- Closed
Addition or alteration · Other
New wall mounted guardrails at roof level of Toronto Transit Commission's Harbourfront Substation Maintenance acess
Applied Sep 13, 2021 · issued Sep 30, 2021 · completed Feb 8, 2024 · Permit 21 211771 BLD
Committee of Adjustment
No applications to the City's Committee of Adjustment for this address since 2017. That's where an owner asks for a minor variance (a small exception to the zoning by-law) or a consent to divide a lot.
What’s planned nearby
Development sites within 500 m
- Under review
49 storeys · Mixed use
160 m away · Rezoning · Under review · filed Oct 18, 2024
- Under review
49 storeys · Mixed use
160 m away · Site plan · Under review · filed Oct 18, 2024
- Under review
72 storeys · 7,986 homes · Mixed use
490 m away · Rezoning · Under review · filed May 3, 2022
Neighbours’ Committee of Adjustment files within 250 m
350 Queens Quay W · Minor variance
To alter the development standards (as approved under Site Specific Zoning By-law 493-2024) for the 21-storey mixed-use building (located at the northwest corner of the lot, municipally known as 396 Queens Quay West) by increasing the height of the mechanical penthouse, reducing the width of 32 parking spaces, and reducing the indoor amenity space (which will be used for storage space for outdoor furniture).
210 m away · filed Apr 29, 2026 · Approved
350 Queens Quay W · Minor variance
To convert the existing commercial space (located on the first floor lobby, and second levels of the building, municipally known as 350 Queens Quay West) into a hotel use, and to expand the permitted hotel use areas (on the second level of the building, municipally known as 390 Queens Quay West). Also, to alter the existing building municipally known as 396 Queens Quay West, by constructing a seventh level shaft on the roof area.
210 m away · filed Jan 20, 2025 · Approved
From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.