The City of Toronto has 5 building permits since 2017 (4 still open) on record for this address.
Building permits
Every permit the City lists for this address since 2017, and any still open from before, newest first.
- Revision issued
Addition or alteration · Other
Revision 01 - to change to ELS designProposal to replace existing emergency diesel generator with new natural gas generator
Applied Aug 22, 2023 · issued Oct 31, 2023 · Permit 21 112911 BLD (revision 01)
- Cancelled
Addition or alteration · Other
Toronto Hydro is decomissioning a vault and ducts on Union Station property and would like approval to install new ducts and secondary cable to re-supply the TTC streetcar loop.
Applied Jan 17, 2022 · completed Jan 26, 2022 · Permit 22 104782 BLD
- Permit issued
Plumbing
Plumbing - Proposal to replace existing emergency diesel generator with new natural gas generator
Applied Feb 4, 2021 · issued Dec 2, 2021 · Permit 21 112911 PLB
- Permit issued
Heating and ventilation
HVAC - Proposal to replace existing emergency diesel generator with new natural gas generator
Applied Feb 4, 2021 · issued Dec 2, 2021 · Permit 21 112911 HVA
- Inspections under way
Addition or alteration · Other
Proposal to replace existing emergency diesel generator with new natural gas generator
Applied Feb 4, 2021 · issued Dec 2, 2021 · Permit 21 112911 BLD
Committee of Adjustment
No applications to the City's Committee of Adjustment for this address since 2017. That's where an owner asks for a minor variance (a small exception to the zoning by-law) or a consent to divide a lot.
What’s planned nearby
Development sites within 500 m
- Approved
- Under appeal
40 storeys · 480 homes · Mixed use
160 m away · Site plan · Under appeal · filed Aug 9, 2023
- Under review
187-199 Bay Street, 18-30 Wellington Street West and 3 other streets
64 storeys · Residential
270 m away · Site plan · Under review · filed Aug 26, 2021
- Under review
65 storeys · 649 homes · Mixed use
310 m away · Site plan · Under review · filed Apr 7, 2025
- Under review
60 storeys · 256 homes · Mixed use
320 m away · Condominium · Under review · filed Nov 8, 2021
- Under review
68 storeys · 836 homes · Residential
340 m away · Rezoning · Under review · filed Oct 21, 2024
Neighbours’ Committee of Adjustment files within 250 m
71 Front St W · Minor variance
To alter the existing Union Station (railway station) by constructing a new South Platform, Tracks Q and R, Concourse Extension from York Street to Bay Street, and Single Canopy Structure.
110 m away · filed Dec 12, 2022 · Approved
200 Bay St · Minor variance
To expand the existing mezzanine floor located on the 12 ½ floor level of the North Tower within the existing 26-storey commercial office building to provide additional office space.
120 m away · filed Feb 5, 2020 · Application withdrawn
141 Bay St · Minor variance
To alter the development plan approved under Site Specific By-Law 1104-2016 permitting the construction of a 50 storey office building with a seven-storey retail podium by altering the building envelope, podium and parapet height, mechanical penthouse height and roof coverage, parking space quantity and size, and the P1 level vehicular ramp.
110 m away · filed Oct 31, 2019 · Approved
From the City of Toronto’s open data: building permits (active, and cleared since 2017), Committee of Adjustment applications and address points, this record updated Sep 29, 2026, and the development sites from its Development Applications data. Contains information licensed under the Open Government Licence – Toronto. Construction cost estimates and contractors’ names are left out on purpose, and nothing here names an owner.