed
  • Plumbing

    Plumbing - Construction of a new 2 storey single family dwelling with integral garage and finished basement

    Applied May 11, 2017 · issued Jun 21, 2017 · completed Aug 22, 2018 · Permit 17 158139 PLB

    Closed
  • New house · New building

    Construction of a new 3storey single family dwelling with integral garage.

    Applied May 11, 2017 · issued Jun 21, 2017 · completed Aug 22, 2018 · 1 home added · Permit 17 158139 BLD

    Closed
  • Drains and site services

    Drain - Construction of a new 2 storey single family dwelling with integral garage and finished basement

    Applied May 11, 2017 · issued Jun 21, 2017 · completed Aug 22, 2018 · Permit 17 158139 DRN

    Closed

Committee of Adjustment

This address's applications to the City's Committee of Adjustment since 2017, and any still open. A minor variance asks for a small exception to the zoning by-law, such as a little more height or a smaller setback; a consent divides a lot or grants an easement.

  • Consent · Sever lot

    To obtain consent to sever the property into two residential lots.

    Decision: Approved (hearing Jan 12, 2017)

    Filed Oct 12, 2016 · File B0077/16EYK

    Closed
  • Minor variance · New R building

    To construct a new detached dwelling with an attached garage.

    Decision: Approved (hearing Jan 12, 2017)

    Filed Oct 12, 2016 · File A0803/16EYK

    Closed
  • Minor variance · New R building

    To maintain the existing detached dwelling.

    Decision: Approved (hearing Jan 12, 2017)

    Filed Oct 12, 2016 · File A0804/16EYK

    Closed

What’s planned nearby

Development sites within 500 m

Neighbours’ Committee of Adjustment files within 250 m

  • 73 Tenth St · Minor variance

    To construct a one-storey rear addition and a new rear deck.

    110 m away · filed Dec 2, 2025 · Approved

  • 115 Tenth St · Minor variance

    To legalize and to maintain an enclosed second storey front platform, to construct a second storey rear addition, and to convert the existing dwelling into a duplex.

    70 m away · filed Oct 14, 2025 · Approved

  • 46 Tenth St · Minor variance

    To maintain the existing front porch that is currently uncer construction.

    230 m away · filed Sep 26, 2025 · Approved

  • 84 Tenth St · Minor variance

    To construct a second and third storey addition above the existing dwelling.

    110 m away · filed Apr 29, 2025 · Approved

  • 100 Tenth St · Minor variance

    To construct a one-storey vestibule addition along the front wall of the existing place of worship to accommodate an elevator.

    100 m away · filed Dec 4, 2024 · Approved

  • 69 Tenth St · Minor variance

    To construct a two-storey rear addition including a deck in the rear yard.

    130 m away · filed Aug 9, 2024 · Approved

  • 72 Eighth St · Minor variance

    To construct a new detached garage in the rear yard.

    180 m away · filed Dec 21, 2023 · Approved

  • 46 Tenth St · Minor variance

    To construct a second storey addition above the existing dwelling and to legalize and to maintain a detached garage in the rear yard currently under construction.

    230 m away · filed Nov 6, 2023 · Approved

Everything planned in Etobicoke-Lakeshore

From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.